7-06 - PRICING - Jail S AHU.docx
DOCX document 57 KB Posted
- Attached to
- 26RFCSP29 Jail South AHU Replacement
- Solicitation number
- 26RFCSP29
- Issued by
- Williamson County, Texas
About this file
This is a pricing sheet for the Jail South AHU Replacement project issued by Williamson County, Texas through a Competitive Sealed Proposal process. The project consists of phased mechanical system upgrades to air handling units within an actively occupied correctional facility. Respondents must maintain continuous environmental control throughout construction, keeping inmate-area temperatures between 65°F and 80°F. Respondents are required to submit bids using the County-provided pricing sheet without modification; any reworked versions may result in disqualification at the County's sole discretion. The submission must include the bidder's total bid price and estimated construction duration in months from Notice to Proceed to Substantial Completion.
The pricing sheet explicitly identifies excluded costs that will not be reimbursed as construction expenses, consistent with Williamson County's Vendor Reimbursement Policy. Non-reimbursable items include groundbreaking expenses, ribbon-cutting expenses, field office setup and related costs (supplies, cleaning, fire safety and first aid equipment), drinking water, and field office window cleaning. Respondents must account for these excluded costs within their overall pricing strategy and not propose them as billable construction expenses.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6 – Pricing Sheet
Jail S AHU Replacement
Respondent Name:
Respondent must utilize this Pricing Sheet. Any reworked version of this sheet, provided by Respondent as a substitute, may be deemed non-responsive, and may, at the County's sole discretion, result in Respondent's disqualification.
Bidder’s/ Respondent’s Total Bid Price: $
Estimated Construction Duration: months from Notice to Proceed (NTP) to Substantial Completion.
Excluded Costs Williamson County's Vendor Reimbursement Policy (attached to Solicitation) outlines items that will not be paid as proposed Construction costs, including the following:
· Groundbreaking expenses
· Ribbon-cutting expenses
· Field office setup
· Drinking water
· Field office supplies
· Field office cleaning
· Field office fire safety and first aid equipment supplies
· Field office window cleaning 6 - Pricing Sheet Page 1 of 1 Form rev. 09/2024 image1.jpeg
File details come from the government source that posted it. Updated .