This document is a Minimum Standards for Responsiveness form from Salt Lake County for a small project involving HVAC replacement at the Draper Library. The form is designed to evaluate potential general contractors' qualifications and past performance by requiring affirmative responses to ten specific questions about their prior project experiences. The questions cover areas such as successful completion of mechanical projects without owner interventions, project defaults, liquidated damages, experience with similar government or commercial projects, references, and specific capabilities related to HVAC system replacements.

The form serves as a pre-qualification document for bidders, with the county reserving the right to investigate responses further. Contractors must demonstrate experience in areas including replacing HVAC systems in government facilities, working in occupied spaces, having staff with relevant certifications (such as Nate or RSES in hydronics), and maintaining sufficient staffing to complete the project within the allotted timeframe. Any bid that does not receive affirmative answers to all questions will be deemed non-responsive and non-responsible, effectively disqualifying the proposer from the contract opportunity.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MINIMUM STANDARDS FOR RESPONSIVENESS

YES NO QUESTIONS

CONTRACT SPECIFIC PERFORMANCE:

PROJECT SPECIFIC PERFORMANCE:

EXHIBIT A PROJ. ID.

CONSTRUCTION SERVICES FOR: DRAPER LIBRARY HVAC REPLACEMENT

Proposer must answer, in the affirmative, to all questions below or the Proposer's bid will be deemed non-responsive and non-responsible.

In the last five years, has your firm, acting as the General Contractor:

Completed all mechanical projects without the owner(s) calling in or involving sureties to assist in completing or assuming responsibility for completing a project?

Completed all mechanical projects without being removed from the project upon a claim by the Owner for default or breach of contract?

Completed all construction projects without assessment or payment of Liquidated Damages?

In the last five years, has your firm, acting as the General Contractor worked on a project of similar size and scope?

In the last 3 years, has your firm, acting as the General Contractor, worked on a commercial project(s) and/or Government projects(s) outside of new single-family homes and single-family renovations?

From the last five years, is your firm able to provide a minimum of 3 references who will speak to your performance?

Does your firm or your sub-contractor have experience replacing hvac systems in city, state, county, or any other government agency facilities?

Does your firm have successful experience constructing projects while fully occupied in adjacent areas?

Does any of your firm, or the subcontractor for this project have either Nate or RSES Certifications in hydronics?

This form must be included in your bid package as part of the required forms for submittal.

The County reserves the right to investigate further, any of the responses to the above questions.

COMPANY NAME

SIGNER

TITLE

SALT LAKE COUNTY - SMALL PROJECT

Does your firm or subcontractor have the available staff to complete this project in the time frame alloted?

00 0100 MINIMUM STANDARDS FOR RESPONSIVENESS
00 0101 PROJECT COVER PAGE
00 0110 TABLE OF CONTENTS
00 3143 - PERMIT APPLICATION
01 1000 - SUMMARY
01 2500 - SUBSTITUTION PROCEDURES
01 3100 - PROJECT MANAGEMENT AND COORDINATION
01 3233 - PHOTOGRAPHIC DOCUMENTATION
01 3300 - SUBMITTAL PROCEDURES
01 4000 - QUALITY REQUIREMENTS
01 4200 - REFERENCES
01 5000 - TEMPORARY FACILITIES AND CONTROLS
01 6000 - PRODUCT REQUIREMENTS
01 7300 - EXECUTION
01 7419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 7700 - CLOSEOUT PROCEDURES
01 7823 - OPERATION AND MAINTENANCE DATA
01 7839 - PROJECT RECORD DOCUMENTS
02 4119 - SELECTIVE DEMOLITION
07 9200 - JOINT SEALANTS
220500 Common Work Results for Plumbing (lead free)
221316 Sanitary Waste and Vent Piping - 2019-04-02
230100 Mechanical Requirements -2014-11-24
230513 Common Motor Requirements for HVAC Equipment - 2013-01-15
230519 Meters and Gages for HVAC - 2013-03-15
230523 General-Duty Valves for HVAC Piping - 2013-03-15
230529 Hangers and Supports for HVAC Piping and Equipment - 2014-05-13
230548 Vibration and Seismic Controls for HVAC - 2020-03-30
230550 Operation and Maintenance of HVAC Systems - 2016-01-18
230593 Testing Adjusting and Balancing for HVAC - 2013-09-26
230713 Duct Insulation - 2014-05-02
230719 HVAC Piping Insulation - 2016-01-19
230900 Sequence of Operations
232113 Hydronic Piping - 2017-09-13
232116 Hydronic Piping Specialties - 2016-05-09
232500 Chemical Water Treatment
233113 Metal Ducts - 2015-12-09
237324 CUSTOM NATATORIUM AIR-HANDLING UNITS 2015-11-12