7-02.2 Template- Type II.docx
DOCX document 30 KB Posted
- Solicitation number
- UDOT250326MP- 2026
- Issued by
- Utah
About this file
This is a Type II Work Order template issued by the Utah Department of Transportation (UDOT) for the installation, upgrade, or repair of concrete on state routes. The document serves as a template for how UDOT will solicit Type II projects from pre-qualified vendors on the Approved Vendor List (AVL). Contractors must submit detailed estimates with pricing per unit of measure based on work scope descriptions, quantities, and specific project locations identified by route and milepost. The template requires contractors to provide documentation including batch tickets, as-built drawings, and invoices prior to payment. Mandatory site visits with UDOT maintenance representatives must be completed before estimate submission unless UDOT indicates no site visit is anticipated. Contractors must comply with all UDOT 2025 Standards, Specifications, and Drawings, and traffic control and flagging operations will be coordinated with the UDOT representative. Work is subject to specified lane restrictions and limitations of operations that vary by day of week and time of day, which contractors must account for in their cost estimates and production schedules.
Payment will be based on actual quantities placed or performed in the field, with quantities listed in the estimate considered for estimation purposes only and subject to change. Each work item includes equipment, labor, transport, disposal costs, and materials necessary to complete the work. UDOT reserves the right to utilize established state contracts for any bid item, with the decision to use additional state contracts to be made prior to award. This solicitation is part of Stage 1 of an RFSQ process intended to establish an Approved Vendor List for a 12-month qualification period, with the existing AVL list expiring August 31, 2030, and anticipated extension to November 30, 2030. Vendors must resubmit qualifications annually for continued eligibility, and UDOT may reopen the solicitation at any time for requalification of existing vendors or to allow additional vendors to submit responses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5-05. Submittal Form- Attachment A- Agency Terms and Conditions- Yes No.docx | DOCX document | |
| 9-07. Submittal Form- Certifications- Yes No.docx | DOCX document | |
| 3-10. Sample Qualifications Evaluation Sheet.doc | DOC document | |
| 1-08. Title VI.docx | DOCX document | |
| 8-02.1 Items- Measurement Payment.docx | DOCX document | |
| 10-03. Submittal Form- Vendor Set Up Form And W-9.pdf | ||
| 4-01. AVL General Solicitation Information- Concrete.doc | DOC document | |
| 6-06. Submittal Form- Itemized Price List.xlsx | XLSX spreadsheet | |
| 2-04. Submittal Form- Business Confidentiality- Yes No.doc | DOC document | |
| 11-02.0 Scope of Work.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TYPE II WORK ORDER
INSTALLATION, UPGRADE, OR REPAIR OF CONCRETE
NOTICE: This form is NOT to be submitted with the Statement of Qualifications. This form is for information purposes and is an example of how Type II projects will be solicited.
Red text fields are general project information that is to be filled out during project scoping The Utah Department of Transportation (UDOT) is requesting your company to submit a detailed estimate for the paving project as described below.
PROJECT
| Concrete Location (Route & Mile Posts) |
| Route(s) & Milepost(s) |
| UDOT Maintenance Station & Contact |
| Station #### (Name of Station) |
Station Contact (Contact Position) ###-###-#### email@utah.gov
INSTRUCTIONS
| Date of Request |
| ##/##/## |
| Quote Submission Deadline |
| ##/##/## |
| Date of Mandatory Site Visit with UDOT Maintenance Representative before Estimate Submission |
| ##/##/## at ##:## - Provide location details or “We do not anticipate a need for a site visit for this project” |
| Anticipated Completion Date for Scope of Work (weather dependent) |
| ##/##/## - Provide any additional limitations |
RESPONSE
UDOT is seeking a quote to perform insert the proposed work, individual work items, and county in which the work is located. Quote must be submitted as a price per unit of measure. Quantities listed are for estimate purposes only, actual may be more or less and will be determined in the field. Contractor will be paid based on actual quantities placed/performed. Contractor will provide documentation for all items of work prior to receiving payment, including but not limited to: batch tickets, as-builts, and invoices. For project limitations, refer to the Traffic Control and Limitations of Operations section listed below.
SCOPE OF WORK
Contractor will insert detailed description of what the work entails and specifics to the concrete installation(s), upgrade(s) or repair(s). See Table 1 for site locations and general scope. Provide any additional project specifics, for example “Removed asphalt overlay tailings will be the property of the contractor and hauled away by the contractor. The Contractor will remove the overlay without damaging the concrete deck. The contractor is responsible for any damage caused during the removal of the overlay.” Contractor must meet all UDOT 2025 Standards, Specifications, and Drawings.
Traffic Control and flagging operation will be conducted and coordinated with the UDOT Representative.
UDOT reserves the right to utilize established State Contracts for any bid item. The decision to utilize any additional state contracts will be determined prior to award.
Table 1: Concrete Locations of Installation, Upgrade, or Repair
Route
Location
MP
Direction Type (Installation, Upgrade, or Repair)
General Scope
| XX |
| XX |
| XX |
| XX |
| Insert general scope |
Contract items and estimated quantities are listed in Table 2.
Table 2: Contract Items and Estimated Quantities
| No. |
| Item Number |
| Item Description |
| UoM |
| Quantity |
| 1 |
| Insert item number |
| Insert item description |
| Insert Unit |
| XXX |
Each work item includes, but is not limited to any: equipment, labor, transport, disposal costs, and material to complete the item of work. Measurement and payment details for items in the project are shown in Table 3.
Table 3: Measurement and Payment for items not Included or changes to descriptions in Attachment XX
| No. |
| Item Number |
| Item Description |
| UoM |
| 1 |
| Insert item number |
| Insert item description |
Table 3 to be filled out for all items of work without a measurement and payment in Attachment E
TRAFFIC CONTROL AND LIMITATIONS OF OPERATIONS
The limitations of operations for work will be as follows (take these hours into account for production for cost): Modify table as needed
Table: ROUTE Lane Restrictions
| Time |
| Monday - Friday |
| Saturday |
| Sunday |
| Time |
| EB |
| WB |
| EB |
| WB |
| EB |
| WB |
| 0:00 – 0:59 |
| 1 LANE OPEN |
| 1 LANE OPEN |
| 1 LANE OPEN |
| 1 LANE OPEN |
| 1 LANE OPEN |
| 1 LANE OPEN |
| 0:00 – 0:59 |
1:00 – 1:59
1:00 – 1:59
2:00 – 2:59
2:00 – 2:59
3:00 – 3:59
3:00 – 3:59
4:00 – 4:59
4:00 – 4:59
| 5:00 – 5:59 |
| ALL LANES OPEN |
| ALL LANES OPEN |
5:00 – 5:59
6:00 – 6:59
6:00 – 6:59
7:00 – 7:59
7:00 – 7:59
8:00 – 8:59
| 2 LANES OPEN |
| 2 LANES OPEN |
8:00 – 8:59
9:00 – 9:59
9:00 – 9:59
10:00 – 10:59
| 2 LANES OPEN |
| 2 LANES OPEN |
| 10:00 – 10:59 |
11:00 – 11:59
11:00 – 11:59
12:00 – 12:59
12:00 – 12:59
13:00 – 13:59
13:00 – 13:59
14:00 – 14:59
14:00 – 14:59
15:00 – 15:59
15:00 – 15:59
16:00 – 16:59
16:00 – 16:59
17:00 – 17:59
| 1 LANE OPEN |
| 1 LANE OPEN |
| 17:00 – 17:59 |
18:00 – 18:59
18:00 – 18:59
19:00 – 19:59
19:00 – 19:59
| 20:00 – 20:59 |
| 2 LANES OPEN |
| 2 LANES OPEN |
| 1 LANE OPEN |
| 1 LANE OPEN |
20:00 – 20:59
21:00 – 21:59
21:00 – 21:59
| 22:00 – 22:59 |
| 1 LANE OPEN |
| 1 LANE OPEN |
22:00 – 22:59
23:00 – 23:59
23:00 – 23:59
TYPE II WORK ORDER Page 2 of 2