DMCH CMc Solicitation Amend 5_Solicitation Number 6P1QW-17-1001 Q&A

View the file

Other files

File Type Posted
NIA00003_DMCH_CMc_Award_Notification_180621.pdf PDF
DMCH_CMc_Solicitation_Amend_7_SF-30_180427.pdf PDF
DMCH_CMc_Solicitation_Amend_6_Courts_Design_Guide_2007_base.pdf PDF
DMCH_CMc_Solicitation_Amend_6_Courts_Design_Guide_2016_CH1_2_15_16.pdf PDF
DMCH_CMc_Solicitation_Amend_6_SF-1442_Supplement_Pricing_Form_180404.xlsx XLSX spreadsheet
DMCH_CMc_Solicitation_Amend_6_Courts__Design_Guide_2007_CH18.pdf PDF
DMCH_CMc_Solicitation_Amend_6_Pricing_Form.pdf PDF
DMCH_CMc_Solicitation_Amend_6_SF-30_180404.pdf PDF
DMCH_CMc_Solicitation_Amend_6_GSA_013100_Project_Management_&_Coordination.pdf PDF
DMCH_CMc_Amendment_6_Supplement_180404.pdf PDF
DMCH_CMc_Solicitation_Amend_5_SF-30_180327.pdf PDF
DMCH_CMc_Solicitation_Amend_5_SF-1442_Supplement_Pricing_Form_180315.xlsx XLSX spreadsheet
DMCH_CMc_Solicitation_Amend_5_Division_1_Specifications_180327.pdf PDF
DMCH_CMc_Solicitation_Amend_5_Program_of_Requirements_180323.pdf PDF
DMCH_CMc_Solicitation_Amend_4_Pre_Proposal_Conf_Attendance_180228.pdf PDF
DMCH_CMc_Solicitation_Amend_4_SF-1442_Contract_Price_Form_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_4_SF-1442_180305.pdf PDF
DMCH_CMc_Solicitation_Amend_4_SF-30_180305.pdf PDF
DMCH_CMc_Solicitation_Amend_4_THE_SOLICITATION_(CMc201)_180305.pdf PDF
DMCH_CMc_Amendment_4_Supplement_180305.pdf PDF
DMCH_CMc_Solicitation_Amend_4_Pre_Proposal_Agenda_180228.pdf PDF
DMCH_CMc_Solicitation_Amend_4_CASB_Statement.pdf PDF
DMCH_CMc_Solicitation_Amend_3_SF-1442_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_SF-30_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Program_of_Requirements_180202.pdf PDF
DMCH_CMc_Solicitation_Amend_3_App_B_Small_Business_Utilization_Form_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_SF-1442_Supplement_Pricing_Form_180213.xlsx XLSX spreadsheet
DMCH_CMc_Solicitation_Amend_3_Division_1_Specifications_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Statement_of_Work_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_THE_AGREEMENT_(CMc101)_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_SF24_Bid_Bond_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Wage_Determination_IA180142_dated_180119.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Offeror_Reps_and_Certs_(CMc301)_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_THE_SOLICITATION_(CMc201)_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_GSA_Form_527_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Statement_of_Work_AE_CMa_Attachment_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_2_Attachment_A_Updates_and_Q&A_171116.pdf PDF
DMCH_CMc_Solicitation_Amend_2_SF30_171116.pdf PDF
DMCH_CMc_Statement_of_Work_170906.pdf PDF
DMCH_CMc_Solicitation_Offeror_Reps_and_Certs_(CMc301)_170906.pdf PDF
DMCH_CMc_Solicitation_Appendix_A_Owner_Evaluation_Form_170906.pdf PDF
DMCH_CMc_Solicitation_GSA_Form_527_170906.pdf PDF
DMCH_CMc_Solicitation_Wage_Determination__IA170142_170825.pdf PDF
DMCH_CMc_THE_AGREEMENT_(CMc101)_170906.pdf PDF
DMCH_CMc_THE_SOLICITATION_(CMc201)_170906.pdf PDF
DMCH_CMc_Solicitation_Appendix_B_Small_Business_Utilization_Form_170906.pdf PDF
DMCH_CMc_Statement_of_Work_AE_CMa_Attachment_170906.pdf PDF
DMCH_CMc_Solicitation_SF1442_170906.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number 6P1QW-17-1001 Amendment No. 5- Attachment A

Questions and Responses

Question No. 1: Please confirm the delivery method for the Cost Accounting Standards Notices and Certification Disclosure Statement referenced in Amendment No. 4. FAR 52.230-1 read that one original and one copy are to be provided to the Administrative Contracting Officer.

Should this submittal be delivered under separate cover or included in the proposal? If in the proposal, is there a preference to the location in the proposal?

Response: To be included in the price proposal envelope.

Question No. 2: Is there a preferred location in the proposal response for the Proposal Disclosure – Cost Accounting Practice Changes per FAR 52.230-7 added in Amendment 4?

Please specify volume and location within the desired volume.

Response: To be included in the price proposal envelope

Question No. 3: At the Pre-proposal Meeting, reissuing an updated version of the Supplemental Pricing Form was discussed but Amendment 4 did not include a new version.

Will a new version be issued?

Response: An updated Supplemental Pricing Form is included with Amendment #5.

Question No. 4: In section 3.4.2 of the Program of Requirements, a cost saving option of a variable speed screw chiller is allowed. Can this cost saving option be included in the Base Bid (ECW), or does it need to be presented as a separate Deduct to the Base Bid (ECW)? If a Deduct, where do we include pricing option information such as this on the Price Form or Supplemental Pricing Form?

Response: The POR has been updated to strike through the variable speed screw chiller option. The CMc should price the magnetic bearing chillers as described in the POR.

Question No. 5: In section 3.4.2 of the Program of Requirements, single zone VAV air handlers are specified to serve lobbies and public spaces outside courtrooms at an average size of 2-3000 CFM each. Please specify the quantity of single zone VAV air handlers to be installed.

Response: For the purposes of pricing, the number of single zone units in the 2-3,000 CFM range serving lobbies and public spaces should be 4.

Question No. 6: In section 3.4.2 of the Program of Requirements, fourteen (14) dedicated AHUs ranging in size from 7000-9000 CFM are specified. This Section also specifies providing dedicated multizone VAV AHUs to serve each courtroom/chambers. Are the multizone VAV AHUs for the courtroom/chambers included in the (14) dedicated AHU quantity, or are they in addition to the (14) dedicated AHU quantity?

Response: It is the intent that (14) is the total number of 7,000-9,000CFM AHUs serving courtrooms/chambers and other areas throughout the building that are not public lobbies and corridors.

Question No. 7: In section 3.4.2 of the Program of Requirements, a reversed return primary secondary loop piping configuration for the heating hot water system is specified. Is a primary secondary loop piping configuration required for the chilled water system as well?

Response: Yes primary/secondary loop piping system for the chilled water system will be required.

Question No. 8: In section 3.4.2 of the Program of Requirements, it is specified that spaces served by air handling units will utilize CO2 detectors “in the room” to modulate the required outside air being delivered to the spaces. Is "every occupied room" required to have a CO2 detector, or can a CO2 detector be installed in each AHU's return air duct to control the amount of outside air being delivered to the occupied spaces?

Response: CO2 detection must be in the space and not the return duct. These will not need to be in “every occupied room”. The rooms with the largest concentration of people and most frequent use will require the CO2 detectors. For example, one in each courtroom and one in judge’s chambers conference room but not in other smaller associated rooms. The ventilation rate will be driven by whichever one is activated.

Question No. 9: In section 3.4.2 of the Program of Requirements, a 14,000 CFM purge exhaust system is specified for the mail room. The Room Data Sheet specifies the NSF and ceiling height of the mail room to be 550 NSF and 10 Ft which equates to an air change per hour rate of over 150 utilizing a 14,000 CFM purge exhaust fan. Should the purge exhaust fan be smaller than 14,000 CFM? If so, what size should it be?

Response: At this stage of the project, proceed with the 14,000 CFM purge exhaust rate for the emergency purge exhaust fan.

Question No. 10: In Specification Section 012100, Allowances, Allowance #1 for Exterior Structures is specified for landscaping walls, guard shacks and vehicle barriers. Page 22 of the Program of Requirements specifies five (5) vehicle barriers, control booth/guard shack, etc.

Please verify the vehicle barriers and control booth/guard shack costs are part of Allowance #1.

Response: Allowance #1 includes the five (5) vehicle barricades and control booth/guard shack per the description on page 22 of the Program of Requirements. Language has been updated in the specification section to reflect this.

Question No. 11: Specification Section 013000, Paragraph 1.4, please advise if Primavera P6 is compatible with Meridian Proliance.

Response: Primavera P6 is not compatible with Meridian Proliance.

Question No. 12: Specification Section 013110, Paragraph 1.04.D, please strike the text in the second and third lines between “Section” and “throughout” in this paragraph so offerors are able to accurately define the costs to include for Critical Path Method Scheduling on the project.

Response: Language has been struck-through and updated specification section is included in amendment.

Question No. 13: Specification Section 013110, Paragraph 1.05.B.1, please revise the due date of the Preliminary Schedule from two weeks in advance of Notice to Proceed to 30 calendar days after Contract Award.

Response: The intent of this paragraph is to note the the Preliminary Construction schedule will be required in advance of the Construction Notice to Proceed. (It should be noted that this has been revised to thirty days in advance of the anticipated Construction NTP. There is no requirement for a preliminary schedule immediately after Contract Award.

Question No. 14: Specification Section 013110, Paragraph 1.08.A, please define the number of GSA-requested worker/equipment recording to be anticipated on the project so offerors are able to accurately define the costs to include in our General Conditions for this effort.

Response: This section remains unchanged.

Question No. 15: Specification Section 014000, Quality Assurance & Control specifies the CMc is to include the costs for the Independent Testing Agency. Without understanding the final design concept, the testing is not well defined. Please provide an allowance for Offerors to include in their Price Proposal for the Independent Testing Agency until design is further developed.

Response: Specification Section Allowances 012100 has been modified to include the following language:

Allowances 012100 - 3.3 SCHEDULE OF ALLOWANCE ITEMS B. Allowance Item No. 02: Lump Sum Allowance (not to exceed) for Independent Testing Agency as referenced in Specification Sections: 014000 – Quality Assurance & Control Requirements, 014025 – Quality Control Testing for Air Barrier Systems, and 014100 –

Structural Testing Laboratory Services. Testing/inspections included in this allowance: soil compaction/density/proctor testing, auger cast pile testing, structural steel welding and bolted connections testing, concrete reinforcing steel inspections, concrete compressive strength testing, floor flatness testing, fireproofing thickness and density testing, roofing inspections, elevator inspections, arc flash testing, curtainwall laboratory mockup testing, and air barrier envelope testing. Carry an allowance of $600,000 for such items.

Question No. 16: Specification Section 014025, Quality Control Testing for Air Barrier Systems specifies the CMc is to include the costs for the Independent Testing Agency. Without understanding the final design concept, the testing is not well defined. Please provide an allowance for Offerors to include in their Price Proposal for the Independent Testing Agency until design is further developed.

Response: Specification Section Allowances 012100 has been modified to include the following language:

Allowances 012100 - 3.3 SCHEDULE OF ALLOWANCE ITEMS B. Allowance Item No. 02: Lump Sum Allowance (not to exceed) for Independent Testing Agency as referenced in Specification Sections: 014000 – Quality Assurance & Control Requirements, 014025 – Quality Control Testing for Air Barrier Systems, and 014100 – Structural Testing Laboratory Services. Testing/inspections included in this allowance: soil compaction/density/proctor testing, auger cast pile testing, structural steel welding and bolted connections testing, concrete reinforcing steel inspections, concrete compressive strength testing, floor flatness testing, fireproofing thickness and density testing, roofing inspections, elevator inspections, arc flash testing, curtainwall laboratory mockup testing, and air barrier envelope testing. Carry an allowance of $600,000 for such items.

Question No. 17: Specification Section 014100, Structural Testing Laboratory Services specifies the CMc is to include the costs for the Independent Testing Agency. Without understanding the final design concept, the testing is not well defined. Please provide an allowance for Offerors to include in their Price Proposal for the Independent Testing Agency until design is further developed.

Response: Specification Section Allowances 012100 has been modified to include the following language:

Allowances 012100 - 3.3 SCHEDULE OF ALLOWANCE ITEMS B. Allowance Item No. 02: Lump Sum Allowance (not to exceed) for Independent Testing Agency as referenced in Specification Sections: 014000 – Quality Assurance & Control Requirements, 014025 – Quality Control Testing for Air Barrier Systems, and 014100 – Structural Testing Laboratory Services. Testing/inspections included in this allowance: soil compaction/density/proctor testing, auger cast pile testing, structural steel welding and bolted connections testing, concrete reinforcing steel inspections, concrete compressive strength testing, floor flatness testing, fireproofing thickness and density testing, roofing inspections, elevator inspections, arc flash testing, curtainwall laboratory mockup testing, and air barrier envelope testing. Carry an allowance of $600,000 for such items.

Question No. 18: In Specification Section 015000, Temporary Facilities and Controls, can the permanent HVAC equipment be used for temporary conditioning during construction if the systems are protected by the appropriate filtration and the specified equipment warranties are maintained?

Response: Specification Section 015000 3.2.A.3 has been updated to reflect this. Additional language has been included for required maintenance to ensure equipment is in as "near new" condition as possible at turnover of the building/equipment.

Question No. 19: In the Supplemental Pricing Form, Construction Phase 3472-2, 20 Plumbing - D2090 Other Plumbing Systems is defined as “Number of special fixtures, etc." per note 26.

Please clarify which "special fixtures" are included in this category, how do they differ from the fixtures in the D2010 Plumbing Fixtures category?

Response: Include all items not included in the other D20 line items.

Question No. 20: We understand the pricing forms required to be submitted with our Price Proposal include; SF 1442, Contract Price Form (Amendment 4), Design Phase Services Supplemental Pricing Form, Construction Phase 3472-1 Pricing Form and Construction Phase 3472-2 Pricing Form. Please confirm this understanding is correct.

Response: An updated supplemental pricing sheet is included with Amendment #5. The 3472-1 Pricing Form is no longer required. All other items noted are required as part of the pricing proposal.

Question No. 21: In the Supplemental Pricing Form, Construction Phase 3472-2, 30 HVAC – D3010 Energy Supply is defined as "The Total Power of Heating System" per note 28. Does the cost include labor and material cost for the natural gas piping serving the boilers only, and does the MBH include the total Input MBH of the boilers? If not, what is included in this category?

Response: Yes, this includes cost of labor and material for power (gas) input for the boiler plant based on MBH.

Question No. 22: In the Supplemental Pricing Form, Construction Phase 3472-2, 30 HVAC – D3020 Heating Generating Systems is defined as "The Total Power of Heating System" per note

28. Does the cost include labor and material cost of the boilers only (no piping), and does the MBH include the total Input MBH of the boilers? If not, what is included in this category?

Response: Yes, this includes cost of labor and material for the boiler plant based on MBH.

Question No. 23: In the Supplemental Pricing Form, Construction Phase 3472-2, 30 HVAC – D3030 Cooling Generating Systems is defined as "The Total Power of Cooling Capacity" per note 29. Does the cost include labor and material cost of the chillers only (no piping)? If not, what is included in this category?

Response: Yes, this includes cost of labor and material for the chiller plant only based on tonnage.

Question No. 24: In the Supplemental Pricing Form, Construction Phase 3472-2, 30 HVAC – D3040 Distribution Systems is defined as "Power" per note 30. Does the cost include labor and material cost of the distribution piping systems (chilled & hot water) as well as the labor and material cost for the distribution ductwork systems? Is the "Power" (or MBH) the total Input of the boilers and the total cooling Tons of the chillers? If not, what is included in this category?

Response: Yes, this includes cost of labor and material for distribution piping (HW and CW) ductwork for air distribution based on MBH.

Question No. 25: In the Supplemental Pricing Form, Construction Phase 3472-2, 30 HVAC – D3050 Terminal & Package Units is defined as "Power" per note 30. Does the cost include labor and material cost of the VAV reheat boxes and fan coil units? Is the "Power" (or MBH) the total heating capacity of the reheat coils and the total cooling Tons of the fan coil units? If not, what is included in this category?

Response: Yes, this includes cost of labor and material VAV reheat boxes and FCUs based on

MBH.

Question No. 26: In the Supplemental Pricing Form, Construction Phase 3472-2, 30 HVAC – D3060 Controls & Instrumentation is defined as "Power" per note 30. Is the "Power" (or MBH) the total Input of the boilers and the total cooling Tons of the chillers? If not, what is included in this category?

Response: Yes, this includes cost of labor and material for the controls and instrumentation required for the HVAC based on MBH.

Question No. 27: In the Supplemental Pricing Form, Construction Phase 3472-2, 30 HVAC – D3070 Systems Testing & Balancing is defined as "Power" per note 30. Is the "Power" (or MBH) the total Input of the boilers and the total cooling Tons of the chillers? If not, what is included in this category?

Response: Yes, this includes cost of labor and material for systems testing and balancing based on MBH.

Question No. 28: In the Supplemental Pricing Form, Construction Phase 3472-2, 30 HVAC – D3090 Other HVAC Systems and Equipment is defined as "Number of Special Mechanical Systems" per note 31. Please clarify which "special mechanical systems" are included in this category - does this include stairwell pressurization fans, parking garage ventilation fans, etc.?

Response: Include all items not included in the other D30 line items.

Question No. 29: Please verify all loose furniture, tables, chairs, desks, credenzas, etc. are considered FFE and are NOT to be included in the CMc Cost of Work.

Response: Yes. All loose furniture is not to be considered as part of the CMc Scope of Work.

Question No. 30: Please verify any residential appliances listed are to be included in the CMc Cost of Work.

Response: No residential appliances are included in the CMc Scope of Work.

Question No. 31: What is the anticipated height of the access flooring in the Courtrooms? Is underfloor air distribution desired where we have access flooring?

Response: POR section 3.2.7 has been updated with additional sentence. Anticipated height of the access flooring in the courtrooms is 6.5". There will not be underfloor air distribution.

Question No. 32: Program for Requirements section 3.5.3 states that lighting in occupied spaces shall have dimming capabilities. Please confirm which occupied spaces this applies to, as we assume the intent is not to have all lighting to be dimmable.

Response: Regularly occupied spaces shall have lighting with dimming capabilities.

Mechanical, electrical, telecom rooms, restrooms, closets, kitchens, secure areas and exteriors do not need lighting with dimming capabilities.

Question No. 33 : Program for Requirements section 3.5.3 indicates daylight photosensors shall be provided in locations with natural light available. Please confirm minimum room size.

Response: International Energy Conservation Code (IECC) 2012 will be the guide. There is not a room minimum size.

Question No. 34: Program for Requirements section 3.5.3 indicates lighting controls per space shall be tied into the BAS for remote control. Please confirm which spaces this applies to. For example, are all office required to be controlled by the BAS?

Response: All spaces at this time shall be designed to be through the BAS for remote control.

Control shall be per space, not per fixture.

Question No. 35: Program for Requirements section 3.5.5 indicates that UPS systems will be provided at the direction of GSA’s FAS. Please confirm if these will be GFGI rack mounted UPS’s, or if a centralized UPS is to be provided.

Response: Provide rack-mounted, modular system for the BAS and exterior security systems only.

Question No. 36: Program for Requirements section 3.5.6 indicates separate ATSs shall be provided for each tenant. Please confirm there is to be only (1) additional transfer switch per tenant, and what types of loads they will serve.

Response: ATS's shall be for Emergency Systems, Legally Required systems, and Optional systems. The optional systems shall be individual per tenant. Emergency and Legally required shall be building-wide.

Question No. 37: Program for Requirements section 3.6.1 indicates a loudspeaker system for courtrooms will be required. Please confirm this system is part of the $500k A/V package that is to be by others.

Response: Yes, the Courtroom loudspeaker system is included in the $500K A/V package.

Question No. 38: Please confirm if transfer switches are required to be open or closed transition between the generator source and the utility source.

Response: Refer to item 58.

Question No. 39: Program for Requirements section 3.5.1 uses the term "Main Switchgear".

Please confirm if the two 3,000A service entrance switchgear is in fact required to be switchgear (UL 1558) construction and not switchboard (UL 891) construction.

Response: Switchgear shall be the basis of design.

Question No. 40: Program for Requirements section 3.8.1 indicates that the backbone and infrastructure for the Audio/Visual systems will be by the CMc. Please confirm what is considered "backbone and infrastructure" that is to be carried by the CMc.

Response: Backbone and infrastructure has been updated to state pathways and rough-ins.

Question No. 41: Program for Requirements section 3.9.1 indicates that backbone and infrastructure for security systems is to be included and coordinated by the CMc. Please confirm what is considered "backbone and infrastructure" that should be provided by the CMc.

Response: Backbone and infrastructure has been updated to state pathways and rough-ins.

Question No. 42: The RFP makes no mention of an Interfacility Radio Enforcement System for first responder radios. Please confirm that this system is not to be included in the CMc scope.

Response: This will be included. POR has been updated.

Question No. 43: Please confirm if all low voltage system conduit stubs are required to extend all the way to the cable tray.

Response: Exposed locations shall require conduit to within 1" of cable tray. Above accessible ceilings conduit may be stubbed out of wall and wiring supported, but flown to cable tray.

Question No. 44: Program for Requirements section 3.5.1 indicates that courtrooms are to have a separate panel board. Please confirm what loads are intended to be on this panel board.

Response: All the loads in the courtroom and directly associated with the courtroom.

Question No. 45: Program for Requirements section 3.5.1 states that the electrical contractor is to provide all feeder lengths and equipment information for “a professional engineer” to perform an arc-flash analysis. Please confirm the contractor is not to include cost for the arc-flash analysis.

Response: The final coordination and analysis shall be completed by the electrical contractor's testing agency and a report must be submitted as a part of the commissioning process. Include this cost.

Question No. 46: Program for Requirements section 3.5.2 states that wall mounted clocks shall have outlets mounted for use. Please confirm where wall mounted clocks are intended to be used.

Response: Per U.S. Courts design guide, a clock power outlet should be located in the courtroom directly opposite the bench wall, above the entry doors.

Question No. 47: Program for Requirements section 3.5.5 states that a minimum 3/4" conduit shall be provided for low voltage/security system pathways. Please confirm pricing is to be based on the assumption that 3/4" pathways will be used.

Response: 3/4" conduit shall be the minimum. Larger raceway shall be required to maintain the 40% fill ratio and for A/V cabling connectors.

Question No. 48: Please confirm security system device locations will be limited to those locations specifically identified in the referenced standards. If any additional device locations are required, please provide a list of location types for each system.

Response: No other devices are required.

Question No. 49: Please confirm seismic restraints are not anticipated for electrical equipment/conduits.

Response: Confirmed.

Question No. 50: Program for Requirements section 3.5.1 states that SPDs are required to be provided on all panelboards to meet GSA requirements. Please confirm that the GSA requirement being referenced is the PBS-100 section 6.4, where SPDs are required to be provided based on the Performance Tier, meaning that not "all" panels would require an SPD.

Response: At this time, provide SPDs at switchgear, switchboards, distribution panels and all panels fed by the generator.

Question No. 51: Program for Requirements section 3.5.1 and PBS-100 state that an electrical room should not serve more than 10,000SF. With the intended building footprint to be 31,000 SF, please confirm the intent would be to allow (3) electrical rooms to serve 31,000 SF in-lieu of requiring a fourth electrical room for the additional 1,000SF.

Response: Provide (4) four electrical rooms

Question No. 52: Who has inspection jurisdiction for this building?

Response: Section 2.3 - The federal government (GSA) is the Authority Having Jurisdiction (AHJ) for this project.

Question No. 53: Are the ATS’s supposed to be open or closed transition?

Response: Open-transition in all areas, except Secure areas shall be closed-transition.** Maintenance bypass switches are required.

Question No. 54: What systems/items should be included on the list of things backed up by the generator?

Response: Emergency and legally required systems, secure areas, all lighting, owner selected items on optional system(s), sumps, elevators, sewage ejectors, data rooms, fire pump, fire detection and alarm, fire command center, stairwell pressurization, etc.

Question No. 55: PBS-100 section 6.5.2.1 paragraph titled “Communication System Pathways and Spaces Design Standards”, indicates that GSA’s FAS may have specific system requirements. Please confirm if there are any GSA FAS specific standards or requirements for communication systems or data drop densities.

Response: Additional pathway requirements are being updated in 3.5.5 to clarify this requirement.

Question No. 56: Can you please provide a copy of, or location of, the United States Marshal Services Publication 64? We have been unable to confirm which version is current nor find a location of the most current version

Response: Copy of current USMS Publication 64 is available to offerors by contacting Contracting Officer Michael Flanigan @ michael.flanigan@gsa.gov

Question No. 57: Ref. II.B. Contract Price Form: In section I.E (1) the estimated price range for the project is noted as “between $95,000,000 and $105,000,00.” Does the estimated range correspond to CLIN No. 6 Option for Construction Services or CLIN No.7 Total Contract Price in the Contract Price Form?

Response: The estimated price range corresponds to CLIN No. 6.

Question No. 58: Ref. III.G. Bond Requirements: Please confirm the required value of the bid guarantee that is to be submitted with our proposal. The value is to equal the Total Contract Price. Correct?

Response: The bid guarantee to be submitted with the proposal corresponds to CLIN No. 7 Total Contract Price.

Question No. 59: The Project Schedule requirement for the Technical Proposal response is limited to five pages, assumed to be letter-sized pages. With the amount of information required, we are finding it a challenge to legibly present the activities and logic for a four-year schedule within the five page limit. Please clarify your expectations for the format for presenting our Project Schedule information.

Response: Project Schedule Requirement for the technical proposal is limited to ten (10) 8.5"x 11"pages for the narrative and two (2) 11"x 17" pages for the schedule.

Question No. 60: Please provide additional scope information on the number and type of mock-ups required for the project for the construction option (exterior wall assemblies, terrazzo, etc.)

mailto:michael.flanigan@gsa.gov

Response: Physical mock-ups should include the following: exterior wall assemblies, terrazzo, courtroom casework (spectator bench, spectator railing, lectern, tables, bench witness stand), interior paneling, interior railing/guardrail, courtroom ceiling assembly, courtroom wall assembly, architectural exposed concrete, exterior paver, exterior site walls, exterior site stairs and exterior handrail/guardrail assemblies.

Question No. 61: Statement of Work - A/E Contract - Section 3.5.4.1 Courtroom Mock-up(s):

Please confirm the number of courtroom mock-ups required for the CMc Design Phase Services. The current assumption is a Special Proceedings Courtroom mock-up and a District/Bankruptcy Courtroom mock-up. Please confirm.

Response: Section 3.5.4.1 Courtroom Mock-up(s) from the Statement of Work in the A/E contract states that design mock-ups are required for each courtroom type. There should be a mock-up for the Special Proceedings Courtroom, one for a District Courtroom, one for a Magistrate Courtroom and one for a Bankruptcy Courtroom.

Question No. 62: POR 3.1.7 Foundation System: Are we correct in assuming all grade beams are intended to connect all pile caps in both directions?

Response: Yes.

Question No. 63: POR 3.1.7 Foundation System: The narrative states “Given the floor plate size above and assuming a 25’ x 25’ grid for planning purposes, a total of 50 columns are assumed (along with 50 pile caps).” Given this layout assumption and the 45,000 sf lower level size, a 25’ x 25’ grid gives a total of 91 interior and exterior wall columns. Please confirm.

Response: The POR will be updated to assume 91 interior and exterior columns and thus 91 pile caps for the lower level. Assume 50 columns for upper level floor plates.

Question No. 64: POR 3.2.2 Building Envelope: This section outlines an assumption of 40% glazing and 60% opaque cladding for the exterior envelope. The opaque material is then stated to be 40% brick/stone with the remaining 20% to be an aluminum metal panel system. Our assumption is the exterior envelope opaque material is to be 80% brick/stone blend with the remaining 20% aluminum panel. Please confirm.

Response: The building envelope will be 40% glazing, 40% brick/stone blend and 20% aluminum metal panel. The brick/stone blend will be comprised of 4/5's brick and 1/5 stone, or within the total amount of brick/stone blend the brick will comprise 80% and the stone will comprise 20%.

Question No. 65: POR 3.2.2 Envelope: The exterior wall system identifies “16-guage metal studs spaced ½” O.C.” Our assumption is 12” (1’-0”) on center. Please confirm.

Response: Confirmed - the referenced sentence should read "12-inches on center".

Question No. 66: POR 3.3.4 Site Preparation: Assumptions for imported fill material are provided. Please provide a cubic yard assumption for excavation or a baseline initial site grade relative to the 500-year flood plain so excavation for the lower level can be calculated.

Response: Assume 20,000 CY excavation for the lower level plus additional excavation for footings and foundations.

Question No. 67: PBS-P100 – 1.7.3 Sustainable Performance Requirements: Please confirm what Tier Level the project will be designed for (Baseline, Tier 1, 2, or 3) and whether the Tier Level is consistent for all P100 chapters. The POR 3.1.3 Structural Loads references Tier Level 2 for wind loading while section 3.2.3 Roofing and Waterproofing references Baseline Tier as a minimum.

Response: Unless stated otherwise in the Program of Requirements document or dictated by certifications requirements (LEED Gold), the intent is to meet baseline tier requirements of the P100 standards.

Question No. 68: Please provide a concrete slab-on-grade assumption for the lower level parking area and confirm whether underslab waterproofing will be required.

Response: The concrete slab in the lower level would consist of a 15 mil vapor barrier and a 5” slab with WWF6x6-4.0 x 4.0 reinforcing. We recommend waterstops at all cold joints below grade. Waterproofing and water stops would be required for all elevator pits.

Question No. 69: SF-1442 Supplemental Pricing Form: As mentioned in the Pre-Proposal Conference, this spreadsheet is locked and does not link between Tab 3472-1 and 3472-2.

Please provide a different Excel spreadsheet.

Response: An updated Supplemental Pricing Form is included with Amendment #5.

Question No. 70: SF-1442 Supplemental Pricing Form: For Design Phase Services, we assume the Bare (Base?) Rate for each discipline to align with P-120 in that this rate is “fully loaded” with the employee’s benefits, FICA, etc. and OH is home office overhead. Please confirm.

Response: Yes, this should include a fully loaded rate.