7-009 Bid Items.pdf

PDF 156 KB Posted

Attached to
27000031 PD25-01 Ph 3 Sinclair Ave & P26-02 Westridge Loop 250 Decel Lane
Solicitation number
27000031
Issued by
Mason County, Texas

About this file

This Bid Items document from the State of Texas outlines the line-item pricing structure for the Sinclair Phase III and Westridge Loop 250 Deceleration Lane project. The project encompasses the furnishing of materials and labor for roadway improvements, including site preparation, asphalt paving, concrete work, and associated miscellaneous construction activities. The bid items are organized by category and include various quantities for different work elements such as clearing and grubbing, embankment construction, base course installation, asphalt surface courses, concrete pavement, curb and gutter installation, drainage structures, and traffic control devices. Contractors are required to submit unit prices for each bid item, which will be used to calculate total project costs based on the quantities specified in the document.

The pricing structure requires bidders to provide detailed unit costs for all identified line items, enabling the state to evaluate proposals on a standardized basis. The bid items format allows for potential changes in quantities during construction, with final payment determined by actual work completed multiplied by the contracted unit prices. This method protects both the contracting agency and the contractor by establishing clear pricing mechanisms while accommodating unforeseen conditions typical in roadway construction projects. The document serves as the foundation for competitive bidding and establishes the framework through which all proposals will be evaluated and compared.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item No. Quantity Unit Pay Note Unit Price Total Amount

(See Proposal sheet for additional information.)

Description

Total Miscellaneous Items 1 - 4

SINCLAIR PHASE III BID ITEMS

Project Name: Phase III Sinclair Avenue & Westridge Loop 250 Deceleration Lane Project Number: PD25-01 & P26-02

Miscellaneous Items

1)

3) Traffic Control, furnished, installed, complete and in place.

MO

MO

2)

Mobilization, furnished, installed, complete and in place.

Erosion/Sediment Control, furnished, installed, complete and in place.

M1

M2

10 MO

4) Job Site Safety, furnished, installed, complete and in place. 10 MO

M4

M3

D3

Total Demolition Items 1 - 5

Description

3) Unclassified Ditch Excavation, complete and in place.

Demolition Items

SY

LF

D2

D5

LF

2) Unclassified Roadway Excavation (Depth ≤ 30”), complete and in place.

5) Removal & Disposal of Existing Concrete Curb & Gutter, complete and in place.

SY

D4

4) Removal & Dispose of Existing Unclassified Pavement, complete and in place. 38

1) Preparation of Right-of-Way, furnished, installed, complete and in place. 13.16 ACRE D1

2) 8” Gate Valve & Box (MJxMJ/FL), furnished, installed, complete and in place.

Water Items

Description

1) 8” AWWA C-900 DR18, PVC, Water Main, furnished, installed, complete and in place. 567 LF W1

EA W2

3) Ductile Iron Fittings, furnished, installed, complete and in place. 4361 LBS W3

Total Water Items 1 - 5 $___________________________________________________________

5) Open Trenching of Water Main, furnished, installed, complete and in place. 567 LF W5

4) Connect to Existing Water Main, furnished, installed, complete and in place. 6 EA W4

Wastewater Items

Description

1) 8” SDR 26 ASTM D2241, PVC, Wastewater Main, furnished, installed, complete and in place. 500 LF WW1

LF WW4

2) Connection to Existing Manhole, furnished, installed, complete and in place. 5 EA WW2

Total Wastewater Items 1 - 4 $___________________________________________________________

4) Open Trenching of Wastewater Main, furnished, installed, complete and in place.

3) 8” Wastewater Main Plug, furnished, installed, complete and in place. 250 EA WW3

Total Storm Drain Items 1 - 10

2)

4)

36” Reinforced Concrete Pipe (RCP), furnished, installed, complete and in place.

Reinforced Concrete Headwall, furnished, installed, complete and in place.

SD1

LF SD2

EA SD3

Storm Drain Items

Description

1) 6’x2’ Reinforced Concrete Box Culvert furnished, installed, complete and in place. 120 LF

10) 8” Rock Rip-Rap, furnished, installed, complete and in place. 1787 SY SD9

5) Open Trenching of Storm Drain, (0’-10’ Deep), furnished, installed, complete and in place. 290 LF SD4

300 SY SD6

4” Concrete Footing, furnished, installed, complete and in place. 43 SY SD5

8) 6” Concrete Flume, furnished, installed, complete and in place. 713 SY

7)

SD7

6)

Concrete Scupper, furnished, installed, complete and in place.

SD2

3) 24” Reinforced Concrete Pipe (RCP), furnished, installed, complete and in place. 60 LF

1113 SY SD8

9) 6” Concrete Pilot Swale, furnished, installed, complete and in place.

No. Quantity Unit Pay Note Unit Price Total AmountDescription

ST4

LF ST3

Structural Items

12071 LF ST1

2) Fence Gate, complete and in place.

5 EA ST2

1) Barbed-Wire Fence, complete and in place.

4) Bollard, complete and in place.

8 EA

3) Type 3 Barricade (Permenant), complete and in place.

Total Structural Items 1 - 4

Paving Items

Description Subgrade Preparation (Depth ≤ 8”), furnished, installed, complete and in place.

6)

7)

8) 12” Flexible Base (Type A, Grade 4), furnished, installed, complete and in place. 63671 SY P7

P6 2” Type C HMAC Asphalt Pavement Surface Course (PG64-22, 110 LBS / SY @ 1” Thick), furnished, installed, complete and in place.

P6

Unclassified Embankment (Density Controlled), furnished, installed, complete and in place.

3” Type C HMAC Asphalt Pavement Surface Course (PG64-22, 110 LBS / SY @ 1” Thick), furnished, installed, complete and in place.

SY

SY

SY

SY

SY

P4

P5

49113

49113

63671

16372

P3

P1

P2

SY

CY

7” Continuously Reinforced Concrete Pavement, furnished, installed, complete and in place.

7” Jointed Concrete Pavement, furnished, installed, complete and in place.

2” Type D HMAC Asphalt Pavement Surface Course (PG70-22, 110 LBS / SY @ 1” Thick), furnished, installed, complete and in place.

4)

5)

3)

2)

1)

418 SY P7

9) 8” Flexible Base (Type A, Grade 4), furnished, installed, complete and in place.

10) Bituminous Prime Coat (MC-30, 0.20 Gal / SY), furnished, installed, complete and in place. 9823 GAL P8

11) Tack Coat (MC-30, 0.10 Gal / SY), furnished, installed, complete and in place. 4911 GAL P9

12) 8” Concrete Median, furnished, installed, complete and in place. 5983 SY P10

13) 8” Concrete Fillet, furnished, installed, complete and in place. 485 SY P11

14) 8” Concrete Valley Gutter, furnished, installed, complete and in place. 1767 SY P12

15) 7” Commercial Concrete Driveway Approach, furnished, installed, complete and in place. 56 SY P13

11735 LF P14

16) Type A Concrete Curb & Gutter, furnished, installed, complete and in place. 12323 LF P14

18) Type II 5-3/4" Concrete Curb & Gutter, furnished, installed, complete and in place. 318 LF P15

17) Type C Concrete Curb & Gutter, furnished, installed, complete and in place.

SY38

Total Paving Items 1 - 23

23) P19

Flowable Fill / 2-Sack Backfill, furnished, installed, complete and in place.

19) Concrete Pedestrian Access Ramp, furnished, installed, complete and in place. 19 SY P16

5 EA P18

20) 4” Concrete Sidewalk, furnished, installed, complete and in place. 1108 SY P17

22) Water Valve Box Ring & Cover Adjustment, furnished, installed, complete and in place. 11 EA P18

21) Manhole Ring & Cover Adjustment, furnished, installed, complete and in place.

No. Quantity Unit Pay Note Unit Price Total AmountDescription

1) Retroreflectorized Pavement Markings, TxDOT Item 666 (8” White, Solid), furnished, installed, complete and in place.

152 LF T1

Total Traffic Control Items 1 - 10 $___________________________________________________________

Traffic Control Items

2) Retroreflectorized Pavement Markings, TxDOT Item 666 (6” White, Solid), furnished, installed, complete and in place.

12304 LF T1

768 LF T1

3) Retroreflectorized Pavement Markings, TxDOT Item 666

(6” White, Broken, 10'/30'), furnished, installed, complete and in place.

12903 LF T1

5) Retroreflectorized Pavement Markings, TxDOT Item 666

(24” Yellow, Solid), furnished, installed, complete and in place.

254 LF T1

4) Retroreflectorized Pavement Markings, TxDOT Item 666 (6” White, Broken, 2'/6'), furnished, installed, complete and in place.

10) Small Sign Assembly, furnished, installed, complete and in place. 9 EA T3

6) Retroreflectorized Pavement Markings, TxDOT Item 666 (6” Yellow, Solid), furnished, installed, complete and in place.

10353 LF T1

12 EA T2

7) Retroreflectorized Pavement Markings, TxDOT Item 666

(6” Yellow, Solid/Solid), furnished, installed, complete and in place.

240 LF T1

9) Prefabricated Pavement Markings, TxDOT Item 666

(White, Pavement Letter), furnished, installed, complete and in place.

1 EA T2

8) Prefabricated Pavement Markings, TxDOT Item 666 (White, Arrow Symbol), furnished, installed, complete and in place.

3. Water Items $___________________________________________________________________________________________

4. Wastewater Items

7. Paving Items $___________________________________________________________________________________________

Price For:

1. Miscellaneous Items

2. Demolition Items

$___________________________________________________________________________________________Total Price

5. Storm Drain Items $___________________________________________________________________________________________

6. Structural Items $___________________________________________________________________________________________

8. Traffic Control Items $___________________________________________________________________________________________

Proposal-Pvng

File details come from the government source that posted it. Updated .