This document is the Work Item Standards and Specifications (WISS) for Coast Guard Vessel Maintenance and Repair, which provides detailed requirements and procedures for various maintenance actions that may be required on Coast Guard vessels.

The key details include:

  • Definitions of generic maintenance, service, and administrative actions that will be used throughout the WISS
  • General administrative requirements such as submitting reports, attending meetings, and developing plans (e.g. Environmental Protection Plan, Fire Prevention and Response Plan)
  • Specific technical requirements for hull structure, welding, and other vessel systems and components
  • Procedures for tasks like 3D scanning, plate thickness measurements, and weld repairs
  • Emphasis on safety, environmental protection, and maintaining fire detection/fighting capabilities during maintenance periods

This WISS document provides the standards and specifications that would be invoked by a federal contract opportunity for drydocking and maintenance of a Coast Guard cutter vessel.

View the file

Other files

File Type Posted
Amendment 0005_ext.pdf PDF
Amendment 0004_QA.pdf PDF
Amendment 0003_QA.pdf PDF
QA Attachment.pdf PDF
Amendment 0002.pdf PDF
Attachment 3_QA FORMS_.xlsx XLSX spreadsheet
Amendment 0001.pdf PDF
Attachment 1_BLANK Schedule of Services.xlsx XLSX spreadsheet
Attachment 2_Specification.pdf PDF
70Z08024QPBPL0043.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Work Item Standards and Specifications (WISS) for Coast Guard Vessel Maintenance and Repair, Surface Forces Logistics Center (SFLC) v1.0 Page 1 of 112

REFERENCES

COAST GUARD DRAWINGS

Reserved

SFLC MANUALS AND TECHNICAL GUIDANCE

SPECIFICATIONS AND QUALIFIED PRODUCTS LIST FOR COAST GUARD VESSEL COATINGS (CG-COATINGS 5

SPECIFICATIONS), v1.0

OTHER REFERENCES

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding

End

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates 10

International Standard Organization (ISO) 4406, 2018, Hydraulic Fluid Power – Fluids – Method for Coding the Level of Contamination by Solid Particles

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-58, 2003 Edition, Pipe Hangers and Supports

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, 15 Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service 20

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric 25

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities

SAE J1942/1_202112 Qualified Hoses for Marine Applications 30 v1.0 Page 2 of 112

CHAPTER 000 GENERAL GUIDANCE AND ADMINISTRATION

000a Guidance for Understanding Requirements Documents

Category Definition

Generic Maintenance Actions These verbs describe types of maintenance work to be performed on designated configuration items and classes, are defined in subchapter 000b below, and are designated using bold font (e.g., Abate, Clean, Inspect, Operate & Inspect, Overhaul, Renew, Repair, Pressure Test, etc.).

These will generally appear in work items, but appear herein as well to describe sub-tasks.

EXAMPLE

“Overhaul the PORT Propulsion Shaft Seal.”

Generic Service Actions These verbs describe types of service to be provided, are defined in subchapter 000b below, and are designated using bold font (e.g., Provide, Perform, Comply, Provide, etc.).

These will be followed by a description of the service in the work item, or will point to a “Supply, Service, and General Requirements Items Item” herein.

EXAMPLE

“Perform with ”

“Provide TEMPORARY FIRE SAFETY SUPPLIES/SERVICES (000e)”

Generic Administrative Actions These verbs describe types of administrative functions to be performed, are defined in subchapter 000b below, and are designated using bold font (e.g., Submit, Attend, Notify, Verify, etc.).

These will be followed by a description of the administrative function in the work item, or will point to an “Administrative Item” herein.

EXAMPLE

“Submit a CFR.”

Supply, Service, Administrative, and General Requirements Items

These are collections of subtasks/standards/specifications that are designated in ALL CAPS. A SWBS designation (at the end of, or near, the task in the work item) points the reader to a WISS SWBS Section.

ENVIRONMENTAL PROTECTION PLAN (000c) ARRIVAL CONFERENCE (000c)

GENERAL REQUIREMENTS FOR SURFACE PREPARATION AND COATINGS

APPLICATION (631b)

These items are invoked via Tasks in work items or herein.

EXAMPLES

Submit an ENVIRONMENTAL PROTECTION PLAN (000c) Attend the ARRIVAL CONFERENCE (000c) Comply with all GENERAL REQUIREMENTS FOR SURFACE PREPARATION AND

COATINGS APPLICATION (631b) v1.0 Page 3 of 112

Category Definition

Amendments to Generic Actions

These are tables that describe additional maintenance standards that apply to specific types/classes of configuration item, above those required by the Generic Actions.

A SWBS designation (at the end of, or near, the task in the work item) points the reader to a WISS SWBS Section (i.e., the 123a designation).

EXAMPLE

“Clean the Grey Water Tank (123a).”

The reader finds the designated SWBS Section in WISS. In that section the reader finds the table that matches the configuration item being worked. The name of the type/class of configuration item will appear in the top row of the table with a definition of that type/class.

123a Tanks and Voids

The Various additional requirements are then appended to the requirements described by the Generic Action.

Tasks A task is described when an Action (e.g., Clean, Inspect, Overhaul, Renew, Repair, etc.). is coupled with a configuration item (e.g., “the Mast”, “the #1 Fire Pump”, the “port anchor windlass”, etc.), or a Supply, Service, Administrative, and General Requirements Item.

EXAMPLES

“Clean the Grey Water Tank (123a).”

“Provide TEMPORARY FIRE SAFETY SUPPLIES/SERVICES (000e)” “Submit a CFR.”

Optional requirements Whenever optional requirements are presented in the SOW (e.g. “[ ] Option A, [ ] Option B, [ ] Option C”, etc.) all options designated with an “[X]” must be performed or complied with; the other options must not be performed (i.e., the options left blank “[ ]”)

Primary Service Providers The term CONTRACTOR or Contractor is used throughout the SOW and WISS to denote the entity/organization (e.g., the prime commercial contractor, the Coast Guard Yard, any particular Coast Guard Industrial Facility, etc.) who has been charged with performing the services described in the SOW.

Tech-Proposal/Tech-Info Request Items

Tech-Proposal/Tech-Info Request Items describe pre-award document submissions that will inform technical evaluations impacting contract award decisions.

Notes Language designed to assist the reader’s comprehension/navigation of the requirements, or to provide suggestions/data (for info only, must be verified/validated by the reader) and examples based on prior contracts, etc., will appear in grey boxes. This language is not contractually binding.

This is a sample note.

Configuration Item Classes Configuration Item Classes describe groups of configuration items that share maintenance standards. They are defined in the various technical chapters below and are designated by capitalizing the first letter of each word and enclosing in v1.0 Page 4 of 112

Category Definition quotation marks (e.g., “Structural Plate and Shapes”, “Tank” or “Void”, “Wet Deck”, etc.).

Each particular configuration item designated in the SOW may belong to one or more Configuration Item Classes.

The SOW will direct the reader to the WISS sections that contain the applicable Configuration Item Classes.

The SOW may assist or guide the reader in assigning a Configuration Item Class to a particular configuration item using a note, BUT regardless, the reader must still classify all configuration items designated in the SOW using the Configuration Item Class definitions described herein; then identify and conform to all applicable requirements stated herein for each applicable Configuration Item Class.

v1.0 Page 5 of 112

000b Generic Action Definitions

Generic Maintenance Actions

Whenever the following action terms appear in the SOW or herein with bold letters the corresponding definitions below apply, otherwise use dictionary definitions and the surrounding context to determine their meaning.

Action Definition

No Work or N/A

The corresponding component, assembly, etc. appears in the SOW “for info only”; the corresponding task description requires no work or action.

However, collateral work (e.g., cleaning in support of gas-free certifications, removal as an interference, repair of damage, etc.) may still be required on the corresponding component, assembly, etc. if impacted by other task descriptions specified elsewhere in the SOW, or if the component/assembly is damaged by the contractor, etc.

Abate This is the removal and proper disposal of hazardous material. Typically, this will be used in work items that remove known hazardous materials such as LEAD BASED PAINT (LBP), ASBESTOS CONTAINING MATERIAL (ACM), etc. Comply with all Federal, state, and local regulations that may apply.

Operate & Inspect

This is the assessment the designated equipment/system while operating it through its full range of motion and/or functionality for the purpose of determining all discrepancies that may require repair work.

Coast Guard personnel will operate the equipment/system, testing all associated features (e.g., controls, indicators, readouts, displays, panels, etc.) and cycling all associated items (e.g., actuators, shafting, linkages, etc.).

For deck machinery the equipment should be operated in a safe, no-load condition; an operational test using test weights is not required. However, to supplement the no-load test specified and required above, test weights may be handled by request pending COR approval after the COR determines the system is safe to handle weights. The rated load of the system must not be exceeded. Furnishing and handling test weights for the purpose of troubleshooting must result no additional cost to the Government.

If applicable, Inspect sheave assemblies, using Coast Guard Drawing FL-1702-11 as a guide.

All unusual conditions (e.g., noise, vibration, overheating, binding, misalignment, maladjusted controls, and malfunctioning controls or read-outs found, etc.) must be reported in a CFR.

At the conclusion of all operations, Inspect the equipment/system.

Clean This is the removal of all contaminates (e.g., dust, dirt, grease, foreign material, etc.) from the designated surface, component, item, etc. to the greatest extent practicable.

See the Terms and Definitions section below for the definition of “Cleanliness Grade A” (a work item may require that a surface/fluid/etc. meet the “Cleanliness Grade A” description).

Inspect This is the examination of, either visually or physically by touch, all designated surfaces/parts/components/systems.

All instruments/tools used during the inspection that require calibration must possess a valid calibration documentation (e.g., unexpired calibration sticker, etc.).

The examination is for the purpose of identifying and reporting all discrepancies. Include a description of those discrepancies in the applicable/associated report submission with recommended repairs.

If not part of final testing/inspection, open or remove any inspection plates, cover plates, and other non-load bearing and non-power transmitting components that may be part of the designated surfaces/parts/components/systems, to gain access to hidden surfaces.

Do not disassemble or disturb load bearing or power transmitting components to perform the examination unless directed in the SOW or elsewhere herein.

Perform the following as they apply to the item being examined:

• Identify all leaks (e.g. fuel leaks, hydraulic fluid leaks, sea water leaks, air leaks in pneumatic systems, oil leaks, etc.) at mechanical piping joints.

• Identify all damage (e.g. impacts, deformation, warping, bending, yielding, excessive corrosion, significant loss of base material, cracks, excessive wear, unusual wear patterns, etc.) that may v1.0 Page 6 of 112

Generic Maintenance Actions

Whenever the following action terms appear in the SOW or herein with bold letters the corresponding definitions below apply, otherwise use dictionary definitions and the surrounding context to determine their meaning.

Action Definition affect the strength or the proper, trouble-free, safe operation of load bearing and power transmitting components (e.g. structural members, pressurized piping, pump cases, motor cases, valve bodies, hydraulic cylinder bodies, cylinder tie rods, accumulator and flask bodies, hose assemblies, heat exchanger tubing and shells, shafts, mechanical pins, keys, keyways, splines, set-screws, stakes, gear teeth, cams, cam-followers, couplings, cylinder rods, clevises, and trunnions etc.).

• Identify all damage (e.g. raised metal, nicks, burrs, scratches, scoring, heat checks, galling, pitting, gouges, corrosion, damage, yielding or stretching, excessive wear, and all other unusual discontinuities with surrounding surfaces, etc.) that may affect proper, trouble-free, safe operation (e.g. sealing, flow rates and pressures, etc.) of each surface that is critical to the operation of the part/component/system, or that mates with or runs against a machined or plated surface (e.g. various machined surfaces, cylinder bores, pistons, piston rods, all surfaces that mate with o-rings or seals, valve spools and spool bores, valve seats, and screw threads, bearing/journal surfaces, etc.).

After the examination is complete reinstall all removed parts and return the component/system to normal operating condition pending completion of other tasks being performed in conjunction with the examination.

Service & Inspect

This is performing all practicable preventive maintenance tasks (e.g., inspections, cleaning, lubricating, etc.) on an item without performing significant/intrusive disassembly or other potentially high-risk actions.

Remove from the designated component/assembly/system all inspection plates, cover plates, and other non-mechanical load bearing components, as applicable, to gain access to hidden surfaces. Do not disturb mechanical load bearing components or mechanical power transmission components prior to or during the inspection.

Clean, Inspect all accessible surfaces. Uncoated surfaces must meet Cleanliness Grade A, unless otherwise specified herein, or in the work item, or system specifications.

Lubricate uncoated surfaces of the component/assembly/system as specified in the system specifications or the work item. When a lubricant is not specified herein, or in the work item, or the system specifications use a lubricant conforming to CID A-A-50433.

Prior to reinstalling removed covers, plates, and non-mechanical load bearing components Perform all other work specified or invoked by the work item.

Reinstall all removed parts and return the component to normal operating condition.

Lubricate This is the application of a lubricant (e.g., grease, oil, silicone, etc.) on the designated surface/component to reduce sliding friction or to protect the surface from oxidation/corrosion. When a lubricant is not specified in the task description, system specifications, or herein, use a lubricant conforming to CID A-A- 50433.

3D-Scan This is the digital capture of dimensional data using a laser scanning device.

NDE This is nondestructive examination, the act of determining the suitability of a material or a component for its intended purpose using techniques not affecting its serviceability.

NDE is the standard term used by AWS. Nondestructive inspection (NDI), nondestructive testing (NDT), and nondestructive evaluation are interchangeable terms for NDE

Overhaul This is the complete disassembly of an item to identify and perform all necessary repairs/renewals to sub-components that can only be assessed after disassembly; after conditional repairs are performed the item is completely reassembled with all new consumable/wearing components and reinstalled into the system and tested.

Completely disassemble the designated component/assembly.

Determine which sub-components are wearing components/consumables, and which are not.

v1.0 Page 7 of 112

Generic Maintenance Actions

Whenever the following action terms appear in the SOW or herein with bold letters the corresponding definitions below apply, otherwise use dictionary definitions and the surrounding context to determine their meaning.

Action Definition

Inspect all exposed surfaces of all non-wearing sub-components; Submit a CFR detailing all discrepancies and recommended repairs.

Clean, Inspect all accessible surfaces. Uncoated surfaces must meet Cleanliness Grade A, unless otherwise specified herein, or in the work item, or system specifications.

Renew each Government-furnished sub-component that was not designated as conditional (**).

Perform all newly authorized work specified in CR(s) that resulted from the prior inspections (e.g., renewal of conditional GFP, etc.).

Perform all other work specified or invoked by the task description that can only be performed prior to reassembling the component or assembly.

Lubricate uncoated surfaces of the component or assembly as specified in the system specifications, the task description, or herein.

Renew each wearing component/consumable at reassembly (e.g., seal, gasket, o-ring, bearing, etc.).

Reassemble the designated component/assembly and return it to normal operating condition within the system.

Repair This is correcting an identified discrepancy to a given standard of performance or material condition;

corrective maintenance.

Renew This is the permanent removal and disposal of an item and then the installation, in its place, of a new and unused item which is identical in material, form, fit, and function; the new item must:

• Have the same shape, size, dimensions, and other physical parameters.

• Physically interface/interconnect with the existing equipment/surfaces the same way the original item did, becoming an integral part of that component/system.

• Perform the same functions as the original item.

Groom The is the preparation of the designated equipment/system for final testing by performing the following in conjunction with all other associated work specified, and while Coast Guard personnel operates the equipment/system in a no-load condition.

Operate and Inspect all components in the designated equipment/system. Perform the following as they apply to the particular equipment/system:

Verify that all reservoirs and gear cases are filled to the level required in the system specifications.

Verify that all installed system isolation valves (e.g., return line valves, case drain line valves, etc.)

are properly aligned prior to energizing and operating equipment.

Verify that all associated control valves, electrical and mechanical controls, and actuators are operating properly.

If the designated equipment/system is hydraulic remove air from the hydraulic system. Break mechanical joints at high points while cycling actuators, if required, to bleed air from the hydraulic system. Verify there are no lube oil or hydraulic fluid leaks.

Adjust, as required, adjustable components (e.g., sensors, controls, readouts, pressure control valves, flow control valves, limit switches, proximity switches, etc.) to achieve proper operation, as specified in the work item or in the system specifications (i.e., dwgs, TPs, manufacturer’s instructions, etc.).

Identify all lubrication points in the system. Lubricate these points as specified in the work item or in the system specifications.

Pressure Test

This is a test that proves the strength of a pressure-vessel (e.g., pipe, flask/bottle, accumulator, etc.) or structural boundary by internally pressurizing that pressure-vessel /boundary with a fluid or gas to a measured pressure.

v1.0 Page 8 of 112

Generic Maintenance Actions

Whenever the following action terms appear in the SOW or herein with bold letters the corresponding definitions below apply, otherwise use dictionary definitions and the surrounding context to determine their meaning.

Action Definition

Typically, a temporary pressure test rig is used to perform the test that includes a pump/compressor, a certified pressure gage, a relief valve. The relief valve must be set to relieve at a pressure that will prevent damage to the vessel/boundary.

A test pressure and relief valve pressure will be specified herein, in the work item, or in the test specifications.

Pull Test This is a procedure used to prove the design of, or weld repairs to, the designated item (e.g., pad eyes, tie-downs, bits, chocks, etc.)

If not specified in the work item or system specification, the required force for the pull test on the designated item must be determined as specified below:

• For periodic testing of a deck fitting the force of pull on the fitting must be 1.5 times the deck fitting’s rated load.

• For testing subsequent to a weld-repair of a deck fitting (i.e., renewal or repair of a fitting) the force of pull on the deck fitting must be 2 times the deck fitting’s rated load.

The proper direction to pull against the specified item must be determined; generally, this is the direction in which the deck fitting and surrounding deck or bulkhead displays its greatest resistance to damage and deformation.

General purpose fittings are typically strongest when pulled perpendicular to the deck or bulkhead where they are attached. Special purpose fittings may be stronger in a direction specific to their intended use that may differ from perpendicular to the deck or bulkhead.

Pull the designated item to the force and in the direction determined above and hold for one minute.

Release the load and verify no permanent deformation or damage to the designated item or the surrounding structure (e.g., deck, bulkhead, etc.) as applicable.

Weight Test

This is an operational test using test weights. Procedures may be specified herein, in the work item, or in the system specifications. If no test procedure is specified, Submit a proposed written procedure to the COR; do not proceed with weight testing without COR approval.

Provide all necessary temporary rigging gear (e.g., temporary wire ropes and pendants, external lifting devices such as a crane, strong-backs, test weights, tag lines, dynamometers, come-alongs, steamboat ratchets, shackles, dunnage, bumpers, etc.).

Place dunnage under test weights to protect the vessel’s deck and pier, as applicable. Place bumpers or other protective measures between the hull and pier when test procedures involve warping the vessel.

Provide all necessary rigging services (e.g., riggers, external crane operators, etc.) required to perform the referenced testing procedures invoked by the task description.

Conduct a briefing for cognizant shipboard personnel at least 24 hours prior to initiating the test.

Allow Coast Guard personnel to inspect and approve all temporary rigging gear prior to use.

Determine the vessel’s load status and verify that the vessel’s stability is adequate and safe for performing the test procedure. Conduct weight testing only when the vessel is waterborne and only after at least one of the following three conditions have been met:

• The vessel is in a full liquid load condition.

• A full liquid load condition has been simulated through the use of equivalent weights that have been arranged shipboard to achieve the same metacentric height (GM) as a full liquid load condition.

• The vessel’s DCA or EO or EPO has determined that the vessel’s stability meets or exceeds the minimum stability required to safely perform the test procedure.

Avoid conditions that will cause sudden application of test loads.

v1.0 Page 9 of 112

Generic Maintenance Actions

Whenever the following action terms appear in the SOW or herein with bold letters the corresponding definitions below apply, otherwise use dictionary definitions and the surrounding context to determine their meaning.

Action Definition

Keep test weights as close to the deck as practicable while performing the test procedure to minimize damage to the vessel if control of the test weight is lost.

Do not allow immersion of a deck edge or a list of over 15 degrees while performing the test procedure.

Inspect-Op Test (Initial)

This set of inspections and tests must be performed prior to performing any subsequent maintenance action (e.g., cleaning, disassembly, etc.) that may inadvertently cause new discrepancies; at least one Inspect-Op Test (Initial) task must be performed in each work item.

These inspections and tests must be performed with the intent of identifying and reporting all previously undocumented discrepancies.

Before proceeding with maintenance work it is critical that all new, previously unidentified, discrepancies are identified and reported at this step.

Otherwise, it will be assumed that all newly discovered discrepancies were caused by the party performing the follow-on maintenance work (i.e., that party will be expected to prove that they did not cause the discrepancy); correction of those discrepancies will be at that party’s expense. New discrepancies that can only be discovered post-disassembly are excepted.

Inspect all designated surfaces/equipment/system/etc. any all others that may be affected by any subsequent maintenance action.

If the designated surfaces/equipment/system/etc. contains any subcomponents that can be operated, or if any other undesignated equipment/system/etc. will potentially be affected by any subsequent maintenance actions then Operate and Inspect all those components.

Perform all other associated actions (e.g., Weight Test, etc.) that may be specified in the work item.

Submit a report of findings as described in the SOW.

Inspect-Op Test (Final)

This action must be performed immediately prior to the completion of each work item and after performing all other associated maintenance tasks.

This action must be performed on the designated surfaces/equipment/systems/etc., and on all other surfaces/equipment/system/etc. that were affected by work. The intent is to prove that all maintenance and repairs were performed satisfactorily, and to prove that no new discrepancies were introduced during the performance of work. A report must be submitted that documents satisfactory completion of all associated work.

It will be assumed that all new discrepancies identified at this step were caused by the party performing the associated maintenance work (i.e., that party will be expected to prove that they did not cause the discrepancy). Correction of these new discrepancies must be at the expense of the party who performed those maintenance actions.

If the designated surfaces/equipment/system/etc. contain any components that can be operated, or if any other undesignated equipment/system/etc. was potentially affected by work then Operate and Inspect all those components.

Perform all other associated actions (e.g., Weight Test, etc.) that may be specified in the work item.

Inspect all designated surfaces/equipment/system/etc., and all others that may have been affected by work.

Submit a report of attesting to satisfactory completion of the work item.

v1.0 Page 10 of 112

Generic Service Actions

Whenever the following action terms appear in the SOW or herein with bold letters the corresponding definitions below apply, otherwise use dictionary definitions and the surrounding context to define them.

Action Definition

Provide This is to furnish a supply item or service item; all associated incidental/overhead activities (general & administrative, procurement, shipping, handling, disposal of associated containers/waste, etc.) must be included.

For sub-contracted services, the provider must oversee/supervise the sub-contractor and be responsible for all their associated and incidental actions/waste/etc.

Perform Carry out, accomplish, or fulfill the designated service; Comply with the associated requirements.

Comply Act in accordance with all designated document(s). The document(s) will contain requirements that must be followed while performing tasks specified in the SOW or herein.

These designated document(s) generally describe mandatory procedures for performing maintenance actions, provide configuration specifications, or specify standards and specifications for performing work.

Conform Act in accordance with all specified or applicable rules, standards, regulations, laws, statutes, etc.

These are generally requirements that are incidental to the maintenance tasks being performed.

Rip-out This means to remove and properly dispose of the designated item(s) (e.g., part, component, equipment, etc.).

Install This means to place or fix the designated item (or items, e.g., part, component, equipment, etc.) in its final position in the system. If that item is not designated as GFP in the work item or a CR/mod, then Provide that item.

Remove/Reinstall This means to take the designated item (or items, e.g., part, component, equipment, all associated sub-components, etc.) away or off from its position occupied in the system. Retain that item for reinstallation later back into the system. Perform any designated tasks on that item and take all necessary precautions to prevent damage to that item in the interim. Then place or fix the designated item in back position within the system again; restore it to its prior configuration with all prior functionality.

Package This means to completely prepare the designated item (or items, e.g., part or parts, component or components, equipment, all associated sub-components, etc.) for shipment.

Refer Read or otherwise use the specified document(s) as a source of information, guidance, advice, etc.;

consult. The document(s) may contain suggested procedures, best practices, expected configuration descriptions, etc., but it is the obligation of the reader to select the best, most appropriate action/requirement/task/etc. in the context of 1) all available information, 2) the particular circumstances, and 3) the actual requirements specified in the SOW/WISS/Law/Regulation/Statute/etc.

Generic Administrative Actions

Whenever the following action terms appear in the SOW or herein with bold letters the corresponding definitions below apply, otherwise use dictionary definitions and the surrounding context to define them.

Action Definition

Submit Communicate the information described in the task to the COR/KO in an appropriate document format that can be used as evidence of the communication later (e.g., photo-image, fax, written report, e-mail, letter, etc.).

Attend This means to be present at the designated event or meeting.

v1.0 Page 11 of 112

Generic Administrative Actions

Whenever the following action terms appear in the SOW or herein with bold letters the corresponding definitions below apply, otherwise use dictionary definitions and the surrounding context to define them.

Action Definition

Notify This means to formally/officially advise the COR or KO, as designated in the SOW, of proposed details and scheduling of a designated event, and then only finalize the scheduling of that event after the COR concurs with that proposal.

Submit the designated information. Wait for confirmation of receipt and concurrence (i.e., do not proceed without an affirmative response from the Coast Guard).

Notification must occur at least 24 hours prior to events that require Coast Guard personnel witness or verification. If such an event will occur more than 50 miles from the primary location of contract performance, then provide at least 3 working days notice. Do not proceed without Coast Guard personnel being present.

Verify Establish the truth, accuracy, or reality of a condition or an action, prior to proceeding to the next step.

000c General Administrative Items

ARRIVAL CONFERENCE – This is an in-person meeting, phone-conference, or combination of both that is planned and scheduled by the KO/COR and occurs after contract award and prior to the start of contract work. In-person 5 meetings may either convene onboard the vessel or near the vessel at the CONTRACTOR’s conference facilities. A letter containing an agenda for meeting will be sent to the CONTRACTOR.

In addition to other agenda items, the following fire prevention and fire response topics must be discussed/addressed and a:

• Fire alarm and response procedures 10

• Firefighting jurisdictional cognizance

• Installation or municipal fire and emergency services firefighting capability and procedures

• CONTRACTOR communication system for fire reporting and control or firefighting efforts

• Shipboard arrangement including access routes, availability or firefighting systems (installed and temporary), and communication systems 15

• Shipboard firefighting organization, systems, drills, and equipment

• Compatibility of vessel, CONTRACTOR, and/or region/installation or municipal fire and emergency service’s firefighting equipment

(General Requirements (All Contracts))

CFR – This is a “condition found report”; they are generally used to document discrepant conditions on vessels, but may be used to submit measurements, certify satisfactory completion of a task such as a test, etc. CFRs should be in electronic format whenever possible, and should be submitted within 24 hours after completing the task that requires documentation (e.g., after completing an Inspect/Op Test (Final) on a particular system, etc.).

((General Requirements (All Contracts)) | Maintenance Work Item) 25

CIR – This is a type of CFR that must be submitted within the first 25% of the contract performance period so that repairs can be authorized and performed in a timely manner that supports contract/project schedule. CIRs generally must be submitted immediately after conducting inspections/tests that are intended to reveal discrepancies that must be corrected prior to completing the work item. 30

((General Requirements (All Contracts)) | Maintenance Work Item) v1.0 Page 12 of 112

ENVIRONMENTAL PROTECTION PLAN – This is a document that outlines how hazardous materials, petroleum products, hazardous substances, hazardous wastes, and other solid wastes will be handled.

The intent is to encapsulate all environmental-related documentation in one document (or set of documents), the ENVIRONMENTAL PROTECTION PLAN. Submit the first version (version 1) pre-award or at the ARRIVAL CONFERENCE, as directed in the SOW. This document is maintained 5 throughout the contract performance period by the Contractor.

Then, as the contract progresses, and previous environmental regulation compliance documents are edited, or as new documentation is generated, append those documents to the ENVIRONMENTAL PROTECTION PLAN and resubmit the entire plan as a new/most-accurate version (e.g., version 2, version 3, etc.). 10 The last version submitted must be a complete record of all environmental regulation compliance actions.

Contact Kyle Klinedinst Kyle.C.Klinedinst@uscg.mil (717) 856-6953 with questions.

The ENVIRONMENTAL PROTECTION PLAN must be maintained (i.e., edited, and resubmitted whenever one of the required elements below changes during contract execution). The final version of the ENVIRONMENTAL 15 PROTECTION PLAN must serve as a record of all related actions taken during the contract performance period.

The ENVIRONMENTAL PROTECTION PLAN must Comply with all requirements within all Federal, state, and local regulations, the plan must address/describe, at a minimum, the following (use these headings in the plan for clarity):

General 20

• GENERAL STORAGE SITE PLAN - describe/show where hazardous materials will be properly staged and/or stored

• WASTE COLLECTION AND CONTAINMENT PROCEDURES – describe how waste will be contained and collected following requirements of 49 CFR 178.

• HAZARDOUS MATERIAL (HM) SPILL AND CLEANUP PLAN - describe tools and materials that will be on hand 25 and readily available to facilitate containment and cleanup.

• HAZARDOUS WASTE (HW) MANAGER – provide training certifications for the Contractor's hazardous waste manager and all personnel conducting hazardous waste activities.

• HW IDENTIFICATION METHODS – describe methods that will be used to analyze and identify whether or not generated material (blasting debris, paint waste, etc.) are hazardous wastes. 30

• HW LICENSES AND PERMITS – provide all documents that are required to be obtained or currently held by the Contractor as prescribed by Federal, state, and local regulations, including Contractor’s EPA Generator

ID#.

• AIR DISTRICT PERMITS – provide all documents required to be obtained or currently held by the Contractor as prescribed by Federal, state, and local regulations. 35

• OTHER PERMITS – All permits required by the National Pollutant Discharge Elimination System (33 U.S.C.

1342) to be obtained or currently held by the Contractor as prescribed by Federal, state, and local regulations.

Contract/Project Specific

• HM/HW LIST - A list of all anticipated solid waste, trash/debris, hazardous wastes that will be generated 40 and a Federal/state/local regulation cross reference list that will impact proper disposal, and copies of the analysis of all Hazardous Material (HM) or Hazardous Waste (HW) disposal samples taken and results.

o When performing HAZARDOUS MATERIAL ABATEMENT (e.g., LBPs removal, ACMs removal, etc.)

include the following, as applicable:

Copies of all HM sample results prior to commencing work. 45 Results of all air monitoring samples to the COR within 24-hours of completing the sampling, or upon receipt of the laboratory test results.

All notices to the EPA, as required by 40 CFR 61.145 and other applicable state and local agencies, prior to commencing asbestos removal work.

Documentation that certifies all primary and sub-contractors fulfilling abatement requirements 50 possess all local, state, and federal certification licenses and applicable permits, for fulfilling those abatement requirements.

A report containing the LBP sample results.

A report containing the “aggressive air sample” results.

v1.0 Page 13 of 112

• OTHER PERMITS/LICENSES/ETC. – submit a copy of the applicable EPA and/or state permit(s), manifest(s), or license(s) for transportation, treatment, storage, and disposal of hazardous and regulated waste by permitted facilities

• OTHER PLANS – provide all other applicable facility response plans (OIL SPILL PLAN, etc.), required by Federal, state, or local requirements 5

• HVAC/REFRIDGERANT CERTS - A copy of all heating and air conditioning servicing technician EPA certifications prior to the initiation of work.

o Whenever reclaimed refrigerant is used, submit proof that the refrigerant meets the relevant standard of purity.

• EPA NOTIFICATIONS - copies of all notifications, required by EPA (NATIONAL EMISSION STANDARDS FOR 10 HAZARDOUS AIR POLLUTANTS), that have been or will be provided to any regulatory authority for work on board the vessel (within 48 hours of providing such notice to the regulatory authority)

• WHEN AT A COAST GUARD FACILITY

o RESERVED (General Requirements (All Contracts)) 15

ELECTRICAL PLAN – This is a document containing the following elements, as applicable, and all other appropriate information that will demonstrate that the risk of damage to Coast Guard assets will be mitigated. Separate diagrams must be included for waterborne and non-waterborne/dry-docked periods.

• a one line electrical diagram showing how ungrounded shore power will be supplied, including the winding 20 and grounding configuration and rating of any generator or isolation transformer.

• a diagram showing the general proposed location of each electric arc welding machine, the grounding configuration of each machine, and the return current conductor size and length.

• a diagram showing how hull grounding straps will be installed, how they will be sized (length and gauge) and connected for work periods while the vessel is not waterborne (see TEMPORARY INSTALLATION AND 25 REMOVAL OF HULL GROUNDING STRAPS (863a)).

• a diagram showing how tool and equipment power will be supplied and distributed for dockside and shipboard use. If the source of power is to be a temporary generator, include its weight, fuel tank capacity, fuel consumption rate, and footprint, including any safety zones required to keep personnel from contacting hot surfaces or exceeding hearing protection thresholds. Identify the expected loads, grounding 30 scheme, proposed locations of temporary electrical power distribution equipment, and sources of power.

(General Requirements (All Contracts))

PLANNING DOCUMENT – This is a graphical document (e.g., Gantt Chart, etc.) showing work scheduling, it does not need to be created specifically for submission to the Coast Guard (i.e., may be a copy of the CONTRACTOR’s already 35 existing internal scheduling document).

The PLANNING DOCUMENT must:

• Show the overall duration for each CLIN, with start and stop dates of major tasks and sub-tasks.

• Show the due dates for Critical Inspection Reports (CIR)

• Show events requiring COR or Coast Guard Inspector presence. 40

• Show all time periods that require sub-contracted services (e.g. OEM Tech Rep assistance, etc.)

• Identify the critical path(s) for the project

• Identify the projected best-case project completion date

• Identify the contract performance period end date

• Show the number of days available for schedule slip without negatively impacting delivery date. 45 v1.0 Page 14 of 112

• Include a list of names, contact information, and written commitment from all subcontractors and required Tech Reps indicating they are available for work during the proposed time period.

• Include a list of all instruments (i.e. instrument name, valid calibration date, work item(s) where the instrument will be used, etc.) that will be used for inspections and tests.

(General Requirements (All Contracts)) 5

FIRE PREVENTION AND RESPONSE PLAN – This document must describe how the risk of fire, and the damage caused by fire, will be mitigated. The FIRE PREVENTION AND RESPONSE PLAN must contain the following data/representations, and all other relevant information; the plan must be revised/amended, resubmitted, and approved by the COR in advance of any change that will affect the accuracy of the data/representations contained 10 therein.

• the name/contact info (e.g. business phone number, personal phone number, etc.) of each employee designated as a “Fire Prevention Supervisor”

• when the vessel will be berthed or drydocked at a Contractor’s facility provide the facility’s Fire Safety Plan document described in 29 CFR 1915.502 Fire Safety Plan. Also include a description of 1) who will fight a fire 15 and what equipment will be used, 2) the location of where all manual disconnects/breakers for all temporary power sources (e.g., shore-tie, portable generators, etc.) will be located relative to the vessel accesses/gangways/brows.

• a list of the vessel’s “Fire Detection/Alarm Systems” (000d) components that must be temporarily disabled or secured in order to complete the contract requirements; and a description/proposal of how the functionality of 20 those components will be temporarily substituted/supplemented (see TEMPORARY FIRE SAFETY SUPPLIES/SERVICES below).

• a list of the vessel’s “Fire Fighting/Dewatering System” (000d) components (e.g., firemain pumps, portable fire extinguishers, halon and AFFF systems, etc.) that must be temporarily disabled or secured in order to complete the contract requirements; and a description/proposal of how the functionality of those components will be 25 temporarily substituted/supplemented (see TEMPORARY FIRE SAFETY SUPPLIES/SERVICES below).

• a description of 1) when shipboard “Fixed Fire Fighting Systems” (000d) will be online or offline, 2) how temporary systems will integrate with shipboard systems if this will be necessary, 3) how the temporary systems will be tested, the frequency of tests, 4) how the vessel’s temporary functional alarms and communications that are used during shipboard emergencies will be maintained/supplemented,. 30

• a list of every fitting (e.g., door, hatch, scuttle, etc.) that will be made inoperable (i.e., cannot be easily and rapidly closed or secured to stop air flow during a fire, or cannot be easily fully opened as an escape route in the event of a fire, etc.) during the execution of the contract. Describe how the risks caused by each inoperable fitting will be mitigated (e.g., use of quick-disconnect fittings on hoses/cables to allow rapid fitting closure, use of fire curtains in Fire Zone Boundary openings, fitting will be made clear/operable whernever left 35 unattended or at the end of each shift by removing hoses/cable/etc., etc.)

• A list of every breach that will be made to any “Fire Zone Boundary” (e.g., hull access cuts through a boundary, removal of sea valves or piping that will allow air a new path to flow across a boundary, etc.). Also describe the methods that will be used to temporarly seal or slow down air flow across these breaches when they are left unattended or in the event of a fire. 40

• A description of escape routes in the event each installed “Fixed Fire Fighting System” (000d) is activated.

• Procedures that have been developed to properly enable/disable systems that, when discharged, are immediately dangerous to life/health (e.g., CO2 total flooding systems, etc.)

(General Requirements (All Contracts))

SEVERE WEATHER PLAN – This document describes the actions that must be taken to mitigate the risk of damage to a Coast Guard asset in the event of severe weather. This document must contain the following data/representations, and all other appropriate information.

https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1915/subpart-P/section-1915.502 v1.0 Page 15 of 112

WEATHER

CONDITION

(As determined by the CO of the vessel)

Approx.

Arrival Time (hours)

ACTION

GALE STORM/

HURRICANE/

TYPHOON

IV 74 Review hazardous/destructive weather implementation plan.

III 48 Take preliminary precautions.

II 24 Take precautions to permit establishing an appropriate state of readiness on short notice.

I 12 Take appropriate precautions to minimize damage.

THUNDERSTORM/

TORNADO

(Lightning and thunder anticipated)

II 6 Take precautions to permit establishing an appropriate state of readiness on short notice.

I 0* Take appropriate precautions to minimize damage.

Trend indicates a possible threat of destructive winds within the number of hours shown.

Destructive winds accompanying the phenomenon are reported or expected in the general area within the number of hours shown.

*IMMINENT

• a description of all actions that will be taken at each Weather Conditions Level, with a responsible party 5 assigned to each action

• the name/contact info (e.g. business phone number, personal phone number, etc.) of the Contractor’s employee who will execute Severe Weather Plan Supervisor duties, who the vessel’s CO will call whenever a weather-related action must be taken.

• each step that will be taken to secure or remove all Contractor-furnished items and equipment (e.g. staging, 10 generators, welding machines, cranes, etc.).

• each step that will be taken to secure and safeguard all Government owned properties (e.g. removed interferences, GFP, MTI items, etc.)

• a description of how the vessel will be protected from other floating items (e.g. barges, doughnuts, work floats, other vessels, etc.). 15

• a description of how all emergency services will be provided (e.g. security, fire protection, flooding protection, shipboard dewatering and fire main capability, electrical power generation, communications, etc.).

• a description of how the vessel will be secured to the pier or drydock, including the following:

o Size, type, and number of lines.

o A sketch, showing location of all securing devices (e.g. fenders, bumpers, camels, etc.) 20 o How tension and slack in lines will be monitored during heavy weather.

o How all openings will be made watertight.

• how floating pier (if installed) will be secured during high winds or high tides.

v1.0 Page 16 of 112

000d Ancillary/Collateral Work

000 Configuration Item Classes

Particular vessel configuration items designated in the SOW may belong to one or more the classes described below;

determine the applicable classes, then conform to the corresponding requirements for those classes as they apply to the tasks designated in the SOW.

Class Definition

“Consumables” Parts or components that are generally made from relatively soft materials that are designed to wear, or tend to wear, significantly faster than surrounding/mating parts.

These softer less durable parts are not intended to last the service life of the parent component/assembly. Examples include seals, gaskets, o-rings, bearings, bushings, wear strips, self-locking fasteners with soft parts that deform at installation, etc.

“Disturbed Consumables” These are “Consumables” that have been removed or have otherwise been made accessible or are otherwise exposed during the process of disassembly or interference removal, while performing a task.

“Interferences” Any part of a vessel, whether permanently installed or portable, that must be moved, isolated, or disturbed so that the work specified in a work item may be accomplished;

these may include machinery, piping, ducts, wiring, insulation, structure, and anything else which interferes with proper/safe accomplishment of a work item.

These also include items that may have been necessarily, or inadvertently, damaged during disassembly (e.g., paint/coatings, insulation material, seals/gaskets/o-rings, etc.).

“Restricted Interferences” “Interferences” that are vital to the health, well-being, and feeding of the vessel’s crew that, if removed, will result in a dangerous or hazardous condition to the vessel or the environment.

All firefighting equipment (e.g., extinguishers, alarms/detectors and associated cables, etc.)

“Fire Zone Boundary” A fire zone boundary is a permanent, continuous, interior bulkhead or deck that will limit the passage of flame/smoke/air. All closable “Fittings” (100a) that are part of the bulkhead/deck are considered part of the boundary.

A Fire Zone Boundary is breached when

Unless otherwise specified elsewhere in the SOW, treat all watertight bulkheads and decks, and all associated “Fittings” (100a) as Fire Zone Boundaries.

“Fire Detection/Alarm Systems”

These are all vessel installed systems with various sensors (e.g., heat, smoke, etc.) and alarms (e.g., bells, horns, cell phone callers, etc.) designed to alert personnel when an unintentional fire has been detected.

“Fire Fighting/Dewatering Systems”

These are all vessel installed systems/equipment (e.g., piping, hoses, pressure vessels, valves, electrical sensors/controls, etc.) designed to hold and disburse various firefighting agents (e.g., firemain sea water, halon…