This document provides responses to questions regarding Request for Quotation (RFQ) 70Z03824QK0000024 issued by the United States Coast Guard (USCG) for a Fluorescent Penetrant Inspection (FPI) Wastewater Treatment System with Closed-Loop Water Recycler (WWTS). The RFQ requires the purchase, installation, and start-up support of the WWTS in Elizabeth City, North Carolina. The USCG estimates an annual consumption of 25 gallons of the raw penetrant and provides details on the typical tanks and process flow for the FPI line. The RFQ is a 100% small business set-aside, with a required delivery date of September 26, 2024 and an anticipated award date on or about July 12, 2024. The solicitation includes a Statement of Work, evaluation criteria, and applicable clauses, and requires email quotations to be submitted by July 5, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Responses to Questions Amend 3.pdf | ||
| Responses to Questions Amend 1.pdf | ||
| Statement of Work (SOW).pdf | ||
| SOW Attachment 1 ALC Visitor Contractor Brochure.pdf | ||
| SOW Exhibit 1.pdf | ||
| Terms and Conditions.pdf | ||
| Schedule of Supplies and Services.xlsx | XLSX spreadsheet | |
| Notification of Services Rendered Form.pdf | ||
| Instructions to Offerors.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70Z03824QK0000024
Responses to Questions
Amendment 2 Answers provided 2 July 2024
This document provides United States Coast Guard (USCG) responses for questions that have been asked regarding request for quotation (RFQ) 70Z03824QK0000024. Question numbers are provided simply as a reference and in no way infer a prioritization of the questions.
Number Question USCG Response 1 Estimate of annual consumption (gallons/year) of the raw penetrant by the inspection process line?
25 gallons per year (estimated by draw out and product replacement every year)
2 Base material of parts to be processed? Aluminum, Magnesium, Stainless steel, Titanium
3 Size of largest part? 2ft wide by 3ft long
4 Parts per day to be processed? Average 25 parts per day
5 Basic description of the tanks in the penetrant line?
Typically, as follows:
Tank 1 – Penetrant Tank 2 – Dwell Tank 3 – Rinse (immersion or spray?)
Tank 4 – Emulsifier (If the process is post emulsifiable, or PE) Tank 5 – Rinse (immersion or spray?)
Tank 6 – Dryer Tank 7 – Developer
**Note: If this is a water washable application, omit Tank 4 and Tank 5.
Tank 1 -Penetrant Tank 2 -Dwell Tank 3 -Emulsifier Tank 4 -Dwell Tank 5 -Rinse Tank 6 -Dryer Tank 7 -Developer Tank 8 -Inspection Booth
Type 1 Post-Emulsifiable Lipophilic Method B
PLEASE REFER TO THE SOLICITATIONS ATTACHMENT 1 “INSTRUCTIONS TO OFFERORS”
FOR A COMPLETE LIST OF THE SALIENT CHARACTERISTICS AND REQUIREMENTS.