This is Addendum No. 2 issued by the Port Authority of New York and New Jersey on May 22, 2026, modifying contract documents for HT-224.228, which concerns the installation of a storage facility for flood protection equipment at the Holland Tunnel in Jersey City, New Jersey. The addendum requires all bidders to physically annex or electronically attach the document behind the last page of the contract booklet and initial it before submission. The addendum replaces page 12 of the original contract booklet entirely with new specifications. Prospective bidders may arrange site inspections by contacting Kenneth Wright at (973) 418-3774 or kwright@panynj.gov. Questions regarding contract requirements must be submitted to Megan Lancelot-Zielinski at (212) 435-5694 or mlancelotzielinski@panynj.gov no later than 5:00 PM seven calendar days before the bid due date. The Port Authority clarifies that only written addenda issued by the Chief Engineer are authorized to provide contract interpretations or additional information beyond what is contained in the contract documents themselves.
The addendum revises the minority and women-owned business enterprise outreach requirements, specifically addressing how joint venture participation by MBE, WBE, and Service-Disabled Veteran-Owned Business (SDVOB) firms will be counted toward outreach goals. Under the revised terms, only the percentage of work that MBE/WBE/SDVOB firms perform with their own forces in joint ventures counts toward goals, and second-tier subcontracting by these firms qualifies toward outreach goals only if the second-tier subcontractor is itself an MBE, WBE, or SDVOB. Contractors must submit monthly outreach plan progress reports to the Engineer in Excel format or through the B2G Diversity Management Software platform at https://panynj.diversitysoftware.com, documenting all MBE, WBE, and SDVOB firms contacted to bid or participate in the work, including firm names, addresses, and proposed subcontracting services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-NTB1.pdf | ||
| 3-HT-224.228 Available Documents.pdf | ||
| 4-HT-224.228 Contract Drawings Vol 1 of 2.pdf | ||
| 6-Add No.1.pdf | ||
| 2-HT-224.228 Contract Booklet.pdf | ||
| 5-HT-224.228 AD.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE PORT AUTHORITY OF NEW YORK AND NEW JERSEY
TWO MONTGOMERY STREET - 1st FLOOR
JERSEY CITY, NJ 07302
May 22, 2026
ADDENDUM NO. 2
TO PROSPECTIVE BIDDERS ON CONTRACT HT-224.228 – INSTALLATION OF
STORAGE FACILITY FOR FLOOD PROTECTION EQUIPMENT
The following changes are hereby made in the Contract documents for the subject Contract.
This communication should be physically annexed (electronically) behind the last page of the Contract booklet and initialled by each bidder before submitting his Bid.
In case any bidder fails to conform to these instructions, his Bid will nevertheless be construed as though this communication had been so physically annexed and initialled.
CHANGES IN THE CONTRACT BOOKLET
Page 12 - Delete the entire page and substitute therefor new page 12 which is attached hereto and made a part hereof.
THE PORT AUTHORITY OF NEW YORK AND NEW JERSEY
M. Rizwan Baig, P.E.
Chief Engineer/Director
INITIALLED BY THE BIDDER:
12 Addendum No. 2
e. If the MBE, WBE or SDVOB firms are given opportunities to bid or propose through a joint venture, only the percentage amount equal to the proportion of the total dollar value of the subcontract to be awarded equal to clearly defined portion of the subcontracted work the MBE/WBE/SDVOB is proposed to perform with its own forces will be counted towards the respective Outreach Goal.
f. If the MBE, WBE or SDVOB proposes to subcontract to another firm part of the Work to be awarded to the MBE, WBE or SDVOB, the value of the work subcontracted to another firm may be counted toward Outreach Goals only if the proposed second-tier subcontractor is also itself an MBE, WBE or SDVOB.
F. Monthly Outreach Plan Progress Report
The Contractor shall submit a report each month ("Monthly Report") to the Engineer providing information on implementation of its Outreach Plans. Such Monthly Reports shall be submitted in an Excel format or such other forms or a third-party platform as advised by the Authority (currently the B2G Diversity Management Software platform found at the following link: https://panynj.diversitysoftware.com) that include the firm name, address and type of proposed subcontracting services for every MBE, WBE and SDVOB firm that was contacted to bid or propose to participate in the Work.
Nothing herein shall be deemed to supersede or to otherwise modify the clause of the Form of Contract entitled "Assignments and Subcontracts".
10. INSPECTION OF SITE
Each bidder or his authorized representative must make proper arrangements with the Engineer at the construction site before inspecting the construction site. To make such arrangements call Kenneth Wright at (973) 418-3774 or email at kwright@panynj.gov.
11. QUESTIONS BY BIDDERS
Questions by prospective bidders concerning the Contract may be addressed to Megan Lancelot-Zielinski, at (212) 435-5694 or email at mlancelotzielinski@panynj.gov, who, however, is authorized only to direct the attention of prospective bidders to various portions of the Contract so that they may read and interpret such portions for themselves. Neither Megan Lancelot-Zielinski nor any other employee or representative of the Authority is authorized to give interpretations of any portion of the Contract or to give information as to the requirements of the Contract in addition to that contained in the Contract. Interpretations of the Contract or additional information as to its requirements, where necessary, shall be communicated to bidders only by written addendum issued over the name of the Chief Engineer, which addendum shall be considered part of this Contract. Accordingly, nothing contained herein and no representation, statement or promise, oral or in writing, of the Authority, its Commissioners, officers, agents, representatives or employees shall impair or limit the effect of the warranties of the Contractor contained in the clause of the Form of Contract entitled "Contractor's Warranties" or elsewhere in this Contract. The provisions of this clause shall apply to questions addressed by prospective bidders both before and after their receipt of Contract documents.
Questions by prospective bidders shall be submitted to the person whose name and email address is listed not later than 5:00 PM on the day which is 7 calendar days before the date of receipt of Bids.