BEAR (WMEC 270A) UPDD AJW 26R2.pdf
PDF 1 MB Posted
- Attached to
- DRY DOCK USCG BEAR FY26 UPDD Federal contract opportunity
- Solicitation number
- 70Z08026QMECP0008
About this file
USCGC BEAR (WMEC-901) Specification for Unplanned Drydock Repairs FY2026
This document is a Performance Work Statement (Specification) for unplanned drydock repairs to the USCGC BEAR (WMEC-270A), a 270-foot Medium Endurance Cutter, during fiscal year 2026. The specification is organized into three primary work items: (1) Tanks, Ballast, Repair and Preserve 100 Percent; (2) Drydock; and (3) Temporary Services, Provide - Cutter. The contracting entity is the United States Coast Guard's Surface Forces Logistics Center.
Work Item 1 requires the contractor to repair and preserve three ballast tanks (4-228-1-W, 4-228-2-W, and 4-242-0-W) with total capacity of approximately 9,000 gallons. The contractor must perform 500 ultrasonic thickness measurements, conduct pit-depth measurements, crop and renew approximately 50 square feet of steel plating and 80 linear feet of internal structure across the three tanks, renew manhole covers and internal ladders/sounding tubes, and apply complete preservation coatings to 100% of internal surfaces using SFLC Standard Specification 6310 systems. Critical Inspection Reports must be submitted within the first 25% of contract performance. Work Item 2 covers drydocking and undocking operations in accordance with SFLC Standard Specification 8634, including provision of pre-award calculations, blocking arrangements, and underwater hull cleaning via high-pressure fresh water wash (3,500-7,000 psi). Work Item 3 specifies temporary services including parking, electrical power (400A/450V, 3-phase), potable water (5,000 gallons/day at 40 psig), cooling water, firemain system access, hazardous waste disposal (4,000 gallons bilge water), refuse disposal, and heavy lift equipment for 48 hours. Government-furnished property limited to one transducer cover plate (PN: FL-184-002, DET 15-E, estimated cost $50.00, loaned and returnable). All work must comply with SFLC Standard Specifications 0000, 0740, 6310, 8634, and 8635; applicable Coast Guard drawings and publications; and relevant federal regulations including CFR Title 29 Part 1915 (OSHA shipyard employment standards).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 70Z08026QMECP00080005_A00005_BEAR DD.pdf | ||
| BEAR FY26 UPDD AMENDMENT 70Z08026QMECP00080004.pdf | ||
| BEAR FY26 UPDD AMENDMENT 70Z08026QMECP00080003.pdf | ||
| 70Z08026QMECP0008-0002_CGC BEAR FY26 UPDD_Attachment 5.pdf | ||
| 70Z08026QMECP0008-0002_CGC BEAR FY26 UPDD Amendment 002 (KO Signed).pdf | ||
| 70Z08026QMECP0008-0002_CGC BEAR FY26 UPDD_Attachment 4.pdf | ||
| 70Z08026QMECP0008-0001_CGC BEAR FY26 UPDD Amendment 0001.pdf | ||
| 70Z08026QMECP0008-0001_CGC BEAR FY26 UPDD Attachment 3.pdf | ||
| 70Z08026QMECP0008_Solicitation_CGC BEAR FY26 UPDD.pdf | ||
| BLANK SCHEDULE CGC ESCANABA FY26 DD.xls | XLS spreadsheet | |
| SOW_CGC BEAR FY26 DD.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC BEAR (WMEC 901)
SPECIFICATION FOR UNPLANNED DRYDOCK REPAIRS
FY2026
Developed By: Allison J Waters
(Rev-2, 27 March 2026)
USCGC BEAR (WMEC-270A) UNPLANNED AVAILABILITY FY2026
ii (Rev-2)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: Tanks, Ballast, Repair and Preserve 100 Percent WORK ITEM 2: Drydock WORK ITEM 3: Temporary Services, Provide - Cutter iii (Rev-2)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
19 FEB 2026 1 1
Modified paragraph 3.4 to update structural repair areas.
Modified paragraphs 3.1.1 and 3.4.1 to require a CIR for the UT measurements. Added note regarding retention of manhole covers. Added paragraph 3.9. Added multiple drawing references to Section 2. Updated Consolidated
List of References and Consolidated List of Critical
Inspection Items to reflect changes within Work Item #1.
27 MAR 2026 2 1 Removed EDG and steering system as interferences. Modified paragraph 3.4.3 repair area. Added reference photos in Section 4.
27 MAR 2026 2 3 Added Refuse Disposal to para 3.2 Table 1 sub para 3.3.12
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-2)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 111-002, Rev G, Shell Exp Aft 182
Coast Guard Drawing 901 WMEC 117-010, Rev G, Web Fr/Stan/Fr 190 Aft
Coast Guard Drawing 901 WMEC 167-001, Rev R, List of Structural Closures
Coast Guard Drawing 901 WMEC 183-001, Rev F, Diesel Gen Fdns
Coast Guard Drawing 901 WMEC 183-004, Rev E, Misc Elec Fdn Oms – Aft 184
Coast Guard Drawing 901 WMEC 185-012, Rev K, Steering Gear Rm Fdns
Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds, Aft 182
Coast Guard Drawing 901 WMEC 122-006, Rev F, Transv Bhds 196, 207, 228, 242
Coast Guard Drawing 901 WMEC 141-002, Rev H, 1st Platf Pltg & Framing, Aft 182
Coast Guard Drawing 901 WMEC 501-003, Rev M, Steering Gear Rm Arr
Coast Guard Drawing 901 WMEC 529-001, Rev N, Ballasting & Emer Bilge Drainage Sys Diagram
Coast Guard Drawing 901 WMEC 562-005, Rev K, A & B Class Rudder Stock And Steering Gear A&D
Coast Guard Drawing 901 WMEC 801-006, Rev M, General Arrangement 1st Platform
Coast Guard Drawing 901 WMEC 801-012, Rev B, Curves of Form
Coast Guard Drawing 901 WMEC 801-022, Rev L, Docking Plan
Coast Guard Drawing FL 184-002, Rev B, SS60 Transducer Install Adapter Assy
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary
Services v (Rev-2)
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary
Hull Accesses
OTHER REFERENCES
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
MIL-PRF-16173, Oct 2017, Corrosion Preventive Compound, Solvent Cutback, Cold Application vi (Rev-2)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
2 Y *Transducer Cover
Plate
PN: FL-184-002, DET 15-E 1 ea. 50.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter vii (Rev-2)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4
(Inspection report particulars)):
Work
Item Title
1 Tanks, Ballast, Repair and Preserve 100 Percent viii (Rev-2)
PRINCIPAL CHARACTERISTICS
270' WMEC (A-CLASS)
PHYSICAL
Length overall 270' 0"
Length between perpendiculars 255' 0"
Beam molded 38' 0"
Depth molded, main deck amidships
01 level amidships
23' 6"
31' 4"
Full load displacement 1,902.2 long tons
Draft, full load to baseline amidships 14' 3"
Highest projection above baseline
*height approximated
≈ 110' 0"
Shore tie voltage requirements 2 cables, 400A / 450V, 3 phase
Frame spacing 1' 0"
MACHINERY
Main propulsion 2 ALCO Model 18-251-F Diesel Engines, 3,600 BHP each
Ship’s service generators 2 Caterpillar Model D-398-TA Diesel-driven KATO 6P6-
1350 Generators. 475 KW each @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Emergency generators Caterpillar Model D-348-TA Diesel-driven KATO 4P4-
1900. 475KW @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Number of propellers 2
Propeller diameter 9' 0"
Number of blades, Each 4
Pitch Controllable
Shaft RPM 260
Shaft diameter 10.55" at exit of hull
Anchor & chain Two 4,000 lb Navy Stockless Anchors, 8 shots of chain each
TANK CAPACITIES
Diesel fuel total (95%) 79,210 gal.
JP-5 total (95%) 25,890 gal.
Potable water total (100%) 8,553 gal.
Hydraulic & lube oil total (95%) 2,237 gal.
1 (Rev-2)
00000_0725_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-2)
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast
Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must
3 (Rev-2) be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’
Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous
Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental
Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
4 (Rev-2)
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 Not applicable.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-2)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
6 (Rev-2)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
7 (Rev-2)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /
TIME
8 (Rev-2)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading
(mils)
9 (Rev-2)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
10 (Rev-2)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
11 (Rev-2)
4.2 Tank and Void Assessment form.
12 (Rev-2)
13 (Rev-2)
63110_ESD_0723_FLT
REC_12316_FLT_270’ WMEC ‘A’ Class (ALL) (0320)
S25_0008_12100_AJW_1125_901
WORK ITEM 1: Tanks, Ballast, Repair and Preserve 100 Percent
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to repair internal structure, and prepare and coat 100% of the surfaces of the following tank(s):
TABLE 1 - TANKS
TYPE OF STRUCTURE LOCATION CAPACITY - 95%
(gallons)
LOW SUCTION
(gallons)
Ballast 4-228-1-W 3,521 282
Ballast 4-228-2-W 3,521 282
Ballast 4-242-0-W 2,989 239
NOTE
Tanks also used for storing grey water – considered immediately dangerous to life and health (IDLH).
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 111-002, Rev G, Shell Exp Aft 182
Coast Guard Drawing 901 WMEC 117-010, Rev G, Web Fr/Stan/Fr 190 Aft
Coast Guard Drawing 901 WMEC 167-001, Rev R, List of Structural Closures
Coast Guard Drawing 901 WMEC 183-001, Rev F, Diesel Gen Fdns
Coast Guard Drawing 901 WMEC 183-004, Rev E, Misc Elec Fdn Oms – Aft 184
Coast Guard Drawing 901 WMEC 185-012, Rev K, Steering Gear Rm Fdns
Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds, Aft 182
Coast Guard Drawing 901 WMEC 122-006, Rev F, Transv Bhds 196, 207, 228, 242
Coast Guard Drawing 901 WMEC 141-002, Rev H, 1st Platf Pltg & Framing, Aft 182
Coast Guard Drawing 901 WMEC 501-003, Rev M, Steering Gear Rm Arr
Coast Guard Drawing 901 WMEC 529-001, Rev N, Ballasting & Emer Bilge Drainage Sys
Diagram
14 (Rev-2)
Coast Guard Drawing 901 WMEC 801-006, Rev M, General Arrangement 1st Platform
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary Hull Accesses
OTHER REFERENCES
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
• 3.4 Repair.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
• Diesel Oil Tanks 4-207-0-F, 4-207-1-F, 4-207-2-F, and 2-228-1-F (total capacity 28,826 gallons)
3.1.5 Temporary access openings. Due to limited access to work areas, the Contractor may, with express permission of the KO (via submission of a CFR), cut access holes to facilitate accomplishment of the work specified herein. Perform all work required to open and close the access openings in accordance with SFLC Std Spec 8636.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
15 (Rev-2)
Any ballast tanks being listed for preservation will have been pumped down to low suction by ship’s force prior to arrival at the Contractor facilities.
3.3 Content removal. The Contractor must remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations. Plug all inlet and outlet piping in the tank to prevent contaminants from entering the tank. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings. Maintain a plug accountability log outside the tank(s) to prevent any of the installed temporary plugs from being lost inside the tank or forgotten inside at tank closure.
3.4 Repair. The Contractor must perform the following repairs, as designated by the Coast Guard
Inspector, in accordance with SFLC Std Spec 0740 and Coast Guard Drawings 901 WMEC 111-002, 901
WMEC 117-010, 901 WMEC 183-001, 901 WMEC 183-004, 901 WMEC 185-012, 901 WMEC 121-
001, 901 WMEC 122-006, 901 WMEC 141-002, and 901 WMEC 501-003.
3.4.1 Ultrasonic thickness (UT) measurement. The Contractor must take a total of 500 UT measurements in accordance with SFLC Std Spec 0740, Appendix C in locations designated by the Coast Guard
Inspector and using Coast Guard Drawings 901 WMEC 111-002, 901 WMEC 121-001, 901 WMEC 131-
002, and 901 WMEC 141-002 as guidance. Submit a CIR.
3.4.2 In addition to the UT measurements, take a total of 25 pit-depth measurements, using a suitable pit depth gauge.
3.4.3 Crop and renew approximately 20 square feet of steel plating and 20 linear feet of internal structure, including but not limited to sections of the tank top and supporting structure, in the 4-228-1-W ballast tank.
3.4.4 Crop and renew approximately 20 square feet of steel plating and 40 linear feet of internal structure in the 4-228-2-W ballast tank.
3.4.5 Crop and renew approximately 10 square feet of steel plating and 20 linear feet of internal structure in the 4-242-0-W ballast tank.
3.4.6 Crop and renew all manhole rings and corresponding covers for tanks: 4-228-1-W, 4-242-0-W, and
(forward manhole only) 4-228-2-W, using Coast Guard Drawing 901 WMEC 167-001 as guidance.
3.4.7 Crop and renew two ladders and one sounding tube, as designated by the Coast Guard Inspector, including all mounting points and hardware.
3.5 Surface preservation. The Contractor must accomplish the following tasks for the tanks listed in paragraph 1.1 (Intent):
3.5.1 The Contractor must remove and retain the tank manhole cover(s).
NOTE
The original manhole covers designated in paragraph 3.4.6 do not need to be retained after renewal.
16 (Rev-2)
3.5.2 The Contractor must prepare and coat all tank interior surfaces (including internal surfaces of manhole cover(s), manhole cover hull ring(s) extending outward to the weld line that ties the hull ring into the tank plating on the tank exterior) using the system specified for "Tanks and Voids, Ballast Tanks;
Option I or II " in SFLC Std Spec 6310, Appendix B (Cutter and Boat Interior Painting Systems). Select finish/top coat color to match existing.
3.5.3 The Contractor must prepare and coat all manhole cover external surfaces to match existing adjacent surfaces, using the system specified for “Tanks and Voids (Grey Water, Sewage, and CHT Tanks), Option II, in SFLC Std Spec 6310 Appendix B (Cutter Boat Interior Painting Systems). Select finish/top coat color to match existing adjacent surfaces.
3.6 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces).
NOTE
Surfaces being preserved are considered “critical-coated surfaces”.
3.7 Inspection. After surface preparation and before coating application, the Contractor must visually inspect all tank interior and manhole cover surfaces; including, but not limited to bulkheads, floor and overhead plating, structural members, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Structural condition.
• Inaccessible areas.
• Tank level indicator (TLI) and/or float switch condition.
• Sounding tube and striker plate condition.
• Suction and discharge piping.
• Fastener condition.
3.8 Tank closing. The Contractor must ensure that the tank(s) remain open for at least 24 hours after completion of the tasks specified above. Notify the COR at least 24 hours prior to closing the tank(s).
3.8.1 After satisfactory inspection by the Coast Guard Inspector and after all authorized repairs, accomplish the following:
• Reinspect all TLIs, as applicable, to verify proper operation. Submit CFR.
• Close tank manhole cover(s) with new gasket material conforming to ASTM D1330 and new cotton grommets on all studs (as applicable). Chase threads on studs to ensure even installation of the access covers.
3.8.2 The Contractor must renew 100% of nylon insert/nylock nuts and washers.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.9 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
17 (Rev-2)
4. NOTES
4.1 Structure photos. Photos of the overhead structure below the EDG in the 4-228-1-W ballast tank.
18 (Rev-2)
19 (Rev-2)
86340_ESD_0425_FLT
REC 86340_FLT_270A WMEC (ALL) (0925)
WORK ITEM 2: Drydock
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to drydock the vessel, undock the vessel, and perform various drydocking-related tasks.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
Y *Transducer Cover Plate PN: FL-184-002, DET 15-E 1 ea. 50.00
*Government-loaned property, which must be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 562-005, Rev K, A & B Class Rudder Stock And Steering
Gear A & D
Coast Guard Drawing 901 WMEC 801-012, Rev B, Curves of Form
Coast Guard Drawing 901 WMEC 801-022, Rev L, Docking Plan
Coast Guard Drawing FL 184-002, Rev B, SS60 Transducer Install Adapter Assy
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking
OTHER REFERENCES
MIL-PRF-16173, Oct 2017, Corrosion Preventive Compound, Solvent Cutback, Cold Application
20 (Rev-2)
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
• Anchor assembly
• Load conditions
• U/W body appendages
3.2 Key personnel. The Contractor must determine key personnel and require their presence during all drydocking phases as required by SFLC Standard Spec 8634. Submit list of key personnel to the COR.
3.3 Docking and undocking. The Contractor must perform drydock and undock in accordance with SFLC
Std Spec 8634, using Coast Guard Drawing 901 WMEC 801-022 for guidance.
3.4 Cutter conditions. The Contractor must use the Full Load Condition values listed below all in inches, for purposes of performing Pre-Award calculations as described in Appendix A (Requirements for
Calculations) of SFLC Std Spec 8634.
• Displacement (LT FW): 1890
• VCG (FT ABL): 16.62
• LCG (FT AFT MS): 4.62
• LCF (FT AFT MS): 14.14
• Trim (FT by stern): 0.734
• MT1” (LT-FT/Inch): 272.76
3.4.1 Blocking. The Contractor must facilitate docking the vessel in designated block position by arranging keel and side blocks and ensuring minimum block heights as shown on the vessel's docking plan.
21 (Rev-2)
TABLE 1 – BLOCKING
POS. #
BLOCK HEIGHT ABOVE DOCKING
FACILITY DECK
STEEL
PLATE
SITUATION
AWARENESS
FIN
STABILIZERS ADDITIONAL MIN.
RUDDER
REMOVAL
PROPELLER
REMOVAL
SHAFT
REMOVAL
1 48" NA 30' 0"
minimum from stern for shaft removal
NA NA If the drydock has a sliding block arrangement, the
Dockmaster must exercise special care and/or set side blocks between frames 96 and 104 (fin stabilizer area) by a different method which clears the fin stabilizers.
None
3.5 Pre-award calculations. The Contractor must provide to the KO a set of pre-award calculations, as described in SFLC Std Spec 8634 Appendix A.
3.5.1 Provide vertical side/bilge block offsets for any side blocks placed in a location where vertical offsets are not already defined by the docking plan.
3.5.2 Submit an alternate blocking arrangement, as part of the pre-award calculation submission, to compensate for any changes from the docking plan.
3.5.2.1 If the alternate blocking arrangement interferes with U/W hull plate inspection or 100% preservation of U/W body surfaces required under separate work items in this specification package, the
Contractor must include a plan of how inspection/preservation will be accomplished. Plan must include any modifications necessary to the prescribed docking plan including removing, shifting, repositioning blocks, or fleeting the vessel at no additional cost to the Government.
22 (Rev-2)
1. The USCG has established several approved alternate docking plans for each vessel-class, to facilitate complete access to the entire U/W body structure, for periodic comprehensive inspection and/or 100% preservation.
This inspection and preservation pattern and periodicity is a configuration management concern that is a vital requirement of the contract. Intention to deviate from these plans (fewer blocks, block spacing, additional blocks, etc) is to be identified on pre-award calculations (Paragraph 3.5.2); an alternate docking plan and mitigation strategy will be provided to maintain preservation and inspection configuration.
2. Pre-award calculations may be deemed unsatisfactory - and may adversely affect contract award if they are submitted with the following detrimental factors:
a. No methods have been proposed that meet the requirements for the specified docking plan.
b. Proposed block shifting or fleeting risk-mitigating plan may result in delays in period of performance.
c. Proposed alternate docking plan violates USCG configuration management policies.
3.6 Unplanned availability: Underwater body cleaning-removal of marine growth. The Contractor must accomplish the work in this paragraph in lieu of the work described in SFLC Std Spec 8634 paragraphs
3.5.4.1 and 3.5.4.2. Within four hours after the vessel has been docked, the Contractor must start cleaning the entire underwater hull from the upper edge of the boot top down, including sea chest gratings, sea chest interiors, fairwaters, rope guards, rudder, shaft strut, z-drive, thruster tunnel, and zinc anodes, as applicable. The Contractor must remove all marine growth, fouling, salt, and dirt from the underwater hull by High Pressure Fresh Water Wash, using a minimum pressure at the nozzle of 3,500 psi and maximum pressure of 7,000 psi. Complete the hull cleaning before marine growth hardens. Removal of gratings is not required.
WARNING
Do not use chemical additives in the freshwater wash. Take extreme care to avoid damaging or removing existing intact underwater body coating.
3.7 Fuel offloading. The Contractor must be aware that fuel offloading is not mandatory to drydock the vessel.
3.8 Fleeting. Not required.
4. NOTES
4.1 Arrival conditions. The COR will advise the Contractor of the actual tank and draft readings when the vessel arrives, and will discuss with the Contractor any liquid loading changes necessary.
23 (Rev-2)
86350_ESD_1021_FLT
REC_86350_FLT_270A WMEC (ALL) (1110)
WORK ITEM 3: Temporary Services, Provide - Cutter
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to provide temporary services to the Cutter, during the performance of this availability.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary Services
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
24 (Rev-2)
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences).
3.2 Temporary service particulars. The Contractor must provide the below listed temporary services, in accordance with SFLC Std Spec 8635.
TABLE 1 - SERVICE SELECTION
*SUB-
PARAGRAPH
TITLE
Y/N
3.3.1 Office space N
3.3.2 Telephone and internet access N
3.3.3 Parking Y
3.3.4 Duty section berthing N
3.3.5 Electrical power (including all requirements in associated sub-paragraphs) Y
3.3.6 Hull grounding straps (not applicable when cutter is waterborne) N
3.3.7 Compressed air (including all requirements in associated sub-paragraphs) N
3.3.8 Hazardous material/hazardous waste disposal (see Tables 2 and 3 below) Y
3.3.9 Heavy lift equipment: 48 hours Y
3.3.10 Water supply
3.3.10.1 Potable water: 5,000 gallons per day, at 40 psig Y
3.3.10.2 Hot-circulating water N
3.3.10.3 Cooling water (including 2-1/2” supply and return lines for the ASW system) Y
3.3.10.4 Firemain system (including all requirements in associated sub-paragraphs) Y
3.3.11 Steam (including all requirements in associated sub-paragraphs) N
3.3.12 Refuse disposal Y
3.3.13 Sewage and grey water disposal (including all requirements in associated sub-paragraphs)
Y
3.3.14 Storage – General (including all requirements in associated sub-paragraphs):
3.3.14 Dry stores. N
3.3.14 Paint and flammable stores. N
3.3.14 Refrigerated stores. N
3.3.15 Small boat storage (including all requirements in associated sub-paragraphs) N *Each sub-paragraph number relates directly to the identical sub-paragraph number in SFLC Std Spec 8635.
TABLE 2 - HAZARDOUS WASTE DISPOSAL – LIQUIDS (GALLONS)
PAINT THINNERS ENGINE COOLANT BILGE WATER
N/A N/A 4,000
TABLE 3 - HAZARDOUS WASTE DISPOSAL – SOLIDS
OILY
FILTERS
OILY RAGS
(LBS)
EMPTY 1-GAL
CONTAINER*
EMPTY 5-GAL
CONTAINER*
EMPTY 55-GAL
CONTAINER*
N/A N/A N/A N/A N/A
*Previously housed hazardous materials.
3.3 Extended temporary services. If the performance period of the contract is extended by the KO, the contractor must continue to provide all temporary services as specified herein for the extension period.
25 (Rev-2)
4. NOTES
This section is not applicable to this work item.