Amendment 2 70FB8027Q00000003 Gov Responses.pdf

PDF 73 KB Posted

Attached to
Transportable Temporary Housing Unit (TTHU) Retro Fit Shower and Accessories Installation Kits
Solicitation number
70FB827Q00000003
Issued by

About this file

This document is a Question and Answer (Q&A) clarification response issued by the Government for federal contract solicitation 70FB8027Q00000003, Amendment 2, regarding the supply of retrofit shower installation kits for FEMA.

The solicitation involves two primary shower kit configurations: a 60x30-inch kit (CLIN 1) and a 36x36-inch kit (CLIN 2), with pricing evaluated on a Lowest Price Technically Acceptable (LPTA) basis. The kits include shower enclosures, grab bars, curtains, rods, and installation materials, with specifications detailed in the revised Attachment 1 Statement of Work. The Government clarified that the NextGen Retrofit Shower Drawings referenced in the SOW will not be provided; quoters must price items as specified in Amendment 1 Attachment 1. Key specifications addressed include drain locations (60x30 kit requires a right-drain Bestbath model 5LBS6030E75B or equal), grab bar dimensions (straight 24-inch stainless steel bars), and packaging requirements (each complete kit must be contained in one package with all items in original factory packaging). Pricing is submitted on Attachment 4, which contains formula corrections issued in Amendment 1; the 3.8% annual escalation for option-year unit prices is built into the revised pricing table. The question deadline was October 30, and offers are due November 13, 2026, at 1:00 PM ET. Payment will be made for items accepted by the Government in accordance with the Prompt Payment Act (31 U.S.C. 3903). The Government confirmed that offerors with no past performance will not be negatively rated and remain eligible for award consideration. Delivery is required within 30 calendar days after order placement (per Amendment 2 updates), and independent product resellers may remain the contracting seller while manufacturer-assembled kits are shipped directly to FEMA, provided the reseller remains responsible for deliverable quality.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# Question/Clarification Government Response

Attachment 4 (Pricing Table) appears to have formula errors. Cell J4 (CLIN 2 shipping, Option 1 unit price) is hard-coded to 0 instead of escalating from the base price, so all CLIN 2 option-year shipping prices calculate to $0. Cell Q5 (CLIN 3, Option 3 total) is hard-coded to 15 instead of quantity x unit price. Cell G7 in the Total row contains a pre-filled value of 307.16. Can the Government issue a corrected pricing table, or confirm how these cells should be treated?

A revised Attachment 4 was issued on the SAM on October 27, 2026, under Amendment 1 -

70FB8027Q00000003.

Attachment 4 automatically escalates option-year unit prices by 3.8% per year (=prior year x 1.038). Is this escalation mandatory, or may offerors enter their own option-year unit prices?

A revised Attachment 4 was issued on SAM on October 27,2026, under Amendment 1_

70FB8027Q00000003.

Attachment 1 (SOW), Section 3 / CLIN tables: for "or equal" kits (Best Bath 5LBS6030E75B and 4LBS3636B5B), what documentation must be submitted with the quote to show equivalency? Also, the SOW references the FEMA NextGen Retro Fit Shower Drawings, which are not posted. Can those drawings be provided?

The drawings are not required. Quoters shall provide prices for all times included in the Amendment 1_ 70FB8027Q00000003 - Attachment 1 - Statement of Work in accordance with the Amendment 1_70FB8027Q000000003 - Attachment 4 Pricing Table.

Drain location, 60x30 kit: SOW section 3.2, item 1.1 calls for a right drain, while Attachment 4, CLIN 1 lists both "center drain" and drain location "Left." Which is required?

A revised Attachment 1 - Statement of Work was issued on SAM on October 27, 2026, under Amendment 1_70FB8027Q00000003 which includes the items specifications.

Grab bars: the SOW lists straight 24" stainless grab bars (two for the 60x30 kit; one 24" and one 12" for the 36x36 kit). Attachment 4 lists "2 Grab Bars (48" x 24")" for both kits.

Which governs?

A revised Attachment 1 - Statement of Work was issued on SAM on October 27, 2026, under Amendment 1_70FB8027Q00000003 which includes the items specifications.

Curtain and rod, 36x36 kit: the SOW calls for a 42" x 74" curtain and a 37.5" rod;

Attachment 4 lists 66" x 74" and 59.5". Which governs?

A revised Attachment 1 - Statement of Work was issued on SAM on October 27, 2026, under Amendment 1_70FB8027Q00000003 which includes the items specifications.

Attachment 4 includes a 3" flange trim kit and "installation materials," which are not in the SOW list. Should they be included, and what should "installation materials" cover?

A revised Attachment 1 - Statement of Work was issued on SAM on October 27, 2026, under Amendment 1_70FB8027Q00000003 which includes the items specifications.

SOW section 2 refers to the FEMA NextGen Retro Fit Shower Drawings, which are not in the package. Can FEMA share them, or confirm that the SOW is sufficient to judge "or equal" products?

The Drawings will not be shared. Quoters shall provide pricing for the items in included with Amendment 1 - 70FB8027Q00000003 - Attachment 1 Statement of Work.

Past performance: an offeror with no past performance "will not be rated." For this LPTA award, will such an offeror be considered acceptable on that factor? An offeror with no past performance will not be negatively rated.

Closing time: SAM.gov shows November 13 at 1:00 PM ET, and Attachment 3 says 10:00 AM ET. Which applies? A revised Attachment 3 - Past Performance Questionnaire was issued under Amendment 1 -

70FB8027Q00000003. The Quote submission date is November 13, 2026, 1:00PM ET.

Attachment 4 formulas: the base-year totals (H3:H6) are blank, J4 is set to 0 so option-year shipping for the 60x30 kit calculates to $0, Q5 holds a fixed 15, and G7 holds 307.16.

May offerors correct these formulas, and must option-year prices follow the built-in 3.8% yearly increase?

Amendment 1_70FB8027Q00000003 Attachment 4 - Pricing Table was issued under Amendment 1 - 70FB8027Q00000003 on October 27, 2026.

For the 60x30 shower, the SOW specifies a right-hand drain, while the pricing table mentions both center and left drain. Which configuration governs, and can you provide the referenced NextGen drawings?

A revised Attachment 1 - Statement of Work was issued on SAM on October 27, 2026, under Amendment 1_70FB8027Q00000003 which includes the items specifications.

The two attachments also differ on grab-bar sizes and several accessories, including the curtain/rod for the 36x36 kit. Please confirm the controlling complete bill of materials and any revised pricing table.

A revised Attachment 1 - Statement of Work was issued on SAM on October 27, 2026, under Amendment 1_70FB8027Q00000003 which includes the items specifications.

Are the quantities of 15 in the pricing table evaluation estimates, or will any quantity be ordered at award? Is any minimum purchase guaranteed under a BPA?

The quantities of 15 in the pricing table are evalution estimates. These quantities will not be ordered at award. No, there is no minimum purchase guaranteed under a BPA. The Government is only obligated to the extent that authorized orders are placed under BPAs.

May a product reseller propose manufacturer-assembled kits shipped directly to FEMA, with each complete kit in a single protective container on pallets? Is any onsite installation or labor required from the supplying vendor?

Yes, manufacturer-assembled kits may be shipped directly to FEMA; however, the BPA awardee is still responsible for the quality of the deliverables.

Attachment 2 permits stating that no recent relevant past performance exists and says such a vendor will not be rated. Can that vendor still be eligible for an acceptable award determination, and may documented manufacturer fulfillment capability support the technical evaluation?

Yes, a vendor can still be eligible for an acceptable award determination with no past performance. Past Performance shall be submitted in accorddance with Amendment 1_70FB8027Q000000003-Attachment 2 Terms and Conditions FAR 52.212-1 INSTRUCTIONS

TO OFFERORS – COMMERICAL PRODUCTS AND COMMERICAL SERVICES. (AUG 2025)

(DEVIATION 25-21). Volume II - Past Performance. The Quoter shall provide a maximum of three (3) CPARS or PPQs.

Please confirm the applicable solicitation number, current amendments, October 30 question deadline, November 13 offer deadline and payment timing after delivery/acceptance.

The solicitation number is 70FB8027Q00000003. Amendment 2. The question deadline was October 30. Payment Timing and delivery/acceptance is in accordance with the Amendment 1_70FB8027Q00000003 Attachment 1 Terms and Conditions clause 52.212-4 CONTRACT

TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES.

(DEVIATION 25-21) (AUG 2025); including but not limited to: (i) Payment - (1) Items accepted.

Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract. (2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act ( 31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.

Q&A 17/30 removes the ADA-certified-model requirement, while revised Attachment 2's technical quote/evaluation paragraphs still reference A117.1, UFAS and ADA. What evidence must the compliance matrix provide for the named configurations under the revised requirement?

The revised Amendment 1 - 70FB8027Q00000003 - Attachment 2 Terms and Conditions struck through to remove the A117.1, UFAS and ADA and the matrix requirements. Quoters Techincal Quote shall be submitted in accordance with Amendment 1_70FB8027Q00000003 - Attacment 2 Terms and Conditions clause FAR 52.212-1 INSTRUCTIONS TO OFFERORS – COMMERICAL

PRODUCTS AND COMMERICAL SERVICES. (AUG 2025) (DEVIATION 25-21).

May an independent product reseller remain the contracting seller/payee while a documented manufacturer or qualified fulfillment supplier consolidates each complete kit into its single protective container and ships directly to FEMA? We would document the source, components and packing arrangements; no stock or supplier authorization is yet secured.

Yes, an independent product reseller can remain the contracting seller while the deliverables are shipped to FEMA directly from the production/packaging facility; however, the reseller the BPA remains responsible for the quality of the deliverables.

The revised billing instructions allow invoicing after delivery/acceptance and say payment will be no more frequent than monthly. What payment due period and acceptance/proper-invoice event should be used to assess the cash gap?

The Amendment 1_70FB8027Q00000003 Attachment 1 Terms and Conditions clause 52.212-4

CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL

SERVICES. (DEVIATION 25-21) (AUG 2025); including but not limited to: (i) Payment - (1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract. (2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act ( 31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.

Revised SOW Section 5 requires delivery within 30 calendar days after each order. Our current supplier advises a 6 to 8 week lead time for a 30-kit order. May an offer expressly propose that lead time for a larger initial release, or is delivery within 30 days mandatory for every order regardless of quantity?

See Amendment 2_70FB8027Q00000003 Attachment 1 Statemetn of Work for updated delivery requirements.

For the 60 x 30-inch shower kit, the amended Statement of Work (Section 3.2) specifies a right-drain, Bestbath model 5LBS6030E75B or equal. The Attachment 4 Pricing Table appears to describe a different drain configuration. Which drain location is controlling for pricing and delivery?

The Amendment 1_70FB8027Q00000003 Attachment 1 Statement of Work Section 3.3 describes the specifications for the 60x30-inch shower and kit. The Amendment 1_70FB8027Q00000003 - Amendment 1 Attachment 4 Pricing Tables was revised to reference the SOW Section which details the requirements for the items and shipping/delivery requirements.

The accessories in the SOW Section 3.2 differ from elements described in Attachment 4, including grab-bar lengths and shower-seat type/dimensions. Should offerors furnish and price the precise accessory schedule in SOW Section 3.2, the component descriptions in Attachment 4, or a revised consolidated kit bill of materials? Could FEMA provide a controlling bill of materials for both the 60 x 30 and 36 x 36 kits?

The Amendment 1_70FB8027Q00000003 provided revised Attachment 1 Statement of Work and Attachment 4 Pricing Table.

The SOW refers to NextGen Retrofit Shower Drawings that are not included in the documents we obtained. Are those drawings available for prospective offerors? If so, please advise how to access them and whether they govern dimensions, drain placement, or attachment details.

No, the NextGen Retrofit Shower Drawings will not be provided. Quoters shall quote the items included in Amendment 1_70F8027Q00000003 - Attachment 1 Statement of Work.

For the packaging requirement that each complete installation kit be packed in one container, can the shower enclosure remain in its original multi-piece factory packaging and travel secured with separately boxed accessories as one clearly labeled handling unit, or is one outer shipping container mandatory?

The Statement of Work requires each item, including the shower, to remain in their original factory packaging, then the complete items in each kit to be contained in one package. The intention of the government’s requirement to package the complete installation kit is to ensure readiness at the storage site for when the kit is needed for use, which might require transportation to anywhere in the US. The government is not dictating the type or specification of the packing material used for the installation kit.

Amendment 2

File details come from the government source that posted it. Updated .