ATTACHMENT-3_TECHNICAL_EVALUATION_FACTORS.pdf
PDF 217 KB Posted
- Attached to
- DRYDOCK USCGC BLUE SHARK Federal contract opportunity
- Solicitation number
- 70Z080-19-Q-P4500700
About this file
Attachment-3 Technical Evaluation Factors for USCGC BLUE SHARK DD
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MTU_F_A_771903_(2).pdf | ||
| 4499_243_A.pdf | ||
| SF30_AMEND_A00001_RFQ_70Z080-19-Q-P4500700_BLUE_SHARK_DD.pdf | ||
| REQUEST_FOR_CLARIFICATION_01_BLUE_SHARK.pdf | ||
| SOLC_BLUE_SHARK_DD_100118_-_COMB_SYNOP_NMB.pdf | ||
| ATTACHMENT-2__STATEMENT_OF_WORK__USCGC_BLUE_SHARK_DRYDOCK_87360_Rev0_10Jul18.pdf | ||
| ATTACHMENT-1__Schedule_for_BLUE_SHARK_DD.xls | XLS spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL EVALUATION FACTORS
USCGC BLUE SHARK (WPB-87360)
DRYDOCK REPAIRS
70Z080-19-Q- P4500700
ATTACHMENT-3
Technical Acceptability will be evaluated to determine an overall rating. This will be determined by evaluating the technical factors and the Offeror’s ability to provide a sound, compliant approach that meets all requirements listed in the Specification and demonstrates a thorough knowledge and understanding of the requirements. It is the contractor’s responsibility to ensure that their quote clearly demonstrates their ability to perform these requirements. All offerors must provide the following information and documentation with their quotes to be considered technically acceptable:
1. General Technical Approach
Submit a brief overview planning document in accordance with SFLC Std Spec
0000 that outlines the strategy for ensuring that this requirement is completed on or before the contract completion date. The planning document shall include at least:
1) Proposed schedule, resources, completion-dates, float, and major millstones for the various tasks required to complete this contract and
2) Identify a list of items that may pose the most contract schedule risk and approach to mitigate or eliminate each risk.
2. Welding Welding Certifications/Procedures
Submit welding documentation (e.g. WPSs, welder certs, etc.) in accordance with
SFLC Standard Specification 0740, specific to your internal or subcontracted staff for the weld joints that will be installed.
3. Preservation Coatings Certification Requirements
Submit a description of how you intend to meet SFLC Standard Specification
0000 coatings QC/QA requirements for this contract. This plan must include the names of any subcontractors and resumes for any proposed QP1 certified painters and/or independent NACE CIP Level 3 inspectors.
4. HVAC Repairs Environmental Protection Compliance Submit a resume with documentation of Environmental Protection Agency (EPA) certification for each servicing technician IAW SFLC Standard Specification
0000, Appendix A & B (e.g. résumé w/photo-copy of cert card, etc.).
TECHNICAL EVALUATION FACTORS
USCGC BLUE SHARK (WPB-87360)
DRYDOCK REPAIRS
70Z080-19-Q- P4500700
ATTACHMENT-3
5. Dry Dock Dry Dock Certifications and Pre-Award Calculations Submit all documents specified under “3.5.1 Pre-award events” in SFLC Standard
Specification 8634 (e.g. dry dock facility certifications, pre-award calculations, etc.).
USCG Surface Forces Logistics Command (SFLC) Standard Specifications associated with the Vessel’s Specification can be found at the following website:
http://www.dcms.uscg.mil/Our-Organization/Assistant-Commandant-for-
Engineering-Logistics-CG-4-/Logistic-Centers/Surface-Forces-Logistics-
Center/Contracting-Links/Standard-Specifications/ http://www.dcms.uscg.mil/Our-Organization/Assistant-Commandant-for-Engineering-Logistics-CG-4-/Logistic-Centers/Surface-Forces-Logistics-Center/Contracting-Links/Standard-Specifications/ http://www.dcms.uscg.mil/Our-Organization/Assistant-Commandant-for-Engineering-Logistics-CG-4-/Logistic-Centers/Surface-Forces-Logistics-Center/Contracting-Links/Standard-Specifications/ http://www.dcms.uscg.mil/Our-Organization/Assistant-Commandant-for-Engineering-Logistics-CG-4-/Logistic-Centers/Surface-Forces-Logistics-Center/Contracting-Links/Standard-Specifications/
File details come from the government source that posted it.