DMCH_CMc_Solicitation_Amend_3_Division_1_Specifications_180213.pdf

PDF 1 MB Posted

Attached to
New Des Moines Federal Courthouse CMc Solicitation
Solicitation number
6P1QW-17-1001
Issued by

About this file

DMCH CMc Solicitation Amend 3_Division 1 Specifications 180213

View the file

Other files

File Type Posted
NIA00003_DMCH_CMc_Award_Notification_180621.pdf PDF
DMCH_CMc_Solicitation_Amend_7_SF-30_180427.pdf PDF
DMCH_CMc_Solicitation_Amend_6_Courts_Design_Guide_2007_base.pdf PDF
DMCH_CMc_Solicitation_Amend_6_Courts_Design_Guide_2016_CH1_2_15_16.pdf PDF
DMCH_CMc_Solicitation_Amend_6_SF-1442_Supplement_Pricing_Form_180404.xlsx XLSX spreadsheet
DMCH_CMc_Solicitation_Amend_6_Courts__Design_Guide_2007_CH18.pdf PDF
DMCH_CMc_Solicitation_Amend_6_Pricing_Form.pdf PDF
DMCH_CMc_Solicitation_Amend_6_SF-30_180404.pdf PDF
DMCH_CMc_Solicitation_Amend_6_GSA_013100_Project_Management_&_Coordination.pdf PDF
DMCH_CMc_Amendment_6_Supplement_180404.pdf PDF
DMCH_CMc_Solicitation_Amend_5_Solicitation_Number_6P1QW-17-1001_Q&A.pdf PDF
DMCH_CMc_Solicitation_Amend_5_SF-30_180327.pdf PDF
DMCH_CMc_Solicitation_Amend_5_SF-1442_Supplement_Pricing_Form_180315.xlsx XLSX spreadsheet
DMCH_CMc_Solicitation_Amend_5_Division_1_Specifications_180327.pdf PDF
DMCH_CMc_Solicitation_Amend_5_Program_of_Requirements_180323.pdf PDF
DMCH_CMc_Solicitation_Amend_4_Pre_Proposal_Conf_Attendance_180228.pdf PDF
DMCH_CMc_Solicitation_Amend_4_SF-1442_Contract_Price_Form_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_4_SF-1442_180305.pdf PDF
DMCH_CMc_Solicitation_Amend_4_SF-30_180305.pdf PDF
DMCH_CMc_Solicitation_Amend_4_THE_SOLICITATION_(CMc201)_180305.pdf PDF
DMCH_CMc_Amendment_4_Supplement_180305.pdf PDF
DMCH_CMc_Solicitation_Amend_4_Pre_Proposal_Agenda_180228.pdf PDF
DMCH_CMc_Solicitation_Amend_4_CASB_Statement.pdf PDF
DMCH_CMc_Solicitation_Amend_3_SF-1442_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_SF-30_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Program_of_Requirements_180202.pdf PDF
DMCH_CMc_Solicitation_Amend_3_App_B_Small_Business_Utilization_Form_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_SF-1442_Supplement_Pricing_Form_180213.xlsx XLSX spreadsheet
DMCH_CMc_Solicitation_Amend_3_Statement_of_Work_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_THE_AGREEMENT_(CMc101)_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_SF24_Bid_Bond_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Wage_Determination_IA180142_dated_180119.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Offeror_Reps_and_Certs_(CMc301)_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_THE_SOLICITATION_(CMc201)_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_GSA_Form_527_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_3_Statement_of_Work_AE_CMa_Attachment_180213.pdf PDF
DMCH_CMc_Solicitation_Amend_2_Attachment_A_Updates_and_Q&A_171116.pdf PDF
DMCH_CMc_Solicitation_Amend_2_SF30_171116.pdf PDF
DMCH_CMc_Statement_of_Work_170906.pdf PDF
DMCH_CMc_Solicitation_Offeror_Reps_and_Certs_(CMc301)_170906.pdf PDF
DMCH_CMc_Solicitation_Appendix_A_Owner_Evaluation_Form_170906.pdf PDF
DMCH_CMc_Solicitation_GSA_Form_527_170906.pdf PDF
DMCH_CMc_Solicitation_Wage_Determination__IA170142_170825.pdf PDF
DMCH_CMc_THE_AGREEMENT_(CMc101)_170906.pdf PDF
DMCH_CMc_THE_SOLICITATION_(CMc201)_170906.pdf PDF
DMCH_CMc_Solicitation_Appendix_B_Small_Business_Utilization_Form_170906.pdf PDF
DMCH_CMc_Statement_of_Work_AE_CMa_Attachment_170906.pdf PDF
DMCH_CMc_Solicitation_SF1442_170906.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Des Moines Federal Courthouse Des Moines, IA PCN NIA00003

Summary 011000 - 1

SECTION 011000 – SUMMARY

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Name and Location:

Des Moines Federal Courthouse Address TBD Des Moines, IA

B. Project Summary Description:

The General Services Administration (GSA) intends to construct a new U.S. Courthouse in Des Moines Iowa. The planned project delivery method is Construction Manager as Constructor (CMc). The CMc contractor shall provide a new courthouse on a government-owned site in Des Moines Iowa and will be approximately 229,000 gross square feet, including 42 inside parking spaces, in Des Moines, Iowa. The United States District Court, United States Bankruptcy Court, United States Probation And Pretrial Services, United States Marshals Service and General Services Administration will occupy the facility. The space will include 5 District Courtrooms, 2 Magistrate Courtrooms and 2 Bankruptcy Courtrooms and their associated supporting spaces, such as judge's chambers, jury deliberation facilities, jury assembly, grand jury suites, holding cells, etc.

Office space will be provided for the other aforementioned tenants.

C. Architect: The term Architect refers to the project designer. The Architect's status relative to the construction will be stated in writing by the Contracting Officer prior to the pre-construction conference. The project will be designed by:

Lead Designer: Mack Scogin Merrill Elam Architects

Architect of Record (contract holder): Neumann Monson Architects

D. Project Delivery Method: Construction Manager as Constructor (CMc)

E. Other Key Consultants:

1. Mechanical/Electrical/Plumbing Designer: MODUS Engineering and Sustainable

Design

2. Structural: Raker Rhodes Engineering

F.

G. See Statement of Work (SOW) and GSA’s Partnering with the Public Building Service Policy dated March 5, 2014.

H.

I. The Contracting Officer for the project is: Michael Flanigan (Michael.flangigan@gsa.gov)

Summary 011000 - 2

1.2 WORK SEQUENCE

1. See Statement of Work (SOW). It is the intention of the Government and design team that design packages will be issued in sequence to allow for construction start prior to 100% design complete. The CMc will be instrumental in working with the project team in determining the scope and timing of these packages.

1.3 WORK BY OTHER CONTRACTORS

A. The Contractor shall cooperate with other contractors performing related work, including providing labor, materials and other costs necessary to satisfactorily coordinate the Contract work with work performed under other contracts.

1.4 SCHEDULE OF GOVERNMENT-FURNISHED PROPERTY

A. The project includes the following Government furnished property to be installed by the Contractor. The contractor shall advise GSA at least 30 days in advance of when the property should be delivered.

1. Government Furnished Property (GFP) may be identified as part of the design phase effort.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011000

Work Restrictions 011400 - 1

SECTION 011400 - WORK RESTRICTIONS

1.1 CONTRACTOR USE OF PREMISES

A. The Contractor shall develop a site plan prior to mobilization to layout project offices, service entrances, visitor entrances, laydown area, parking etc. This must be submitted and approved by the Contracting Officer.

B. The Contractor will review and document the existing conditions surrounding the project premises. Provide documentation to the Government prior to the commencement of any construction activity.

C. During the construction period, the Contractor shall have full use of the designated premises for construction operations, including full use of the indicated work site, limited only by the Government's right to perform work or retain other contractors to perform work on portions of the project.

1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.

2. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.

3. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. When not required for powering unloading operations, turn off engines when docked.

4. Smoking is not permitted in or around the building, see Facilities Management Regulation (FMR) Case 2008-102—3. Also see Code of Federal Regulations (CFR) 41 CFR Part 102-74.

5. Cell Phones: Contractor is to provide company cell phone during this contract. All cell phones to be “on vibrate” after beneficial occupancy of the building.

1.2 GOVERNMENT OCCUPANCY

A. The Government reserves the right to occupy, place, and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. Prior to partial Government occupancy, mechanical and electrical systems for the building shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.

2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.

PART 2 - PRODUCTS (Not Applicable)

Work Restrictions 011400 - 2

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011400

Allowances 012100 - 1

SECTION 012100 - ALLOWANCES

1.1 RELATED DOCUMENTS

A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract, including Federal Acquisition Regulations (FAR) and General Services Administration Acquisition Regulations (GSAR) contract clauses, and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements governing allowances.

1. Certain items are described in the Program of Requirements as allowance items. The purpose of allowance items is to defer selection of actual products and systems to a later date when direction will be provided to the Contractor. The Contracting Officer will issue Modifications to incorporate allowance items in the Work after actual products and systems have been determined.

B. Types of allowance items may include the following :

1. Lump-sum allowance items.

2. Unit-price allowance items.

3. Quantity allowance items.

1.3 SELECTION AND PURCHASE

A. At the earliest practical date after award of the Contract, advise the Contracting Officer of the date when final selection and purchase of each product or system described by an allowance item must be completed to avoid delaying the Work. Allowances must be included in all schedule submissions

1.4 ACTION SUBMITTALS

A. Submit proposals for products or systems described by allowance items in the form specified for Change Orders.

1.5 INFORMATIONAL SUBMITTALS

A. Submit copies of invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each unit-price and quantity allowance item.

B. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.

Allowances 012100 - 2

1.6 COORDINATION

A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.

B. Modifications based on an allowance item shall include cost to Contractor of specific products and systems selected by the contracting officer under allowance and shall include taxes, freight, delivery to Project site, Contractor's costs for receiving and handling at Project site, labor, installation, overhead, and profit.

1. If requested by the contracting officer, purchase additional quantities under unit-price or quantity allowances and prepare unused material for storage by Contracting officer.

Deliver unused material to Contracting officer's storage space as directed.

1.7 ADJUSTMENT OF ALLOWANCE ITEMS

A. Modifications to an allowance item shall comply with the changes clauses and any other contract modifications procedures found in the Contract Documents.

B. Contracting officer reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine products covered by an allowance item promptly on delivery for damage or defects.

Return damaged or defective products to manufacturer for replacement.

3.2 PREPARATION

A. Coordinate materials and their installation for each allowance item with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.

3.3 SCHEDULE OF ALLOWANCE ITEMS

A. Allowance Item No. 01: Lump Sum Allowance (not to exceed) for exterior structures such as landscaping walls, guard shacks, and vehicle barricades, shall be solid and integrated with its context and constructed of materials suitable to the overall building aesthetic. Carry an allowance of $750,000 for such items

END OF SECTION 012100

Options 012300 - 1

SECTION 012400 – OPTIONS

1.1 SUMMARY

A. “Option” means a unilateral right in a contract by which, for a specified time, the Government may elect to purchase additional scope of work, products, materials, equipment, systems or installation methods described in the Contract Documents.

B. The amount for an option is the total adjustment from the Base Bid to incorporate the option work into the project.

C. Option work shall include miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation, whether or not mentioned as part of the option description.

D. As part of the base bid Design Phase Services, the Contractor will have the responsibility, working with the project team, to ensure the design remains within the GMP stated as part of Option No. 1 listed below.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 SCHEDULE OF OPTIONS

A. Option No. 1: The Contractor is to provide a Guaranteed Maximum Price for the Construction Phase services described in the Program or Requirements document dated February 2, 2018. It is not anticipated that this option will be awarded in conjunction with the base bid proposal, but will be exercised as the design progresses and prior to Notice to Proceed of the construction work package(s).

END OF SECTION 012400

Substitution Procedures 012500-1

SECTION 012500 - SUBSTITUTION PROCEDURES

1.1 RELATED DOCUMENTS

A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Sections:

1. Division012100 Section "Allowances" for products selected under an allowance.

2. Division 012400 Section “Options” for products selected under an option.

3. Division016000 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

4. Divisions02 through 49 Sections (will be included as design progresses) for specific requirements and limitations for substitutions.

1.3 DEFINITIONS

A. Substitutions: Proposed changes to the Contract Documents by the Contractor for products, materials, equipment, and methods of construction.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner

1.4 SUBMITTALS for Cause or Convenience:

A. Substitution Requests: Per Submittal Procedures Section 013300 submit electronic copies through ePM of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: All pertinent information shall be included in the Contractor provided form.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Government and separate contractors that will be necessary to accommodate proposed substitution.

b. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable specification section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, energy and resource performance goals, warranties, and specific features and requirements indicated.

Indicate deviations, if any, from the Work specified.

c. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

d. Samples, where applicable or requested.

e. Certificates and qualification data, where applicable or requested.

f. List of similar installations for completed projects with project name, location and contact information of owner and architect/engineer of record.

g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

h. Research reports evidencing compliance with building code in effect for project, when applicable for the proposed substitution.

i. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. Provide a schedule fragnet with a time impact analysis to allow the Government to consider the proposed substitution.

j. Cost information, including a proposal of change, if any, in the Contract Sum.

k. Proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

l. The Contracting Officer may require the Contractor to provide a contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. The Contracting Officer or Contracting Officer’s Representative (CO) or (COR) Action: If necessary, the Contracting Officer or COR will request additional information or documentation for evaluation. The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion as may be indicated in the Project Schedule.

1.5 Failure by the government to respond does not constitute acceptance of the proposed substitution.

1.6 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

1.7 PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than 21 calendar days prior to time required for preparation and review of related submittals.

1. Conditions: The Contracting Officer (CO) will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, the Contracting Officer (CO) will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan. .

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: The Contracting Officer (CO) will consider requests for substitution if received within in the design phase prior to Notice to Proceed for respective construction packages. Requests received after that time may be considered or rejected at discretion of the Contracting Officer (CO) or the Contracting Officer Representative (COR).

1. Conditions: The Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied.

a. Requested substitution offers the Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional obligations the Government incurs..

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan.

e. Requested substitution has received necessary approvals of authorities having jurisdiction.

f. Requested substitution is compatible with other portions of the Work.

g. Requested substitution has been coordinated with other portions of the Work.

h. Requested substitution provides specified warranty.

i. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 3 EXECUTION (Not Used)

END OF SECTION 012500

Payment Procedures 012900 - 1

SECTION 012900 - PAYMENT PROCEDURES

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and to process Requests for Payment.

1.2 DEFINITIONS

A. Schedule of Values: A detailed written statement (masterformat/uniformat) furnished by the Contractor outlining the portions of the contract sum, which allocates values (price & percentage) for the various parts of the work and used as the basis for payment application and reviewing progress payments. The Agreement provides further details.

B. Request for Payment: A contractor’s invoice and request for progress payment with substantiating information consistent with approved schedule of values.

C. Open Book Accounting: Refer to CMc Delivery Method Clause.

1.3 SCHEDULE OF VALUES

1. Coordination: Submit completed Schedule of Values no later than [14] calendar days prior to anticipated Notice to Proceed. Refer to Specification Section 013110 Scheduling section for more information on cost loaded schedules.

2. Schedules for Phased Work: Where the work is separated into phases, provide Schedules showing values correlated with each phase using the standard format referenced below.

A. Format and Content: Contractor shall be responsible to complete the GSA Schedule of Values Workbook and compile the values into electronic Project Management (ePM) System. Contractor will enter values into workbook prior to ePM input and provide associated electronic baseline copy to contracting officer for record. Contractor will follow guidelines in the Schedule of Values workbook to support ePM upload.

1. Identification: Complete the following Project Identification fields in the Schedule of Values:

a. Project Name

b. Project Number

c. Project Location, City, State

d. Base Contract Number

e. Task Order Number

f. Modification Number

g. GSA Project Manager

h. Contractor's Name and contact information

i. Date of submittal

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Requests for Payment and progress reports.

a. Work activity – (by division or specific work activity)

b. Dollar value of each specific work activity – both with an amount in dollars and whole cents, and as a percentage of the Contract Sum to nearest one-hundredth percent.

Adjust the amounts to total to the Contract Sum and the percentages to total 100 percent.

Payment Procedures 012900 - 2

c. Each item in the schedule of values and Requests for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

(i.e. no stand alone item for Overhead, and Profit)

d. Modifications that affect value.

e. Update affected work branches and subordinate line items and

f. resubmit the schedule of values before the next Request for Payment when

Modifications result in a change in the Contract Sum

g. Line item for mobilization and de-mobilization

h. Line item for close out (% to be negotiated with GSA COR)

3. Options: Provide a separate Schedule of Values for each exercised Option.

4. Each item in the Schedule of Values and Requests for Payment shall be complete. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at the government's option.

5. Revise and update workbook in ePM with all items affecting scope, schedule or cost and resubmit within 14 calendar days as coordinated with project manager or contracting officer.

Contractor shall provide a final as-built schedule at project completion. Update affected work branches and subordinate line items and resubmit the schedule of values before the next Request for Payment when Modifications result in a change in the Contract Sum

1.4 REQUESTS FOR PAYMENT

A. Requirements for Requests for Payment are in Section III, Terms and Conditions of the Agreement.

B. Each Request for Payment following the initial Request for Payment shall be consistent with previous Requests.

1. Initial Request for Payment, Request for Payment at time of Substantial Completion, and final Request for Payment involve additional requirements.

C. Payment Request Times: Submit Request for Payment to GSA by the 20th of the month. The period covered by each Request for Payment is one month.

1. Submit one paper draft copy (aka pencil copy) of Request for Payment to the CO or enter in ePM along with construction progress report seven days prior to due date for review by GSA.

Provide documentation evidencing the cost of work performed to be included in the Request for Payment. Resolve questions resulting from GSA review of draft Request for Payment and construction progress report prior to submitting Request for Payment. For work done under the Guaranteed Maximum Price (GMP), open book accounting will be applicable. This must be account for in the request for payment and appropriate documentation shall be provided consistent with the CMc delivery clause.

D. Request Preparation: All payments must be executed by a person authorized to legally bind the Contractor.

1. Entries shall match data on the schedule of values and Contractor's construction schedule.

Use updated schedules if revisions were made.

2. Include amounts for work completed following effective date of previous Request for Payment, whether or not payment has been received. Include only amounts for work completed as of effective date of current Request for Payment.

3. Include amounts of Modifications issued before last day of construction period covered by Request.

E. Stored Materials: Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, and consent of surety to payment, for stored materials.

Payment Procedures 012900 - 3

2. Provide supporting documentation that verifies amount requested, such as paid invoices.

Match amount requested with amounts indicated on documentation.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of effective date of previous Request for Payment.

b. Value of previously stored materials put in place after effective date of previous Request for Payment and on or before effective date of current Request for Payment.

c. Value of materials stored since effective date of previous Request for Payment and remaining stored as of effective date of current Request for Payment.

F. Initial Request for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Request for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule per Agreement (startup if not final).

4. Products list (preliminary if not final).

5. Sustainable design submittal for project materials cost data.

6. Sustainable design action plans.

7. Schedule of unit prices.

8. Submittal schedule (preliminary if not final).

9. List of Contractor's staff assignments.

10. List of Contractor's principal consultants.

11. Copies of building permits.

12. Copies of authorizations and licenses from authorities having jurisdiction for performance of the

Work.

13. Initial progress report.

14. Report of preconstruction conference.

G. Request for Payment at Substantial Completion: After GSA issues the Notice of Substantial Completion, submit a Request for Payment less previous payments made for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This Request shall reflect Notices of Substantial Completion issued previously for GSA occupancy of designated portions of the Work.

H. Final Payment Request: The Agreement provides further details

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012900

__________________________________________________ ELECTRONIC PROJECT MANAGEMENT 013000 - 1

SECTION 013000 - ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM

1.1 PURPOSE

A. The Contractor shall use GSA’s web-based electronic Project Management (ePM) system, which is a fully configured version of Meridian Systems’ Proliance Construction Management Software. Click on this link for the ePM minimum requirements: https://insite.gsa.gov/portal/category/517870

1.2 DEFINITION

A. ePM is a web-based project management tool which provides GSA’s Public Buildings Service with an automated workflow, collaboration, document management and project management solution to help manage GSA design and construction projects. ePM is integrated with GSA’s gBUILD (Green Building Upgrade Information Lifecycle Database ) to share project creation and data storage information.

1.3 PROJECT COLLABORATION AND DOCUMENTATION

A. General

1. The Contractor shall effectively manage the ePM database including maintaining adequate staffing levels and ensuring that personnel attend the mandatory GSA-provided training sessions.

2. The Contractor shall use ePM to upload, store, capture, preserve, record, maintain, update, and route all project-related documentation to comply with GSA's Document Security Requirements. Classified material is not permitted to be stored in this system.

3. The Contractor shall use the workflow processes contained within ePM to submit and receive approval for all project deliverables.

4. The Contractor shall continuously monitor and review ePM to ensure the Contractor data is current through completion of the Close-out Phase of Construction.

5. The Contractor is required to store documents from their subcontractors and vendors in ePM. If a subcontractor or vendor does not obtain an ePM license, the contractor will be responsible for uploading and processing documents in ePM on their behalf.

B. Contents of ePM

1. The Contractor shall use ePM as the electronic filing cabinet for all project-related correspondence and submittals. The Contract Documents specify certain documentation that the Contractor shall provide during performance of the Contract. For the avoidance of doubt, and unless specifically stated otherwise in the Contract Documents, in addition to any documentation that the Contractor submits to GSA as set forth in the Contract https://insite.gsa.gov/portal/category/517870

__________________________________________________ ELECTRONIC PROJECT MANAGEMENT 013000 - 2

Documents. The current ePM Minimum Requirements can be found at: http://www.gsa.gov/epm.

1.4 SCHEDULING REQUIREMENTS

1. The Project Schedule shall be produced using widely used, commercially available computer software that is capable of generating and monitoring a CPM schedule and is compatible with Meridian Proliance.® See scheduling specification for additional information/requirements.

1.5 EQUIPMENT AND TRAINING

A. Equipment

1. GSA will not furnish any equipment related to accessing ePM. ePM is web-accessible, and can therefore be accessed via any computer with an Internet connection. For up to date ePM desktop requirements: http://www.gsa.gov/epm.

B. ePM Training

1. GSA will provide no cost training to familiarize team members with the ePM system. The

GSA Project Manager will ensure that appropriate personnel should attend training and what roles they will be set up within the system based on their project responsibilities.\

C. ePM Support

1. GSA will provide ePM system administration and end user support, for the duration of the project.

1.6 PERSONNEL REQUIREMENTS

A. An HSPD-12 security clearance is required to access ePM. Project Team members without an HSPD-12 clearance will need to work with the GSA Project Manager to initiate the clearance process, and request a temporary waiver for ePM access until clearance can be confirmed. A waiver means that once the individual’s HSPD-12 clearance is confirmed, an ePM username and password will be provided. For up to date GSA HSPD-12 information: www.gsa.gov/hspd12. Obtaining clearances vary in length and may take time to receive them.

1.7 DATA OWNERSHIP

A. GSA shall retain ownership of all data entered into the system and shall administer all information contained therein. And distribution of any system data shall be made upon request.

1.8 DOCUMENT SECURITY

A. ePM security access levels ensure that sensitive documents can only be accessed by the appropriate personnel. It is the contractor’s responsibility to ensure their employees, http://www.gsa.gov/epm http://www.gsa.gov/epm http://www.gsa.gov/hspd12

__________________________________________________ ELECTRONIC PROJECT MANAGEMENT 013000 - 3 subcontractors and vendors have the appropriate level of security to ensure document security.

1.9 REFERENCES

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013000

Project Management & Coordination 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

1.1 SUMMARY

A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:

1. General project coordination.

2. Coordination drawings.

3. Conservation.

4. Administrative and supervisory personnel.

5. Conferences and meetings.

6. Utility service interruptions.

7. Cleaning and protection.

See the project Statement of Work for Design and Construction Phase services for any additional requirements.

1.2 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space.

Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices. Assure all controls can be reached and operated.

1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.

2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.

3. Minimize roof penetrations.

B. Notification: Prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. Include notices, reports and meeting minutes as part of the memoranda.

C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work.

Administrative procedures include but are not limited to the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities.

3. Security packages and systems by others (i.e. U.S. Marshals Service (USMS), Federal

Protective Service (FPS), tenants, etc.)

4. Audio Visual (AV) and technology requirements and packages for tenants and/or end users.

5. Telecommunication, data, internet and other tele-work systems for GSA, tenants and/or end users.

Project Management & Coordination 013100 - 2

6. Delivery and processing of submittals.

7. Progress meetings.

8. Project closeout activities.

9. Startup and adjustment of systems.

D. Coordination with GSA’s Art-In-Architecture (AiA) Artist(s)

1. Attend meetings as required for coordination with the A/E team and artists.

2. Provide installation services (as required). If necessary, the A/E team will provide construction drawings to capture completely the required services.

1.3 COORDINATION DRAWINGS

E. Prepare coordination drawings and/or utilize the design BIM model and data where coordination is needed for installation of products and materials fabricated by separate entities, and prepare coordination drawings where limited space availability necessitates maximum use of the space for efficient installation of different components.

1. Show the relationship of components from the separate shop drawings. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems

2. Indicate required installation sequences.

3. Indicate minimum access space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

4. Show locations and sizes of all access doors on vertical and horizontal surfaces throughout the facility.

5. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.

6. Comply with shop drawing requirements for sheet size and submittal methods specified in

Division 1 Section "Submittal Procedures."

F. Refer to Divisions 23, and 26 Plumbing, Heating Ventilating and Air Conditioning, and Electrical for specific coordination drawing requirements for mechanical and electrical installations.

G. Provide coordination drawings for equipment and system installations in mechanical and electrical rooms and spaces where two or more entities will provide the work and separate shop drawings are insufficient to show coordination.

H. Work installed prior to approval of coordination drawings shall be at the Contractor’s risk.

Subsequent relocations required to avoid interferences shall be made without additional expense to the Government. In case interference develops, the Government will decide which work shall be relocated, regardless of which was installed first.

I. Digital Data Files of Coordination Drawings: Prepare coordination digital data files in accordance with the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as the original Drawings.

Project Management & Coordination 013100 - 3

2. File Submittal Format: Same digital data software program, version, and operating system as the original Drawings and Portable Document Format (PDF).

3. GSA will furnish Contractor one set of digital data files of the Drawings for use in preparing coordination digital data files.

a. GSA makes no representations as to the accuracy or completeness of digital data files as they relate to the Drawings.

b. Digital Data Software Program: Revit 2017

c. Execute a data licensing agreement in a form acceptable to the GSA, if required for

Project.

1.3 CONSERVATION

A. Coordinate conservation of energy, water and materials in the conduct of construction operation.

Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.

B. Comply with Green Purchasing Plan requirements.

C. Waste Management Plan: Establish a program to maximize recycling of waste materials.

Program shall include the following:

1. Designation of a waste management coordinator.

2. Identification of recyclable materials.

3. Identification of available local recycling firms and agencies to receive recyclable materials.

4. Establishment of quantity goals for collection of each recyclable material.

5. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.

6. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.

7. Implementation of the Waste Management Plan: Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the Contract.

a. Contractor shall lay out and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.

b. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant stakeholder of the project, including the Government.

1.4 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. The Contractor shall provide administrative and supervisory personnel for proper performance of the Work.

B. Project Coordinator: Provide a full-time project coordinator, experienced in the administration and supervision of building construction, including all systems required in the project. The project coordinator shall be authorized to act as the coordinator of construction activities, including but not limited to the following:

Project Management & Coordination 013100 - 4

1. Scheduling and sequencing of Work.

2. Sharing access to work spaces.

3. Installations.

4. Protection of work.

5. Cutting and patching.

6. Selections for compatibility.

7. Preparation of coordination of drawings.

8. Inspection and tests.

9. Temporary services and facilities.

C. Safety and Health Officer: Provide a safety and health officer whose duties shall consist of developing and implementing safety and health programs specified in Division 1 Section "Safety and Health."

D. Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.

E. Add additional staff and respective duties as necessary for your specific project

1. If needed, Mechanical Electrical Plumbing (MEP) Coordinator)

2. Commissioning Coordinator,

3. If needed, Systems/IT Coordinator Refer to Statement of Work for additional Design and Construction Phase services.

1.5 CONFERENCES AND MEETINGS

A. Preconstruction Conference: The government shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor. The conference shall review responsibilities and personnel assignments.

1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:

a. Government.

b. Architect.

c. Major design consultants.

d. Contractor.

e. Major subcontractors.

f. Major suppliers.

g. Other concerned parties.

2. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:

a. Tentative construction schedule.

b. Critical work sequencing.

c. Designation of responsible personnel.

d. Procedures for processing field decisions and Change Orders.

e. Procedures for processing Applications for Payment.

f. Distribution of Contract Documents.

g. Submittal of Shop Drawings, Product Data, and Samples.

h. Preparation of Record Documents.

i. Use of the premises.

j. Parking availability.

Project Management & Coordination 013100 - 5

k. Office, work, and storage areas.

l. Equipment deliveries and priorities.

m. Safety procedures.

n. First aid.

o. Security.

p. Housekeeping and progress cleaning.

q. Working hours.

r. Energy and resource efficiency / sustainability

s. Waste management

t. Systems Integration

u. Commissioning

B. Progress Meetings: The Government or designee (CMa) shall conduct progress meetings at the Project Site on a weekly basis. Dates of meetings shall be coordinated with preparation of the payment request.

1. Attendees: In addition to the Contractor's and Government's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.

a. Contractor's Construction Schedule: Review progress since the last progress meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. Provide 3 week schedule look ahead.

b. Review the present and future needs of each entity present, including but not limited to the following:

1) Interface requirements.

2) Time.

3) Sequences of operations.

4) Status of submittals.

5) Deliveries.

6) Off-site fabrication.

7) Access.

8) Site utilization.

9) Temporary facilities and controls.

10) Hours of work.

11) Hazards and risks.

12) Housekeeping and progress cleaning.

13) Quality and work standards.

14) Change Orders.

15) Documentation of information for payment requests.

16) Updating of Record Documents.

3. Schedule Updating: The Contractor shall revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or

Project Management & Coordination 013100 - 6 recognized. The revised schedule shall be issued concurrently with the report of each meeting.

C. Partnering Meetings: See GSA’s Partnering with the Public Building Service Policy PBS 3400.16A;

dated March 5, 2014.

Projects with an estimated construction cost (ECC) over $10 million are required to hold Partnering Meetings. To most effectively accomplish this contract, the Government requires that the Contractor and its Subcontractors participate in a cohesive partnership with the Government. Key personnel from the Government, Contractor, its Subcontractors, and the Designer of Record will participate in the Partnering process.

The Contractor shall provide the Contracting Officer with a list of the key personnel from the Contractor and its Subcontractors who will participate in the partnering sessions. The Contracting Officer may, in his/her sole discretion, add or remove any individual from the list. The Contracting Officer shall provide a list to the Contractor with the names of the individuals who will participate in the partnering sessions on behalf of the Government and its designer and on site construction manager. The Contractor shall issue the invitations to all of the individuals who will participate in the partnering sessions and generally serve as the host during any such session’s team. The Contractor shall provide the meeting room, and other incidental items for the partnering sessions over the life of the project. See the Statement of Work for frequency of Partnering meetings.

Before a Partnering session, the Contractor shall coordinate with the Facilitator all requirements for incidental items (i.e. audio-visual equipment, easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards, etc.) and have these items available at the Partnering session. The Contractor will copy documents for distribution to all attendees. The participants shall bear their own costs for meals, lodging and transportation associated with Partnering.

1. The Initial Partnering Session shall be a duration of one day minimum (8 hours plus an additional 30 minute lunch break). It shall be located at a place off the construction site as agreed to by the Contracting Officer and the Contractor. It may take place concurrently with the Pre Construction Meeting.

2. The Follow-on Partnering Session(s) generally lasts a half day or less. They will be scheduled at specific intervals--depending on the length of the project. Participants are encouraged to utilize electronic means to expedite meetings. Meetings may be held at the project site, or in a Government Facility. Follow-on meetings may be held concurrently with other scheduled meetings.

Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session is recommended to achieve best results and for continuity.

D. Project Closeout Conference: GSA will schedule and conduct a Project closeout conference, at a time convenient to Contractor, CM and Architect, but no later than 90 days prior to the scheduled date of Substantial Completion.

Attendees: Authorized representatives of GSA, CM, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

4. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of record documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Coordination of final commissioning requirements and submittal of written warranties.

Project Management & Coordination 013100 - 7

d. Requirements for completing sustainable design documentation.

e. Requirements for preparing operations and maintenance data.

f. Requirements for delivery of material samples, attic stock, and spare parts.

g. Requirements for demonstration and training.

h. Preparation of Contractor's punch list.

i. Procedures for processing Applications for Payment at Substantial Completion and for final payment.

j. Submittal procedures.

k. Coordination of separate contracts, if any.

l. GSA's partial occupancy requirements.

m. Installation of GSA's furniture, fixtures, and equipment.

n. Responsibility for removing temporary facilities and controls.

5. Minutes: Entity conducting meeting will record and distribute meeting minutes within 3 working days. Meeting Minutes should be uploaded or documented within ePM.

1.6 SUBMITTALS

A. Subcontract List: Thirty (30) calendar days in advance of the anticipated Notice to Proceed (NTP) prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

4. Coordination Drawings: Comply with the shop drawing requirements specified in Division 1

Section "Submittal Procedures".

B. Waste Management: Thirty (30) calendar days in advance of the anticipated Notice to Proceed, submit the waste management plan, followed by monthly implementation reports.

C. Staff Names: Sixty (60) calendar days in advance of the anticipated Notice to Proceed, submit a list of principal staff assignments, including the superintendent and other primary personnel at the Project site.