This is a blank SOS&S (Schedule of Services & Supplies) pricing schedule for unplanned availability work on USCGC BEAR (WMEC-270A) during fiscal year 2026. The schedule outlines definite line items including ballast tank repair and preservation, drydock services, and temporary cutter services, all currently priced at $0.00 pending contractor submission. A composite labor rate will be applied on an hourly basis, with a GFP (Government Furnished Property) report requirement and travel/per diem costs to be invoiced as job items.
The pricing template includes provisions for over and above/growth work with an estimated 1,044 labor hours and a material markup/handling fee of $28,177.00, though the total evaluated price is currently shown as $0.00. The contractor's labor rates and material markup percentages will apply throughout the contract lifecycle if growth work is added via contract modification. The solicitation is issued by the U.S. Coast Guard (Department of Homeland Security) under solicitation number 70Z08026QMECP0008, with point of contact Chelsea Clark. This is a draft pricing schedule dated December 2, 2025, intended for evaluating contractor proposals for the dry dock and maintenance work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 70Z08026QMECP00080005_A00005_BEAR DD.pdf | ||
| BEAR FY26 UPDD AMENDMENT 70Z08026QMECP00080004.pdf | ||
| BEAR (WMEC 270A) UPDD AJW 26R2.pdf | ||
| BEAR FY26 UPDD AMENDMENT 70Z08026QMECP00080003.pdf | ||
| 70Z08026QMECP0008-0002_CGC BEAR FY26 UPDD Amendment 002 (KO Signed).pdf | ||
| 70Z08026QMECP0008-0002_CGC BEAR FY26 UPDD_Attachment 4.pdf | ||
| 70Z08026QMECP0008-0002_CGC BEAR FY26 UPDD_Attachment 5.pdf | ||
| 70Z08026QMECP0008-0001_CGC BEAR FY26 UPDD Amendment 0001.pdf | ||
| 70Z08026QMECP0008-0001_CGC BEAR FY26 UPDD Attachment 3.pdf | ||
| 70Z08026QMECP0008_Solicitation_CGC BEAR FY26 UPDD.pdf | ||
| SOW_CGC BEAR FY26 DD.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: | |||||
| USCGC BEAR (WMEC-270A) UNPLANNED AVAILABILITY FY2026 | |||||
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Tanks, Ballast, Repair and Preserve 100 Percent | JOB | 1 | $0.00 | |
| D-002 | Drydock | JOB | 1 | $0.00 | |
| D-003 | Temporary Services, Provide - Cutter | JOB | 1 | $0.00 | |
| O-00A | Composite Labor Rate | Hour | |||
| D-00B | GFP Report | NSP | EA | NSP | |
| D-00C | Travel and Perdiem | JOB | |||
| Total Price of Definite Items | |||||
| Total Price of Option Items | |||||
| Total Price of Definite and Optional Items | |||||
| Over and Above/Growth Work | |||||
| The Labor Rates and Material Markup/Handling Fee will used throughout the life of the contract if growth work is added to the scope of the contract. If Over and Above/Growth Work is issued, these items will be awarded at the quantities needed via a contract modification. The values shown are an estimate only and may be exceeded at the unit prices offered. The total extended price for both CLINs below are being used solely for the purposes of evaluating price. | |||||
| **Fill in the sections highlighted below: | |||||
| OA/G-001 | Over and Above/Growth Labor Rate | Hour | 1,044 | $0.00 | |
| OA/G-002 | Over and Above/Growth Material Markup/Handling Fee | $28,177.00 | Percent | $0.00 | |
| Total Evaluated Price of Over and Above/Growth | $0.00 |