7-3-MP27005-24279300 CoHa Draft Early Bid Package Schedule All Activities.pdf

PDF 2 MB Posted

Attached to
DFCM Construction - VBS Code & Special Inspections Services - Nucleus Group-USHE - Convergence Hall - Project #24279300
Solicitation number
MP27005-INSPECTIONS
Issued by
Utah

About this file

This is an Early Bid Package Schedule document prepared by the State of Utah's Division of Facilities Construction and Management (DFCM) for the Convergence Hall construction project. The document outlines the timeline and sequencing of all activities required for the Code & Special Inspections Services contract, with an estimated inspection budget of $650,000. The Convergence Hall project is a approximately 163,000 square foot, six-story building located at the University of Utah (USHE) that will include office space, maker space, retail areas, event spaces, and housing. The schedule establishes critical milestones and activity sequences necessary for coordinating code inspections and special inspections throughout the construction phases of the project.

All special inspections contractors, material testing labs, and special inspectors performing work on this DFCM project must be listed on the DFCM Approved Special Inspection Firms, Material Testing Labs, & Special Inspectors list. The contract requires services from DFCM Prequalified Code Inspection Firms. The schedule document serves as the planning instrument to ensure that all inspection activities are properly sequenced and coordinated with the overall construction timeline for Project #24279300, enabling DFCM to maintain quality assurance and code compliance throughout the building's construction phases.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Orig Dur

Rem Dur

Start Finish

Convergence Hall - SD Schedule w/ BPConvergence Hall - SD Schedule w/ BP 910 910 07-Nov-25 02-Jul-29

Executive SummaryExecutive Summary 910 910 07-Nov-25 02-Jul-29

MilestonesMilestones 887 887 07-Nov-25 30-May-29

Overall Project MilestonesOverall Project Milestones 887 887 07-Nov-25 30-May-29

A1000 Notice of Award 0 0 07-Nov-25*

A1160 Design Development (DD Drawings) Complete 0 0 02-Jul-26

A1170 Bid Package 1 or Soil Improvements Complete 0 0 02-Nov-26

A1110 Construction Documents (CD Drawings) Complete 0 0 18-Dec-26

A1010 Begin Earthwork 0 0 26-Jan-27

A1180 Construction Documents City Review Complete 0 0 23-Feb-27

A1410 Start Site Improvements 0 0 28-Jul-28

A1380 Site Improvements Complete 0 0 27-Oct-28

A1390 Start Commissioning & Worklist 0 0 09-Feb-29

A3930 Substantial Completion 0 0 30-May-29*

Tower 1 - Presentation, Auditorium, Lobby & OfficesTower 1 - Presentation, Auditorium, Lobby & Offices 401 401 16-Mar-27 17-Oct-28

A1020 Begin Agg Piers - Tower 1 0 0 16-Mar-27

A1030 Begin Footings - Tower 1 0 0 27-Apr-27

A1070 Being PT Structure - Tower 1 0 0 20-Jul-27

A1350 Start Overhead MEPF Rough-in - Tower 1 0 0 23-Dec-27

A1360 Start In-Wall MEP Rough-In - Tower 1 0 0 12-Jan-28

A1370 Start Finishes - Tower 1 0 0 18-Feb-28

A1080 PT Structure Complete - Tower 1 0 0 05-Jun-28

A6500 Start Roofing 0 0 06-Jun-28

A6610 Finishes Complete - Tower 1 0 0 17-Oct-28

Tower 2 - ResidentialTower 2 - Residential 454 454 20-Apr-27 15-Feb-29

A20680 Begin Agg Piers - Tower 2 0 0 20-Apr-27

A20690 Begin Footings - Tower 2 0 0 28-May-27

A20710 Being PT Structure - Tower 2 0 0 13-Sep-27

A20720 Start Overhead Rough-in - Tower 2 0 0 14-Jun-28

A20760 Start In-Wall MEP Rough-In - Tower 2 0 0 30-Jun-28

A20730 Start Finishes - Tower 2 0 0 08-Aug-28

A20750 PT Structure Complete - Tower 2 0 0 30-Aug-28

A20740 Start Roofing 0 0 29-Sep-28

A20770 Finishes Complete - Tower 2 0 0 15-Feb-29

DurationsDurations 610 610 26-Jan-27 02-Jul-29

A3900 Construction 583 583 26-Jan-27 23-May-29

A3910 Closeout 85 85 05-Mar-29 02-Jul-29

PreconstructionPreconstruction 636 636 07-Nov-25 25-May-28

DesignDesign 281 281 07-Nov-25 18-Dec-26

A3920 Schematic Design 71 71 07-Nov-25 20-Feb-26

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Notice of Award

Design Development (DD Drawings) Complete

Bid Package 1 or Soil Improvements Complete

Construction Documents (CD Drawings) Complete

Begin Earthwork

Construction Documents City Review Complete

Start Site Improvements

Site Improvements Complete

Start Commissioning & Worklist

Substantial Completion

Begin Agg Piers - Tower 1

Begin Footings - Tower 1

Being PT Structure - Tower 1

Start Overhead MEPF Rough-in - Tower 1

Start In-Wall MEP Rough-In - Tower 1

Start Finishes - Tower 1

PT Structure Complete - Tower 1

Start Roofing

Finishes Complete - Tower 1

Begin Agg Piers - Tower 2

Begin Footings - Tower 2

Being PT Structure - Tower 2

Start Overhead Rough-in - Tower 2

Start In-Wall MEP Rough-In - Tower 2

Start Finishes - Tower 2

PT Structure Complete - Tower 2

Start Roofing

Finishes Complete - Tower 2

Construction

Closeout

Schematic Design

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Non-Critical Milestone

Complete Milestone

Data Date:23-Oct-25 Run Date: 24-Sep-26

Project: 25CS21-3 Convergence Hall - SD Schedule w/ BP Layton Construction Company

24-Sep-26 - Preliminary SD Level Schedule

Rem Dur

Start Finish

A3940 Design Re-Programming 50 50 07-Nov-25 22-Jan-26

A3660 Design Development (DD Drawings) 93 93 23-Feb-26 02-Jul-26

A3670 Construction Documents (CD Drawings) 117 117 06-Jul-26 18-Dec-26

A3690 Bid Package 1 or Soil Improvements 85 85 06-Jul-26 02-Nov-26

PermittingPermitting 72 72 03-Nov-26 23-Feb-27

A3700 Early Bid Package Permit Review 51 51 03-Nov-26 25-Jan-27

A3680 CD Permit Review 40 40 21-Dec-26 23-Feb-27

Cost EstimateCost Estimate 225 225 23-Feb-26 19-Jan-27

A3950 SD Cost Estimate 15 15 23-Feb-26 13-Mar-26

A3960 DD Cost Estimate 15 15 06-Jul-26 24-Jul-26

A3710 CD Estimate 15 15 21-Dec-26 19-Jan-27

BiddingBidding 76 76 03-Nov-26 01-Mar-27

A3970 Early Bid Package - Bidding 51 51 03-Nov-26 25-Jan-27

A3720 CD Bid Package 44 44 21-Dec-26 01-Mar-27

ProcurementProcurement 140 140 06-Jul-26 29-Jan-27

A3750 Early Procurement - Electrical, Mechanical, Steel, Exterior Systems, etc. 140 140 06-Jul-26 29-Jan-27

Submittals & ProcurementSubmittals & Procurement 340 340 26-Jan-27 25-May-28

ElectricalElectrical 315 315 02-Mar-27 25-May-28

GeneratorGenerator 315 315 02-Mar-27 25-May-28

A18780 Generator Submittals 10 10 02-Mar-27 15-Mar-27

A18790 A&E Review & Approval 15 15 16-Mar-27 05-Apr-27

A18800 Fabricate & Deliver Generator 290 290 06-Apr-27 25-May-28

Electrical GearElectrical Gear 265 265 02-Mar-27 16-Mar-28

A18920 Electrical Gear Submittals 10 10 02-Mar-27 15-Mar-27

A18930 A&E Review & Approval 15 15 16-Mar-27 05-Apr-27

A18640 Electrical Gear // Submittals & Procurement 240 240 06-Apr-27 16-Mar-28

SewerSewer 41 41 26-Jan-27 23-Mar-27

A18830 Sewer Shop Drawings & Submittals 1 1 26-Jan-27 26-Jan-27

A18840 Review & Approval of Sewer 10 10 27-Jan-27 09-Feb-27

A18850 Fabricate & Deliver Sewer Manhole 30 30 10-Feb-27 23-Mar-27

MechanicalMechanical 125 125 02-Mar-27 25-Aug-27

CPSCPS 75 75 02-Mar-27 15-Jun-27

A19050 CPS Shopd Drawings & Submittals 5 5 02-Mar-27 08-Mar-27

A19060 A&E Review & Approval 10 10 09-Mar-27 22-Mar-27

A19070 Fabricate & Deliver CPS 60 60 23-Mar-27 15-Jun-27

HX'sHX's 125 125 02-Mar-27 25-Aug-27

A19080 HX's Shopd Drawings & Submittals 5 5 02-Mar-27 08-Mar-27

A19090 A&E Review & Approval 10 10 09-Mar-27 22-Mar-27

A19100 Fabricate & Deliver HX's ( Air Handler) 110 110 23-Mar-27 25-Aug-27

MasonryMasonry 75 75 02-Mar-27 15-Jun-27

Walnut MasonryWalnut Masonry 75 75 02-Mar-27 15-Jun-27

A19110 Walnut Masonry Shopd Drawings & Submittals 5 5 02-Mar-27 08-Mar-27

A19120 A&E Review & Approval 10 10 09-Mar-27 22-Mar-27

A19130 Fabricate & Deliver Walnut Masonry 60 60 23-Mar-27 15-Jun-27

Stone PanelsStone Panels 125 125 02-Mar-27 25-Aug-27

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Design Re-Programming

Design Development (DD Drawings)

Construction Documents (CD Drawings)

Bid Package 1 or Soil Improvements

Early Bid Package Permit Review

CD Permit Review

SD Cost Estimate

DD Cost Estimate

CD Estimate

Early Bid Package - Bidding

CD Bid Package

Early Procurement - Electrical, Mechanical, Steel, Exterior Systems, etc.

Generator Submittals

A&E Review & Approval

Fabricate & Deliver Generator

Electrical Gear Submittals

A&E Review & Approval

Electrical Gear // Submittals & Procurement

Sewer Shop Drawings & Submittals

Review & Approval of Sewer

Fabricate & Deliver Sewer Manhole

CPS Shopd Drawings & Submittals

A&E Review & Approval

Fabricate & Deliver CPS

HX's Shopd Drawings & Submittals

A&E Review & Approval

Fabricate & Deliver HX's ( Air Handler)

Walnut Masonry Shopd Drawings & Submittals

A&E Review & Approval

Fabricate & Deliver Walnut Masonry

Rem Dur

Start Finish

A19140 Stone Panels Shop Drawings & Submittals 5 5 02-Mar-27 08-Mar-27

A19150 A&E Review & Approval 10 10 09-Mar-27 22-Mar-27

A19160 Fabricate & Deliver Stone Panels 110 110 23-Mar-27 25-Aug-27

Exterior Metal PanelsExterior Metal Panels 80 80 02-Mar-27 22-Jun-27

A19170 Shop Drawings & Submittals - Exterior Metal Panels 20 20 02-Mar-27 29-Mar-27

A19180 A&E Review & Approval - Exterior Metal Panels 10 10 30-Mar-27 12-Apr-27

A19190 Fabricate & Deliver - Exterior Metal Panels 50 50 13-Apr-27 22-Jun-27

Doors & HardwareDoors & Hardware 75 75 02-Mar-27 15-Jun-27

A19230 Doors & Hardware Shop Drawings & Submittals 5 5 02-Mar-27 08-Mar-27

A19240 A&E Review & Approval 10 10 09-Mar-27 22-Mar-27

A19250 Fabricate & Deliver Doors & Hardware 60 60 23-Mar-27 15-Jun-27

ElevatorElevator 75 75 02-Mar-27 15-Jun-27

A19260 Elevator Shop Drawings & Submittals 5 5 02-Mar-27 08-Mar-27

A19270 A&E Review & Approval 10 10 09-Mar-27 22-Mar-27

A19280 Fabricate & Deliver Elevator 60 60 23-Mar-27 15-Jun-27

Lecture Hall ChairsLecture Hall Chairs 84 84 02-Mar-27 28-Jun-27

A19460 Lecture Hall Chairs Procurement 84 84 02-Mar-27 28-Jun-27

ConstructionConstruction 524 524 26-Jan-27 01-Mar-29

SiteworkSitework 50 50 26-Jan-27 05-Apr-27

A1050 Road Utilities 5 5 26-Jan-27 01-Feb-27

A1690 LCC Mob. 5 5 26-Jan-27 01-Feb-27

A1680 Install Site Fence/SWPPP/ Tree Protection 5 5 01-Feb-27 05-Feb-27

A1670 Clear & Grub 5 5 08-Feb-27 12-Feb-27

A1090 Site Excavation 5 5 15-Feb-27 19-Feb-27

A2510 Storm Drain & Sewer Survey 1 1 15-Feb-27 15-Feb-27

A2500 Install Sewer 5 5 16-Feb-27 22-Feb-27

A2520 Install Water Line 5 5 16-Feb-27 22-Feb-27

A2530 Install Storm Drain 15 15 16-Feb-27 08-Mar-27

A2540 Install Roof Drain Main 5 5 16-Feb-27 22-Feb-27

A1120 Building Excavation & Footing Prep Tower 1 15 15 23-Feb-27 15-Mar-27

A5750 Building Excavation & Footing Prep Tower 2 15 15 16-Mar-27 05-Apr-27

Footings & FoundationsFootings & Foundations 119 119 16-Mar-27 31-Aug-27

Footings & Foundations Tower 1 - Presentation, Auditorium, Lobby & OfficesFootings & Foundations Tower 1 - Presentation, Auditorium, Lobby & Offices 71 71 16-Mar-27 23-Jun-27

A11100 Install Agg Piers - Tower 1 25 25 16-Mar-27 19-Apr-27

Building Deep UtilitiesBuilding Deep Utilities 15 15 20-Apr-27 10-May-27

A12310 Sewer Main - Tower 1 5 5 20-Apr-27 26-Apr-27

A12320 Main Storm/ Roof Drain - Tower 1 5 5 20-Apr-27 26-Apr-27

A12290 Water Service Main - Tower 1 5 5 27-Apr-27 03-May-27

A12300 Fire Riser - Tower 1 5 5 27-Apr-27 03-May-27

A11120 Electrical Main Feeder - Tower 1 5 5 04-May-27 10-May-27

Mat Footings GL 1-11, AA-NMat Footings GL 1-11, AA-N 26 26 27-Apr-27 02-Jun-27

A10960 Reinforce Matt Footings - Tower 1 15 15 27-Apr-27 17-May-27

A2050 Form Elevator Pit Slab - Tower 1 1 1 27-Apr-27 27-Apr-27

A10980 Pour Elevator Pit Slab - Tower 1 1 1 18-May-27 18-May-27

A1220 Pour #1 Footings Matt Footings - Tower 1 1 1 18-May-27 18-May-27

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Stone Panels Shop Drawings & Submittals

A&E Review & Approval

Fabricate & Deliver Stone Panels

Shop Drawings & Submittals - Exterior Metal Panels

A&E Review & Approval - Exterior Metal Panels

Fabricate & Deliver - Exterior Metal Panels

Doors & Hardware Shop Drawings & Submittals

A&E Review & Approval

Fabricate & Deliver Doors & Hardware

Elevator Shop Drawings & Submittals

A&E Review & Approval

Fabricate & Deliver Elevator

Lecture Hall Chairs Procurement

Road Utilities

LCC Mob.

Install Site Fence/SWPPP/ Tree Protection

Clear & Grub

Site Excavation

Storm Drain & Sewer Survey

Install Sewer

Install Water Line

Install Storm Drain

Install Roof Drain Main

Building Excavation & Footing Prep Tower 1

Building Excavation & Footing Prep Tower 2

Install Agg Piers - Tower 1

Sewer Main - Tower 1

Main Storm/ Roof Drain - Tower 1

Water Service Main - Tower 1

Fire Riser - Tower 1

Electrical Main Feeder - Tower 1

Reinforce Matt Footings - Tower 1

Form Elevator Pit Slab - Tower 1

Pour Elevator Pit Slab - Tower 1

Pour #1 Footings Matt Footings - Tower 1

Rem Dur

Start Finish

A1200 Form Elevator Pit Walls - Tower 1 2 2 19-May-27 20-May-27

A6750 Cure Matt Footings - Tower 1 7 7 19-May-27 27-May-27

A6760 Strip Mat Footings - Tower 1 8 8 19-May-27 28-May-27

A1210 Pour Elevator Pit Walls - Tower 1 1 1 21-May-27 21-May-27

A6770 Backfill Mat Footing & Area 2 - Tower 1 8 8 21-May-27 02-Jun-27

Mat Footings FMat Footings F 36 36 27-Apr-27 16-Jun-27

A6780 Reinforce Matt Footings - Tower 1 10 10 27-Apr-27 10-May-27

A6830 Form Mat Footing - Tower 1 5 5 28-May-27 04-Jun-27

A6790 Pour #1 Footings Matt Footings - Tower 1 1 1 07-Jun-27 07-Jun-27

A6800 Cure Matt Footings - Tower 1 1 1 08-Jun-27 08-Jun-27

A6810 Strip Mat Footings - Tower 1 5 5 08-Jun-27 14-Jun-27

A6820 Backfill Mat Footing - Tower 1 5 5 10-Jun-27 16-Jun-27

Remaining FootingsRemaining Footings 28 28 20-Apr-27 27-May-27

A10970 Form Footings & Spots - Tower 1 12 12 20-Apr-27 05-May-27

A1240 Form Reinforce & Pour Stem Walls & Piers - Tower 1 11 11 13-May-27 27-May-27

A6930 Backfill - Tower 1 3 3 13-May-27 17-May-27

Underslab MEPUnderslab MEP 25 25 19-May-27 23-Jun-27

A2360 Underslab Plumbing - Tower 1 20 20 19-May-27 16-Jun-27

A2350 Underslab Electrical - Tower 1 20 20 26-May-27 23-Jun-27

Footings & Foundations Tower 2 - ResidentialFootings & Foundations Tower 2 - Residential 94 94 20-Apr-27 31-Aug-27

A11110 Install Agg Piers - Tower 2 15 15 20-Apr-27 10-May-27

Building Deep UtilitiesBuilding Deep Utilities 15 15 11-May-27 01-Jun-27

A20810 Sewer Main - Tower 2 5 5 11-May-27 17-May-27

A20820 Main Storm/ Roof Drain - Tower 2 5 5 11-May-27 17-May-27

A20790 Water Service Main - Tower 2 5 5 18-May-27 24-May-27

A20800 Fire Riser - Tower 2 5 5 18-May-27 24-May-27

A20780 Electrical Main Feeder - Tower 2 5 5 25-May-27 01-Jun-27

Matt Footings GL 9.8 - 15Matt Footings GL 9.8 - 15 25 25 28-May-27 02-Jul-27

A3730 Reinforce Matt Footings - Tower 2 3 3 28-May-27 02-Jun-27

A6840 Form Mat Footing - Tower 2 10 10 08-Jun-27 21-Jun-27

A6850 Pour #1 Footings Matt Footings - Tower 2 1 1 22-Jun-27 22-Jun-27

A6860 Cure Matt Footings - Tower 2 1 1 23-Jun-27 23-Jun-27

A6870 Strip Mat Footings - Tower 2 5 5 24-Jun-27 30-Jun-27

A6880 Backfill Mat Footing - Tower 2 5 5 28-Jun-27 02-Jul-27

Remainig FootingsRemainig Footings 52 52 06-May-27 20-Jul-27

A1320 Form Footings & Spots - Tower 2 12 12 06-May-27 21-May-27

A1310 Pour Elevator Pit Slab - Tower 2 1 1 06-May-27 06-May-27

A10990 Form Elevator Pit Walls - Tower 2 2 2 07-May-27 10-May-27

A11000 Pour Elevator Pit Walls - Tower 2 1 1 11-May-27 11-May-27

A2370 Backfill Footings Area 1 - Tower 2 5 5 03-Jun-27 09-Jun-27

A3760 Pour #3 Footings - Tower 2 1 1 03-Jun-27 03-Jun-27

A3770 Form Reinforce & Pour Stem Walls & Piers - Tower 2 8 8 03-Jun-27 14-Jun-27

A6940 Form Footings & Spots After Mat - Tower 2 12 12 01-Jul-27 19-Jul-27

A6950 Pour #2 Footings After Mat - Tower 2 1 1 20-Jul-27 20-Jul-27

Underslab MEPUnderslab MEP 30 30 21-Jul-27 31-Aug-27

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Form Elevator Pit Walls - Tower 1

Cure Matt Footings - Tower 1

Strip Mat Footings - Tower 1

Pour Elevator Pit Walls - Tower 1

Backfill Mat Footing & Area 2 - Tower 1

Reinforce Matt Footings - Tower 1

Form Mat Footing - Tower 1

Pour #1 Footings Matt Footings - Tower 1

Cure Matt Footings - Tower 1

Strip Mat Footings - Tower 1

Backfill Mat Footing - Tower 1

Form Footings & Spots - Tower 1

Form Reinforce & Pour Stem Walls & Piers - Tower 1

Backfill - Tower 1

Underslab Plumbing - Tower 1

Underslab Electrical - Tower 1

Install Agg Piers - Tower 2

Sewer Main - Tower 2

Main Storm/ Roof Drain - Tower 2

Water Service Main - Tower 2

Fire Riser - Tower 2

Electrical Main Feeder - Tower 2

Reinforce Matt Footings - Tower 2

Form Mat Footing - Tower 2

Pour #1 Footings Matt Footings - Tower 2

Cure Matt Footings - Tower 2

Strip Mat Footings - Tower 2

Backfill Mat Footing - Tower 2

Form Footings & Spots - Tower 2

Pour Elevator Pit Slab - Tower 2

Form Elevator Pit Walls - Tower 2

Pour Elevator Pit Walls - Tower 2

Backfill Footings Area 1 - Tower 2

Pour #3 Footings - Tower 2

Form Reinforce & Pour Stem Walls & Piers - Tower 2

Form Footings & Spots After Mat - Tower 2

Pour #2 Footings After Mat - Tower 2

Rem Dur

Start Finish

A2380 Underslab Plumbing - Tower 2 15 15 21-Jul-27 10-Aug-27

A2390 Underslab Electrical - Tower 2 20 20 04-Aug-27 31-Aug-27

Slab on GradeSlab on Grade 48 48 24-Jun-27 31-Aug-27

A2330 Gravel Prep Area - Tower1 5 5 24-Jun-27 30-Jun-27

A2310 Slab on Grade Tower 1 5 5 01-Jul-27 08-Jul-27

A7140 Gravel Prep Area - Tower 2 5 5 04-Aug-27 10-Aug-27

A2320 Slab on Grade Area - Tower 2 7 7 23-Aug-27 31-Aug-27

Structure & ShellStructure & Shell 327 327 09-Jul-27 26-Oct-28

Tower 1 - Presentation, Auditorium, Lobby & OfficesTower 1 - Presentation, Auditorium, Lobby & Offices 246 246 09-Jul-27 03-Jul-28

Level 1Level 1 114 114 09-Jul-27 20-Dec-27

Walls & ColumnsWalls & Columns 11 11 09-Jul-27 23-Jul-27

A12240 Form Walls & Columns - T1 L1 3 3 09-Jul-27 13-Jul-27

A12250 Wall & Column Reinforcing - T1 L1 3 3 14-Jul-27 16-Jul-27

A12260 Pour Walls & Columns - T1 L1 1 1 19-Jul-27 19-Jul-27

A12270 Cure Walls & Columns - T1 L1 3 3 20-Jul-27 22-Jul-27

A12280 Strip Walls & Columns - T1 L1 1 1 23-Jul-27 23-Jul-27

PT SlabsPT Slabs 107 107 20-Jul-27 20-Dec-27

A11130 Install Shoring - T1 L1 15 15 20-Jul-27 09-Aug-27

A11140 Install Decking - T1 L1 10 10 03-Aug-27 16-Aug-27

A11210 Strip & Remove Shoring - T1 L1 5 5 14-Dec-27 20-Dec-27

Level 2Level 2 128 128 06-Aug-27 15-Feb-28

Walls & ColumnsWalls & Columns 11 11 27-Aug-27 13-Sep-27

A19790 Form Walls & Columns - T1 L2 3 3 27-Aug-27 31-Aug-27

A19800 Wall & Column Reinforcing - T1 L2 3 3 01-Sep-27 03-Sep-27

A19810 Pour Walls & Columns - T1 L2 1 1 07-Sep-27 07-Sep-27

A19820 Cure Walls & Columns - T1 L2 3 3 08-Sep-27 10-Sep-27

A19830 Strip Walls & Columns - T1 L2 1 1 13-Sep-27 13-Sep-27

PT SlabsPT Slabs 128 128 06-Aug-27 15-Feb-28

A12920 In-Slab MEP - T1 L2 8 8 06-Aug-27 17-Aug-27

A11160 Install Slab Reinforcing & PT Cables - T1 L2 6 6 11-Aug-27 18-Aug-27

A11150 Install Edge Forms - T1 L2 2 2 13-Aug-27 16-Aug-27

A11170 PT Slab Inspection - T1 L2 1 1 19-Aug-27 19-Aug-27

A11180 Place PT Slab (Deck of L2) - T1 L2 1 1 20-Aug-27 20-Aug-27

A11190 PT Slab Cure - T1 L2 3 3 23-Aug-27 25-Aug-27

A11200 Stress Cables - T1 L2 1 1 26-Aug-27 26-Aug-27

A11220 Install Shoring - T1 L2 15 15 08-Sep-27 28-Sep-27

A11230 Install Decking - T1 L2 10 10 22-Sep-27 05-Oct-27

A11300 Strip & Remove Shoring - T1 L2 5 5 09-Feb-28 15-Feb-28

Level 3Level 3 155 155 27-Sep-27 11-May-28

Walls & ColumnsWalls & Columns 11 11 22-Oct-27 05-Nov-27

A19840 Form Walls & Columns - T1 L3 3 3 22-Oct-27 26-Oct-27

A19850 Wall & Column Reinforcing - T1 L3 3 3 27-Oct-27 29-Oct-27

A19860 Pour Walls & Columns - T1 L3 1 1 01-Nov-27 01-Nov-27

A19870 Cure Walls & Columns - T1 L3 3 3 02-Nov-27 04-Nov-27

A19880 Strip Walls & Columns - T1 L3 1 1 05-Nov-27 05-Nov-27

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Underslab Plumbing - Tower 2

Underslab Electrical - Tower 2

Gravel Prep Area - Tower1

Slab on Grade Tower 1

Gravel Prep Area - Tower 2

Slab on Grade Area - Tower 2

Form Walls & Columns - T1 L1

Wall & Column Reinforcing - T1 L1

Pour Walls & Columns - T1 L1

Cure Walls & Columns - T1 L1

Strip Walls & Columns - T1 L1

Install Shoring - T1 L1

Install Decking - T1 L1

Strip & Remove Shoring - T1 L1

Form Walls & Columns - T1 L2

Wall & Column Reinforcing - T1 L2

Pour Walls & Columns - T1 L2

Cure Walls & Columns - T1 L2

Strip Walls & Columns - T1 L2

In-Slab MEP - T1 L2

Install Slab Reinforcing & PT Cables - T1 L2

Install Edge Forms - T1 L2

PT Slab Inspection - T1 L2

Place PT Slab (Deck of L2) - T1 L2

PT Slab Cure - T1 L2

Stress Cables - T1 L2

Install Shoring - T1 L2

Install Decking - T1 L2

Strip & Remove Shoring - T1 L2

Form Walls & Columns - T1 L3

Wall & Column Reinforcing - T1 L3

Pour Walls & Columns - T1 L3

Cure Walls & Columns - T1 L3

Strip Walls & Columns - T1 L3

Rem Dur

Start Finish

PT SlabsPT Slabs 126 126 27-Sep-27 31-Mar-28

A12330 In-Slab MEP - T1 L3 8 8 27-Sep-27 06-Oct-27

A11250 Install Slab Reinforcing & PT Cables - T1 L3 6 6 30-Sep-27 07-Oct-27

A11240 Install Edge Forms - T1 L3 2 2 06-Oct-27 07-Oct-27

A11260 PT Slab Inspection - T1 L3 1 1 08-Oct-27 08-Oct-27

A11270 Place PT Slab (Deck of L3) - T1 L3 5 5 11-Oct-27 15-Oct-27

A11280 PT Slab Cure - T1 L3 3 3 18-Oct-27 20-Oct-27

A11290 Stress Cables - T1 L3 1 1 21-Oct-27 21-Oct-27

A11310 Install Shoring - T1 L3 15 15 02-Nov-27 22-Nov-27

A11320 Install Decking - T1 L3 10 10 16-Nov-27 01-Dec-27

A11390 Strip & Remove Shoring - T1 L3 5 5 27-Mar-28 31-Mar-28

Structural SteelStructural Steel 3 3 09-May-28 11-May-28

A20830 Erect Steel Columns & Girders @ Auditorium - T1 L3 3 3 09-May-28 11-May-28

Level 4Level 4 126 126 19-Nov-27 25-May-28

Walls & ColumnsWalls & Columns 11 11 14-Dec-27 05-Jan-28

A19890 Form Walls & Columns - T1 L4 3 3 14-Dec-27 16-Dec-27

A19900 Wall & Column Reinforcing - T1 L4 3 3 17-Dec-27 21-Dec-27

A19910 Pour Walls & Columns - T1 L4 1 1 22-Dec-27 22-Dec-27

A19920 Cure Walls & Columns - T1 L4 3 3 23-Dec-27 04-Jan-28

A19930 Strip Walls & Columns - T1 L4 1 1 05-Jan-28 05-Jan-28

PT SlabsPT Slabs 122 122 19-Nov-27 19-May-28

A12340 In-Slab MEP - T1 L4 8 8 19-Nov-27 02-Dec-27

A11340 Install Slab Reinforcing & PT Cables - T1 L4 6 6 24-Nov-27 03-Dec-27

A11330 Install Edge Forms - T1 L4 2 2 02-Dec-27 03-Dec-27

A11350 PT Slab Inspection - T1 L4 1 1 06-Dec-27 06-Dec-27

A11360 Place PT Slab (Deck of L4) - T1 L4 1 1 07-Dec-27 07-Dec-27

A11370 PT Slab Cure - T1 L4 3 3 08-Dec-27 10-Dec-27

A11380 Stress Cables - T1 L4 1 1 13-Dec-27 13-Dec-27

A11400 Install Shoring - T1 L4 13 13 23-Dec-27 19-Jan-28

A11410 Install Decking - T1 L4 9 9 14-Jan-28 27-Jan-28

A11480 Strip & Remove Shoring - T1 L4 5 5 15-May-28 19-May-28

Strucutural SteelStrucutural Steel 10 10 12-May-28 25-May-28

A12210 Set Steel Trusses @ Auditorium - T1 L4 5 5 12-May-28 18-May-28

A20840 Install Metal Decking @ Auditorium - T1 L4 2 2 19-May-28 22-May-28

A12440 Inspection @ Auditorium - T1 L4 1 1 23-May-28 23-May-28

A12450 Prep & Place SOMD @ Auditorium - T1 L4 2 2 24-May-28 25-May-28

Level 5Level 5 101 101 20-Jan-28 09-Jun-28

Walls & ColumnsWalls & Columns 11 11 09-Feb-28 23-Feb-28

A19940 Form Walls & Columns - T1 L5 3 3 09-Feb-28 11-Feb-28

A19950 Wall & Column Reinforcing - T1 L5 3 3 14-Feb-28 16-Feb-28

A19960 Pour Walls & Columns - T1 L5 1 1 17-Feb-28 17-Feb-28

A19970 Cure Walls & Columns - T1 L5 3 3 18-Feb-28 22-Feb-28

A19980 Strip Walls & Columns - T1 L5 1 1 23-Feb-28 23-Feb-28

PT SlabsPT Slabs 92 92 20-Jan-28 26-May-28

A12350 In-Slab MEP - T1 L5 7 7 20-Jan-28 28-Jan-28

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

In-Slab MEP - T1 L3

Install Slab Reinforcing & PT Cables - T1 L3

Install Edge Forms - T1 L3

PT Slab Inspection - T1 L3

Place PT Slab (Deck of L3) - T1 L3

PT Slab Cure - T1 L3

Stress Cables - T1 L3

Install Shoring - T1 L3

Install Decking - T1 L3

Strip & Remove Shoring - T1 L3

Erect Steel Columns & Girders @ Auditorium - T1 L3

Form Walls & Columns - T1 L4

Wall & Column Reinforcing - T1 L4

Pour Walls & Columns - T1 L4

Cure Walls & Columns - T1 L4

Strip Walls & Columns - T1 L4

In-Slab MEP - T1 L4

Install Slab Reinforcing & PT Cables - T1 L4

Install Edge Forms - T1 L4

PT Slab Inspection - T1 L4

Place PT Slab (Deck of L4) - T1 L4

PT Slab Cure - T1 L4

Stress Cables - T1 L4

Install Shoring - T1 L4

Install Decking - T1 L4

Strip & Remove Shoring - T1 L4

Set Steel Trusses @ Auditorium - T1 L4

Install Metal Decking @ Auditorium - T1 L4

Inspection @ Auditorium - T1 L4

Prep & Place SOMD @ Auditorium - T1 L4

Form Walls & Columns - T1 L5

Wall & Column Reinforcing - T1 L5

Pour Walls & Columns - T1 L5

Cure Walls & Columns - T1 L5

Strip Walls & Columns - T1 L5

In-Slab MEP - T1 L5

Rem Dur

Start Finish

A11430 Install Slab Reinforcing & PT Cables - T1 L5 5 5 25-Jan-28 31-Jan-28

A11420 Install Edge Forms - T1 L5 2 2 28-Jan-28 31-Jan-28

A11440 PT Slab Inspection - T1 L5 1 1 01-Feb-28 01-Feb-28

A11450 Place PT Slab (Deck of L5) - T1 L5 1 1 02-Feb-28 02-Feb-28

A11460 PT Slab Cure - T1 L5 3 3 03-Feb-28 07-Feb-28

A11470 Stress Cables - T1 L5 1 1 08-Feb-28 08-Feb-28

A11490 Install Shoring - T1 L5 11 11 18-Feb-28 03-Mar-28

A11500 Install Decking - T1 L5 8 8 03-Mar-28 14-Mar-28

A11570 Strip & Remove Shoring - T1 L5 5 5 22-May-28 26-May-28

Structural SteelStructural Steel 10 10 26-May-28 09-Jun-28

A12220 Install Decking @ Auditorium - T1 L5 5 5 26-May-28 02-Jun-28

A12230 Prep & Place Slab on Metal Deck @ Auditorium - T1 L5 5 5 05-Jun-28 09-Jun-28

Level 6Level 6 63 63 08-Mar-28 05-Jun-28

Walls & ColumnsWalls & Columns 11 11 27-Mar-28 10-Apr-28

A19990 Form Walls & Columns - T1 L6 3 3 27-Mar-28 29-Mar-28

A20000 Wall & Column Reinforcing - T1 L6 3 3 30-Mar-28 03-Apr-28

A20010 Pour Walls & Columns - T1 L6 1 1 04-Apr-28 04-Apr-28

A20020 Cure Walls & Columns - T1 L6 3 3 05-Apr-28 07-Apr-28

A20030 Strip Walls & Columns - T1 L6 1 1 10-Apr-28 10-Apr-28

PT SlabsPT Slabs 63 63 08-Mar-28 05-Jun-28

A12360 In-Slab MEP - T1 L6 6 6 08-Mar-28 15-Mar-28

A11520 Install Slab Reinforcing & PT Cables - T1 L6 5 5 10-Mar-28 16-Mar-28

A11510 Install Edge Forms - T1 L6 2 2 15-Mar-28 16-Mar-28

A11530 PT Slab Inspection - T1 L6 1 1 17-Mar-28 17-Mar-28

A11540 Place PT Slab (Deck of L6) - T1 L6 1 1 20-Mar-28 20-Mar-28

A11550 PT Slab Cure - T1 L6 3 3 21-Mar-28 23-Mar-28

A11560 Stress Cables - T1 L6 1 1 24-Mar-28 24-Mar-28

A11580 Install Shoring - T1 L6 15 15 05-Apr-28 25-Apr-28

A11590 Install Decking - T1 L6 10 10 19-Apr-28 02-May-28

A11660 Strip & Remove Shoring - T1 L6 5 5 30-May-28 05-Jun-28

RoofRoof 50 50 24-Apr-28 03-Jul-28

Main RoofMain Roof 50 50 24-Apr-28 03-Jul-28

A12370 In-Slab MEP - T1 Main Roof 8 8 24-Apr-28 03-May-28

A11610 Install Slab Reinforcing & PT Cables - T1 Main Roof 6 6 27-Apr-28 04-May-28

A11600 Install Edge Forms - T1 Main Roof 2 2 03-May-28 04-May-28

A11620 PT Slab Inspection - T1 Main Roof 1 1 05-May-28 05-May-28

A11630 Place PT Slab (Deck of Roof) - T1 Main Roof 1 1 08-May-28 08-May-28

A11640 PT Slab Cure - T1 Main Roof 3 3 09-May-28 11-May-28

A11650 Stress Cables - T1 Main Roof 1 1 12-May-28 12-May-28

A20660 Install Roof - T1 Main Roof 20 20 06-Jun-28 03-Jul-28

High Roof @ Stair TowersHigh Roof @ Stair Towers 17 17 15-May-28 07-Jun-28

A20860 Install Shoring - T1 High Roof 3 3 15-May-28 17-May-28

A20870 Install Decking - T1 High Roof 1 1 18-May-28 18-May-28

A20890 Install Edge Forms - T1 High Roof 1 1 19-May-28 19-May-28

A20880 Install Slab Reinforcing & PT Cables - T1 High Roof 2 2 19-May-28 22-May-28

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Install Slab Reinforcing & PT Cables - T1 L5

Install Edge Forms - T1 L5

PT Slab Inspection - T1 L5

Place PT Slab (Deck of L5) - T1 L5

PT Slab Cure - T1 L5

Stress Cables - T1 L5

Install Shoring - T1 L5

Install Decking - T1 L5

Strip & Remove Shoring - T1 L5

Install Decking @ Auditorium - T1 L5

Prep & Place Slab on Metal Deck @ Auditorium - T1 L5

Form Walls & Columns - T1 L6

Wall & Column Reinforcing - T1 L6

Pour Walls & Columns - T1 L6

Cure Walls & Columns - T1 L6

Strip Walls & Columns - T1 L6

In-Slab MEP - T1 L6

Install Slab Reinforcing & PT Cables - T1 L6

Install Edge Forms - T1 L6

PT Slab Inspection - T1 L6

Place PT Slab (Deck of L6) - T1 L6

PT Slab Cure - T1 L6

Stress Cables - T1 L6

Install Shoring - T1 L6

Install Decking - T1 L6

Strip & Remove Shoring - T1 L6

In-Slab MEP - T1 Main Roof

Install Slab Reinforcing & PT Cables - T1 Main Roof

Install Edge Forms - T1 Main Roof

PT Slab Inspection - T1 Main Roof

Place PT Slab (Deck of Roof) - T1 Main Roof

PT Slab Cure - T1 Main Roof

Stress Cables - T1 Main Roof

Install Roof - T1 Main Roof

Install Shoring - T1 High Roof

Install Decking - T1 High Roof

Install Edge Forms - T1 High Roof

Install Slab Reinforcing & PT Cables - T1 High Roof

Rem Dur

Start Finish

A20900 PT Slab Inspection - T1 High Roof 1 1 23-May-28 23-May-28

A20910 Place PT Slab (Deck of Roof) - T1 High Roof 1 1 24-May-28 24-May-28

A20920 PT Slab Cure - T1 High Roof 3 3 25-May-28 30-May-28

A20930 Stress Cables - T1 High Roof 1 1 31-May-28 31-May-28

A20940 Install Roof - T1 High Roof 5 5 01-Jun-28 07-Jun-28

Tower 2 - ResidentialTower 2 - Residential 289 289 01-Sep-27 26-Oct-28

Level 1Level 1 114 114 01-Sep-27 21-Feb-28

Walls & ColumnsWalls & Columns 11 11 01-Sep-27 16-Sep-27

A20040 Form Walls & Columns - T2 L1 3 3 01-Sep-27 03-Sep-27

A20050 Wall & Column Reinforcing - T2 L1 3 3 07-Sep-27 09-Sep-27

A20060 Pour Walls & Columns - T2 L1 1 1 10-Sep-27 10-Sep-27

A20070 Cure Walls & Columns - T2 L1 3 3 13-Sep-27 15-Sep-27

A20080 Strip Walls & Columns - T2 L1 1 1 16-Sep-27 16-Sep-27

PT SlabsPT Slabs 107 107 13-Sep-27 21-Feb-28

A11670 Install Shoring - T2 L1 15 15 13-Sep-27 01-Oct-27

A11680 Install Decking - T2 L1 10 10 27-Sep-27 08-Oct-27

A11750 Strip & Remove Shoring - T2 L1 5 5 15-Feb-28 21-Feb-28

Level 2Level 2 164 164 30-Sep-27 30-May-28

Walls & ColumnsWalls & Columns 11 11 21-Oct-27 04-Nov-27

A20090 Form Walls & Columns - T2 L2 3 3 21-Oct-27 25-Oct-27

A20100 Wall & Column Reinforcing - T2 L2 3 3 26-Oct-27 28-Oct-27

A20110 Pour Walls & Columns - T2 L2 1 1 29-Oct-27 29-Oct-27

A20120 Cure Walls & Columns - T2 L2 3 3 01-Nov-27 03-Nov-27

A20130 Strip Walls & Columns - T2 L2 1 1 04-Nov-27 04-Nov-27

PT SlabsPT Slabs 164 164 30-Sep-27 30-May-28

A12380 In-Slab MEP - T2 L2 8 8 30-Sep-27 11-Oct-27

A11700 Install Slab Reinforcing & PT Cables - T2 L2 6 6 05-Oct-27 12-Oct-27

A11690 Install Edge Forms - T2 L2 2 2 11-Oct-27 12-Oct-27

A11710 PT Slab Inspection - T2 L2 1 1 13-Oct-27 13-Oct-27

A11720 Place PT Slab (Deck of L2) - T2 L2 1 1 14-Oct-27 14-Oct-27

A11730 PT Slab Cure - T2 L2 3 3 15-Oct-27 19-Oct-27

A11740 Stress Cables - T2 L2 1 1 20-Oct-27 20-Oct-27

A11760 Install Shoring - T2 L2 15 15 01-Nov-27 19-Nov-27

A11770 Install Decking - T2 L2 10 10 15-Nov-27 30-Nov-27

A11840 Strip & Remove Shoring - T2 L2 5 5 23-May-28 30-May-28

Level 2.5Level 2.5 164 164 18-Nov-27 19-Jul-28

Walls & ColumnsWalls & Columns 11 11 17-Dec-27 10-Jan-28

A20140 Form Walls & Columns - T2 L2.5 3 3 17-Dec-27 21-Dec-27

A20150 Wall & Column Reinforcing - T2 L2.5 3 3 22-Dec-27 03-Jan-28

A20160 Pour Walls & Columns - T2 L2.5 1 1 04-Jan-28 04-Jan-28

A20170 Cure Walls & Columns - T2 L2.5 3 3 05-Jan-28 07-Jan-28

A20180 Strip Walls & Columns - T2 L2.5 1 1 10-Jan-28 10-Jan-28

PT SlabsPT Slabs 164 164 18-Nov-27 19-Jul-28

A12390 In-Slab MEP - T2 L2.5 8 8 18-Nov-27 01-Dec-27

A11790 Install Slab Reinforcing & PT Cables - T2 L2.5 6 6 23-Nov-27 02-Dec-27

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

PT Slab Inspection - T1 High Roof

Place PT Slab (Deck of Roof) - T1 High Roof

PT Slab Cure - T1 High Roof

Stress Cables - T1 High Roof

Install Roof - T1 High Roof

Form Walls & Columns - T2 L1

Wall & Column Reinforcing - T2 L1

Pour Walls & Columns - T2 L1

Cure Walls & Columns - T2 L1

Strip Walls & Columns - T2 L1

Install Shoring - T2 L1

Install Decking - T2 L1

Strip & Remove Shoring - T2 L1

Form Walls & Columns - T2 L2

Wall & Column Reinforcing - T2 L2

Pour Walls & Columns - T2 L2

Cure Walls & Columns - T2 L2

Strip Walls & Columns - T2 L2

In-Slab MEP - T2 L2

Install Slab Reinforcing & PT Cables - T2 L2

Install Edge Forms - T2 L2

PT Slab Inspection - T2 L2

Place PT Slab (Deck of L2) - T2 L2

PT Slab Cure - T2 L2

Stress Cables - T2 L2

Install Shoring - T2 L2

Install Decking - T2 L2

Strip & Remove Shoring - T2 L2

Form Walls & Columns - T2 L2.5

Wall & Column Reinforcing - T2 L2.5

Pour Walls & Columns - T2 L2.5

Cure Walls & Columns - T2 L2.5

Strip Walls & Columns - T2 L2.5

In-Slab MEP - T2 L2.5

Install Slab Reinforcing & PT Cables - T2 L2.5

Rem Dur

Start Finish

A11780 Install Edge Forms - T2 L2.5 2 2 01-Dec-27 02-Dec-27

A11800 PT Slab Inspection - T2 L2.5 1 1 03-Dec-27 03-Dec-27

A11810 Place PT Slab (Deck of L3) - T2 L2.5 5 5 06-Dec-27 10-Dec-27

A11820 PT Slab Cure - T2 L2.5 3 3 13-Dec-27 15-Dec-27

A11830 Stress Cables - T2 L2.5 1 1 16-Dec-27 16-Dec-27

A11850 Install Shoring - T2 L2.5 15 15 05-Jan-28 26-Jan-28

A11860 Install Decking - T2 L2.5 10 10 20-Jan-28 02-Feb-28

A11930 Strip & Remove Shoring - T2 L2.5 5 5 13-Jul-28 19-Jul-28

Level 3.5Level 3.5 160 160 25-Jan-28 07-Sep-28

Walls & ColumnsWalls & Columns 11 11 15-Feb-28 29-Feb-28

A20430 Form Walls & Columns - T2 L3.5 3 3 15-Feb-28 17-Feb-28

A20440 Wall & Column Reinforcing - T2 L3.5 3 3 18-Feb-28 22-Feb-28

A20450 Pour Walls & Columns - T2 L3.5 1 1 23-Feb-28 23-Feb-28

A20460 Cure Walls & Columns - T2 L3.5 3 3 24-Feb-28 28-Feb-28

A20470 Strip Walls & Columns - T2 L3.5 1 1 29-Feb-28 29-Feb-28

PT SlabsPT Slabs 160 160 25-Jan-28 07-Sep-28

A12400 In-Slab MEP - T2 L3.5 8 8 25-Jan-28 03-Feb-28

A11880 Install Slab Reinforcing & PT Cables - T2 L3.5 6 6 28-Jan-28 04-Feb-28

A11870 Install Edge Forms - T2 L3.5 2 2 03-Feb-28 04-Feb-28

A11890 PT Slab Inspection - T2 L3.5 1 1 07-Feb-28 07-Feb-28

A11900 Place PT Slab (Deck of L4) - T2 L3.5 1 1 08-Feb-28 08-Feb-28

A11910 PT Slab Cure - T2 L3.5 3 3 09-Feb-28 11-Feb-28

A11920 Stress Cables - T2 L3.5 1 1 14-Feb-28 14-Feb-28

A20340 Install Shoring - T2 L3.5 15 15 24-Feb-28 15-Mar-28

A20350 Install Decking - T2 L3.5 10 10 09-Mar-28 22-Mar-28

A20420 Strip & Remove Shoring - T2 L3.5 5 5 31-Aug-28 07-Sep-28

Level 4.5Level 4.5 130 130 14-Mar-28 14-Sep-28

Walls & ColumnsWalls & Columns 11 11 04-Apr-28 18-Apr-28

A20190 Form Walls & Columns - T2 L4.5 3 3 04-Apr-28 06-Apr-28

A20200 Wall & Column Reinforcing - T2 L4.5 3 3 07-Apr-28 11-Apr-28

A20210 Pour Walls & Columns - T2 L4.5 1 1 12-Apr-28 12-Apr-28

A20220 Cure Walls & Columns - T2 L4.5 3 3 13-Apr-28 17-Apr-28

A20230 Strip Walls & Columns - T2 L4.5 1 1 18-Apr-28 18-Apr-28

PT SlabsPT Slabs 130 130 14-Mar-28 14-Sep-28

A20700 In-Slab MEP - T2 L4.5 8 8 14-Mar-28 23-Mar-28

A20370 Install Slab Reinforcing & PT Cables - T2 L4.5 6 6 17-Mar-28 24-Mar-28

A20360 Install Edge Forms - T2 L4.5 2 2 23-Mar-28 24-Mar-28

A20380 PT Slab Inspection - T2 L4.5 1 1 27-Mar-28 27-Mar-28

A20390 Place PT Slab (Deck of L4) - T2 L4.5 1 1 28-Mar-28 28-Mar-28

A20400 PT Slab Cure - T2 L4.5 3 3 29-Mar-28 31-Mar-28

A20410 Stress Cables - T2 L4.5 1 1 03-Apr-28 03-Apr-28

A11940 Install Shoring - T2 L4.5 15 15 13-Apr-28 03-May-28

A11950 Install Decking - T2 L4.5 10 10 27-Apr-28 10-May-28

A12020 Strip & Remove Shoring - T2 L4.5 5 5 08-Sep-28 14-Sep-28

Level 5Level 5 100 100 02-May-28 21-Sep-28

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Install Edge Forms - T2 L2.5

PT Slab Inspection - T2 L2.5

Place PT Slab (Deck of L3) - T2 L2.5

PT Slab Cure - T2 L2.5

Stress Cables - T2 L2.5

Install Shoring - T2 L2.5

Install Decking - T2 L2.5

Strip & Remove Shoring - T2 L2.5

Form Walls & Columns - T2 L3.5

Wall & Column Reinforcing - T2 L3.5

Pour Walls & Columns - T2 L3.5

Cure Walls & Columns - T2 L3.5

Strip Walls & Columns - T2 L3.5

In-Slab MEP - T2 L3.5

Install Slab Reinforcing & PT Cables - T2 L3.5

Install Edge Forms - T2 L3.5

PT Slab Inspection - T2 L3.5

Place PT Slab (Deck of L4) - T2 L3.5

PT Slab Cure - T2 L3.5

Stress Cables - T2 L3.5

Install Shoring - T2 L3.5

Install Decking - T2 L3.5

Strip & Remove Shoring - T2 L3.5

Form Walls & Columns - T2 L4.5

Wall & Column Reinforcing - T2 L4.5

Pour Walls & Columns - T2 L4.5

Cure Walls & Columns - T2 L4.5

Strip Walls & Columns - T2 L4.5

In-Slab MEP - T2 L4.5

Install Slab Reinforcing & PT Cables - T2 L4.5

Install Edge Forms - T2 L4.5

PT Slab Inspection - T2 L4.5

Place PT Slab (Deck of L4) - T2 L4.5

PT Slab Cure - T2 L4.5

Stress Cables - T2 L4.5

Install Shoring - T2 L4.5

Install Decking - T2 L4.5

Strip & Remove Shoring - T2 L4.5

Rem Dur

Start Finish

Walls & ColumnsWalls & Columns 11 11 23-May-28 07-Jun-28

A20240 Form Walls & Columns - T2 L5 3 3 23-May-28 25-May-28

A20250 Wall & Column Reinforcing - T2 L5 3 3 26-May-28 31-May-28

A20260 Pour Walls & Columns - T2 L5 1 1 01-Jun-28 01-Jun-28

A20270 Cure Walls & Columns - T2 L5 3 3 02-Jun-28 06-Jun-28

A20280 Strip Walls & Columns - T2 L5 1 1 07-Jun-28 07-Jun-28

PT SlabsPT Slabs 100 100 02-May-28 21-Sep-28

A12410 In-Slab MEP - T2 L5 8 8 02-May-28 11-May-28

A11970 Install Slab Reinforcing & PT Cables - T2 L5 6 6 05-May-28 12-May-28

A11960 Install Edge Forms - T2 L5 2 2 11-May-28 12-May-28

A11980 PT Slab Inspection - T2 L5 1 1 15-May-28 15-May-28

A11990 Place PT Slab (Deck of L5) - T2 L5 1 1 16-May-28 16-May-28

A12000 PT Slab Cure - T2 L5 3 3 17-May-28 19-May-28

A12010 Stress Cables - T2 L5 1 1 22-May-28 22-May-28

A12030 Install Shoring - T2 L5 15 15 02-Jun-28 22-Jun-28

A12040 Install Decking - T2 L5 10 10 16-Jun-28 29-Jun-28

A12110 Strip & Remove Shoring - T2 L5 5 5 15-Sep-28 21-Sep-28

Level 6Level 6 70 70 21-Jun-28 28-Sep-28

Walls & ColumnsWalls & Columns 11 11 13-Jul-28 27-Jul-28

A20290 Form Walls & Columns - T2 L6 3 3 13-Jul-28 17-Jul-28

A20300 Wall & Column Reinforcing - T2 L6 3 3 18-Jul-28 20-Jul-28

A20310 Pour Walls & Columns - T2 L6 1 1 21-Jul-28 21-Jul-28

A20320 Cure Walls & Columns - T2 L6 3 3 24-Jul-28 26-Jul-28

A20330 Strip Walls & Columns - T2 L6 1 1 27-Jul-28 27-Jul-28

PT SlabsPT Slabs 70 70 21-Jun-28 28-Sep-28

A12420 In-Slab MEP - T2 L6 8 8 21-Jun-28 30-Jun-28

A12060 Install Slab Reinforcing & PT Cables - T2 L6 6 6 26-Jun-28 03-Jul-28

A12050 Install Edge Forms - T2 L6 2 2 30-Jun-28 03-Jul-28

A12070 PT Slab Inspection - T2 L6 1 1 05-Jul-28 05-Jul-28

A12080 Place PT Slab (Deck of L6) - T2 L6 1 1 06-Jul-28 06-Jul-28

A12090 PT Slab Cure - T2 L6 3 3 07-Jul-28 11-Jul-28

A12100 Stress Cables - T2 L6 1 1 12-Jul-28 12-Jul-28

A12120 Install Shoring - T2 L6 15 15 24-Jul-28 11-Aug-28

A12130 Install Decking - T2 L6 10 10 07-Aug-28 18-Aug-28

A12200 Strip & Remove Shoring - T2 L6 5 5 22-Sep-28 28-Sep-28

RoofRoof 55 55 10-Aug-28 26-Oct-28

Main RoofMain Roof 55 55 10-Aug-28 26-Oct-28

A12430 In-Slab MEP - T2 Main Roof 8 8 10-Aug-28 21-Aug-28

A12150 Install Slab Reinforcing & PT Cables - T2 Main Roof 6 6 15-Aug-28 22-Aug-28

A12140 Install Edge Forms - T2 Main Roof 2 2 21-Aug-28 22-Aug-28

A12160 PT Slab Inspection - T2 Main Roof 1 1 23-Aug-28 23-Aug-28

A12170 Place PT Slab (Deck of Roof) - T2 Main Roof 1 1 24-Aug-28 24-Aug-28

A12180 PT Slab Cure - T2 Main Roof 3 3 25-Aug-28 29-Aug-28

A12190 Stress Cables - T2 Main Roof 1 1 30-Aug-28 30-Aug-28

A20670 Install Roof - T2 Main Roof 20 20 29-Sep-28 26-Oct-28

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Form Walls & Columns - T2 L5

Wall & Column Reinforcing - T2 L5

Pour Walls & Columns - T2 L5

Cure Walls & Columns - T2 L5

Strip Walls & Columns - T2 L5

In-Slab MEP - T2 L5

Install Slab Reinforcing & PT Cables - T2 L5

Install Edge Forms - T2 L5

PT Slab Inspection - T2 L5

Place PT Slab (Deck of L5) - T2 L5

PT Slab Cure - T2 L5

Stress Cables - T2 L5

Install Shoring - T2 L5

Install Decking - T2 L5

Strip & Remove Shoring - T2 L5

Form Walls & Columns - T2 L6

Wall & Column Reinforcing - T2 L6

Pour Walls & Columns - T2 L6

Cure Walls & Columns - T2 L6

Strip Walls & Columns - T2 L6

In-Slab MEP - T2 L6

Install Slab Reinforcing & PT Cables - T2 L6

Install Edge Forms - T2 L6

PT Slab Inspection - T2 L6

Place PT Slab (Deck of L6) - T2 L6

PT Slab Cure - T2 L6

Stress Cables - T2 L6

Install Shoring - T2 L6

Install Decking - T2 L6

Strip & Remove Shoring - T2 L6

In-Slab MEP - T2 Main Roof

Install Slab Reinforcing & PT Cables - T2 Main Roof

Install Edge Forms - T2 Main Roof

PT Slab Inspection - T2 Main Roof

Place PT Slab (Deck of Roof) - T2 Main Roof

PT Slab Cure - T2 Main Roof

Stress Cables - T2 Main Roof

Install Roof - T2 Main Roof

Rem Dur

Start Finish

High Roof @ Stair TowersHigh Roof @ Stair Towers 17 17 31-Aug-28 25-Sep-28

A20950 Install Shoring - T2 High Roof 3 3 31-Aug-28 05-Sep-28

A20960 Install Decking - T2 High Roof 1 1 06-Sep-28 06-Sep-28

A20980 Install Edge Forms - T2 High Roof 1 1 07-Sep-28 07-Sep-28

A20970 Install Slab Reinforcing & PT Cables - T2 High Roof 2 2 07-Sep-28 08-Sep-28

A20990 PT Slab Inspection - T2 High Roof 1 1 11-Sep-28 11-Sep-28

A21000 Place PT Slab (Deck of Roof) - T2 High Roof 1 1 12-Sep-28 12-Sep-28

A21010 PT Slab Cure - T2 High Roof 3 3 13-Sep-28 15-Sep-28

A21020 Stress Cables - T2 High Roof 1 1 18-Sep-28 18-Sep-28

A21030 Install Roof - T2 High Roof 5 5 19-Sep-28 25-Sep-28

Exterior FinishesExterior Finishes 112 112 27-Mar-28 31-Aug-28

Elevation 1 - SouthElevation 1 - South 87 87 27-Mar-28 27-Jul-28

A7790 Sub Mob - Elev 1 South 5 5 27-Mar-28 31-Mar-28

A5360 Exterior Framing - Elev 1 South 10 10 03-Apr-28 14-Apr-28

A8460 Wait ing on Crews & Material - Elev 1 South 5 5 17-Apr-28 21-Apr-28

A5370 Exterior Sheathing - Elev 1 South 5 5 24-Apr-28 28-Apr-28

A5380 Install Airbarrier - Elev 1 South 5 5 01-May-28 05-May-28

A5520 Mason Mob - Elev 1 South 2 2 08-May-28 09-May-28

A5400 Install Brick - Elev 1 South 15 15 10-May-28 31-May-28

A8560 Install Window Frames - Elev 1 South 5 5 10-May-28 16-May-28

A8630 Measure & Fabricate Glass - Elev 1 South 40 40 17-May-28 13-Jul-28

A5390 Install Exterior Glass - Elev 1 South 5 5 14-Jul-28 20-Jul-28

A5410 Install Metal Panel - Elev 1 South 5 5 21-Jul-28 27-Jul-28

A6370 Stone Tile Install - Elev 1 South 5 5 21-Jul-28 27-Jul-28

Elevation 2 - EastElevation 2 - East 97 97 03-Apr-28 17-Aug-28

A5420 Exterior Framing - Elev 2 East 10 10 03-Apr-28 14-Apr-28

A5430 Exterior Sheathing - Elev 2 East 5 5 17-Apr-28 21-Apr-28

A5440 Install Airbarrier - Elev 2 East 5 5 24-Apr-28 28-Apr-28

A8570 Install Window Frames - Elev 2 East 5 5 17-May-28 23-May-28

A5460 Install Brick - Elev 2 East 15 15 01-Jun-28 21-Jun-28

A5450 Install Exterior Glass - Elev 2 East 5 5 14-Jul-28 20-Jul-28

A5470 Install Metal Panel - Elev 2 East 10 10 21-Jul-28 03-Aug-28

A6380 Stone Tile Install - Elev 2 East 10 10 04-Aug-28 17-Aug-28

Elevation 3 - NorthElevation 3 - North 87 87 03-Apr-28 03-Aug-28

A5480 Exterior Framing - Elev 3 North 5 5 03-Apr-28 07-Apr-28

A5490 Exterior Sheathing - Elev 3 North 3 3 10-Apr-28 12-Apr-28

A5500 Install Airbarrier - Elev 3 North 3 3 01-May-28 03-May-28

A8580 Install Window Frames - Elev 3 North 5 5 24-May-28 31-May-28

A5510 Install Exterior Glass - Elev 3 North 5 5 14-Jul-28 20-Jul-28

A5530 Install Metal Panel - Elev 3 North 8 8 21-Jul-28 01-Aug-28

A10050 Stone Tile Install - Elev 3 North 10 10 21-Jul-28 03-Aug-28

Elevation 4 - WestElevation 4 - West 107 107 03-Apr-28 31-Aug-28

A5540 Exterior Framing - Elev 4 West 5 5 03-Apr-28 07-Apr-28

A5550 Exterior Sheathing - Elev 4 West 3 3 10-Apr-28 12-Apr-28

A5560 Install Airbarrier - Elev 4 West 3 3 13-Apr-28 17-Apr-28

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Install Shoring - T2 High Roof

Install Decking - T2 High Roof

Install Edge Forms - T2 High Roof

Install Slab Reinforcing & PT Cables - T2 High Roof

PT Slab Inspection - T2 High Roof

Place PT Slab (Deck of Roof) - T2 High Roof

PT Slab Cure - T2 High Roof

Stress Cables - T2 High Roof

Install Roof - T2 High Roof

Sub Mob - Elev 1 South

Exterior Framing - Elev 1 South

Wait ing on Crews & Material - Elev 1 South

Exterior Sheathing - Elev 1 South

Install Airbarrier - Elev 1 South

Mason Mob - Elev 1 South

Install Brick - Elev 1 South

Install Window Frames - Elev 1 South

Measure & Fabricate Glass - Elev 1 South

Install Exterior Glass - Elev 1 South

Install Metal Panel - Elev 1 South

Stone Tile Install - Elev 1 South

Exterior Framing - Elev 2 East

Exterior Sheathing - Elev 2 East

Install Airbarrier - Elev 2 East

Install Window Frames - Elev 2 East

Install Brick - Elev 2 East

Install Exterior Glass - Elev 2 East

Install Metal Panel - Elev 2 East

Stone Tile Install - Elev 2 East

Exterior Framing - Elev 3 North

Exterior Sheathing - Elev 3 North

Install Airbarrier - Elev 3 North

Install Window Frames - Elev 3 North

Install Exterior Glass - Elev 3 North

Install Metal Panel - Elev 3 North

Stone Tile Install - Elev 3 North

Exterior Framing - Elev 4 West

Exterior Sheathing - Elev 4 West

Install Airbarrier - Elev 4 West

Rem Dur

Start Finish

A8590 Install Window Frames - Elev 4 West 5 5 01-Jun-28 07-Jun-28

A6450 Install Brick - Elev 4 West 10 10 22-Jun-28 06-Jul-28

A5570 Install Exterior Glass - Elev 4 West 5 5 14-Jul-28 20-Jul-28

A5580 Install Metal Panel - Elev 4 West 7 7 21-Jul-28 31-Jul-28

A6440 Stone Tile Install - Elev 4 West 10 10 18-Aug-28 31-Aug-28

Interior FinishesInterior Finishes 302 302 21-Dec-27 01-Mar-29

Tower 1 - Presentation, Auditorium, Lobby & OfficesTower 1 - Presentation, Auditorium, Lobby & Offices 222 222 21-Dec-27 02-Nov-28

Level 1 - Retail Spaces, Main MEP Rooms, Entry Hall, Storage SpacesLevel 1 - Retail Spaces, Main MEP Rooms, Entry Hall, Storage Spaces 86 86 21-Dec-27 21-Apr-28

A12760 Install Track & Hangers - T1 L1 3 3 21-Dec-27 23-Dec-27

A12770 Fire Proofing - T1 L1 7 7 23-Dec-27 04-Jan-28

A12780 Install Mechanical Rough Overhead - T1 L1 15 15 23-Dec-27 14-Jan-28

A12790 Install Electrical Rough Overhead - T1 L1 15 15 27-Dec-27 18-Jan-28

A12800 Install Framing - T1 L1 10 10 28-Dec-27 11-Jan-28

A12810 Install Fire Sprinkler Rough Overhead - T1 L1 15 15 29-Dec-27 20-Jan-28

A12820 Install Plumbing Rough Overhead - T1 L1 15 15 12-Jan-28 02-Feb-28

A12830 Install Inwall Electrical - T1 L1 10 10 12-Jan-28 26-Jan-28

A12840 Install Inwall Plumbing - T1 L1 10 10 12-Jan-28 26-Jan-28

A12850 Inwall Inspection - T1 L1 1 1 27-Jan-28 27-Jan-28

A12860 Hang Drywall - T1 L1 15 15 28-Jan-28 17-Feb-28

A12870 Install Insulation - T1 L1 8 8 02-Feb-28 11-Feb-28

A12880 Tape & Finish Drywall - T1 L1 15 15 09-Feb-28 29-Feb-28

A12890 Install Ceramic Tile - T1 L1 15 15 10-Feb-28 01-Mar-28

A12900 Paint - T1 L1 9 9 18-Feb-28 01-Mar-28

A12910 Install Ceiling Grid - T1 L1 15 15 02-Mar-28 22-Mar-28

A12930 Install Window Frames - T1 L1 10 10 02-Mar-28 15-Mar-28

A13010 Measure & Fabricate Glass - T1 L1 15 15 16-Mar-28 05-Apr-28

A12940 Install Flooring - T1 L1 10 10 23-Mar-28 05-Apr-28

A12950 Install Millwork - T1 L1 10 10 23-Mar-28 05-Apr-28

A12960 Install Mechanical Finishes - T1 L1 8 8 23-Mar-28 03-Apr-28

A12970 Install Electrical Finishes - T1 L1 12 12 23-Mar-28 07-Apr-28

A12980 Install Plumbing Finishes - T1 L1 11 11 23-Mar-28 06-Apr-28

A12990 Install Fire Sprinkler Finishes - T1 L1 8 8 23-Mar-28 03-Apr-28

A13000 Install AV/ Data Finishes - T1 L1 5 5 23-Mar-28 29-Mar-28

A13050 Install Interior Glazing - T1 L1 5 5 06-Apr-28 12-Apr-28

A13030 Install Cabinets Counter Tops - T1 L1 5 5 06-Apr-28 12-Apr-28

A13040 Install ACT Tile - T1 L1 5 5 10-Apr-28 14-Apr-28

A13060 Plumbing Finishes - T1 L1 2 2 13-Apr-28 14-Apr-28

A13070 Install Doors & Hardware - T1 L1 5 5 17-Apr-28 21-Apr-28

A13080 Remaining Floors & Base - T1 L1 5 5 17-Apr-28 21-Apr-28

Level 2 - Auditorium, Main Prefunction, Breakout/Thinking, Consultation RoomsLevel 2 - Auditorium, Main Prefunction, Breakout/Thinking, Consultation Rooms 86 86 16-Feb-28 15-Jun-28

A13100 Install Track & Hangers - T1 L2 3 3 16-Feb-28 18-Feb-28

A13090 Fire Proofing - T1 L2 7 7 18-Feb-28 28-Feb-28

A13110 Install Mechanical Rough Overhead - T1 L2 15 15 18-Feb-28 09-Mar-28

A13120 Install Electrical Rough Overhead - T1 L2 15 15 21-Feb-28 10-Mar-28

A13150 Install Framing - T1 L2 10 10 22-Feb-28 06-Mar-28

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Install Window Frames - Elev 4 West

Install Brick - Elev 4 West

Install Exterior Glass - Elev 4 West

Install Metal Panel - Elev 4 West

Stone Tile Install - Elev 4 West

Install Track & Hangers - T1 L1

Fire Proofing - T1 L1

Install Mechanical Rough Overhead - T1 L1

Install Electrical Rough Overhead - T1 L1

Install Framing - T1 L1

Install Fire Sprinkler Rough Overhead - T1 L1

Install Plumbing Rough Overhead - T1 L1

Install Inwall Electrical - T1 L1

Install Inwall Plumbing - T1 L1

Inwall Inspection - T1 L1

Hang Drywall - T1 L1

Install Insulation - T1 L1

Tape & Finish Drywall - T1 L1

Install Ceramic Tile - T1 L1

Paint - T1 L1

Install Ceiling Grid - T1 L1

Install Window Frames - T1 L1

Measure & Fabricate Glass - T1 L1

Install Flooring - T1 L1

Install Millwork - T1 L1

Install Mechanical Finishes - T1 L1

Install Electrical Finishes - T1 L1

Install Plumbing Finishes - T1 L1

Install Fire Sprinkler Finishes - T1 L1

Install AV/ Data Finishes - T1 L1

Install Interior Glazing - T1 L1

Install Cabinets Counter Tops - T1 L1

Install ACT Tile - T1 L1

Plumbing Finishes - T1 L1

Install Doors & Hardware - T1 L1

Remaining Floors & Base - T1 L1

Install Track & Hangers - T1 L2

Fire Proofing - T1 L2

Install Mechanical Rough Overhead - T1 L2

Install Electrical Rough Overhead - T1 L2

Install Framing - T1 L2

Rem Dur

Start Finish

A13140 Install Fire Sprinkler Rough Overhead - T1 L2 15 15 23-Feb-28 14-Mar-28

A13130 Install Plumbing Rough Overhead - T1 L2 15 15 07-Mar-28 27-Mar-28

A13160 Install Inwall Electrical - T1 L2 10 10 07-Mar-28 20-Mar-28

A13170 Install Inwall Plumbing - T1 L2 10 10 07-Mar-28 20-Mar-28

A13180 Inwall Inspection - T1 L2 1 1 21-Mar-28 21-Mar-28

A13200 Hang Drywall - T1 L2 15 15 22-Mar-28 11-Apr-28

A13190 Install Insulation - T1 L2 8 8 27-Mar-28 05-Apr-28

A13210 Tape & Finish Drywall - T1 L2 15 15 03-Apr-28 21-Apr-28

A13230 Install Ceramic Tile - T1 L2 15 15 04-Apr-28 24-Apr-28

A13220 Paint - T1 L2 9 9 12-Apr-28 24-Apr-28

A13330 Install Ceiling Grid - T1 L2 15 15 25-Apr-28 15-May-28

A13350 Install Window Frames - T1 L2 10 10 25-Apr-28 08-May-28

A13360 Measure & Fabricate Glass - T1 L2 15 15 09-May-28 30-May-28

A13240 Install Flooring - T1 L2 10 10 16-May-28 30-May-28

A13250 Install Millwork - T1 L2 10 10 16-May-28 30-May-28

A13260 Install Mechanical Finishes - T1 L2 8 8 16-May-28 25-May-28

A13270 Install Electrical Finishes - T1 L2 12 12 16-May-28 01-Jun-28

A13280 Install Plumbing Finishes - T1 L2 11 11 16-May-28 31-May-28

A13290 Install Fire Sprinkler Finishes - T1 L2 8 8 16-May-28 25-May-28

A13310 Install AV/ Data Finishes - T1 L2 5 5 16-May-28 22-May-28

A13370 Install Interior Glazing - T1 L2 5 5 31-May-28 06-Jun-28

A13380 Install Cabinets Counter Tops - T1 L2 5 5 31-May-28 06-Jun-28

A13340 Install ACT Tile - T1 L2 5 5 02-Jun-28 08-Jun-28

A13400 Plumbing Finishes - T1 L2 2 2 07-Jun-28 08-Jun-28

A13300 Install Doors & Hardware - T1 L2 5 5 09-Jun-28 15-Jun-28

A13390 Remaining Floors & Base - T1 L2 5 5 09-Jun-28 15-Jun-28

Level 3 - Auditorium Mezzanine, Labs, Offices, & Open Work SpacesLevel 3 - Auditorium Mezzanine, Labs, Offices, & Open Work Spaces 86 86 03-Apr-28 02-Aug-28

A13420 Install Track & Hangers - T1 L3 3 3 03-Apr-28 05-Apr-28

A13410 Fire Proofing - T1 L3 7 7 05-Apr-28 13-Apr-28

A13430 Install Mechanical Rough Overhead - T1 L3 15 15 05-Apr-28 25-Apr-28

A13440 Install Electrical Rough Overhead - T1 L3 15 15 06-Apr-28 26-Apr-28

A13470 Install Framing - T1 L3 10 10 07-Apr-28 20-Apr-28

A13460 Install Fire Sprinkler Rough Overhead - T1 L3 15 15 10-Apr-28 28-Apr-28

A13450 Install Plumbing Rough Overhead - T1 L3 15 15 21-Apr-28 11-May-28

A13480 Install Inwall Electrical - T1 L3 10 10 21-Apr-28 04-May-28

A13490 Install Inwall Plumbing - T1 L3 10 10 21-Apr-28 04-May-28

A13500 Inwall Inspection - T1 L3 1 1 05-May-28 05-May-28

A13520 Hang Drywall - T1 L3 15 15 08-May-28 26-May-28

A13510 Install Insulation - T1 L3 8 8 11-May-28 22-May-28

A13530 Tape & Finish Drywall - T1 L3 15 15 18-May-28 08-Jun-28

A13550 Install Ceramic Tile - T1 L3 15 15 19-May-28 09-Jun-28

A13540 Paint - T1 L3 9 9 30-May-28 09-Jun-28

A13650 Install Ceiling Grid - T1 L3 15 15 12-Jun-28 30-Jun-28

A13670 Install Window Frames - T1 L3 10 10 12-Jun-28 23-Jun-28

A13680 Measure & Fabricate Glass - T1 L3 15 15 26-Jun-28 17-Jul-28

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2026 2027 2028 2029 2030

Install Fire Sprinkler Rough Overhead - T1…