This is a Questions and Answers document for the CO NP BLCA 10(1) South Rim Drive Improvement federal contract opportunity, issued during the advertisement period between September 24 and October 1, 2026.
The document addresses nine clarification questions from prospective bidders regarding project requirements and specifications. Key clarifications include: out-of-state professional licenses and technical certifications are acceptable provided personnel meet credentialing and experience requirements in FP-24 Standard Specifications and project Special Contracting Requirements (SCRs); the Government will consider requests to extend the project completion date or allow weekend work; QL Pay statistical analysis does not apply to the crushed aggregate work, with acceptance based on pass/fail requirements per FP-24 Section 703.06; the grading designation for roadway aggregate is specified in FP Section 703.06, and CODOT or local municipality aggregate base is acceptable; roadway excavation and ditch reconditioning are subsidiary to the Terminal System, Type MGS Tangent pay item 61701-4500; the project completion date has been moved per Amendment A001; the horizontal coordinate system is CO83-SF, NAD83 Colorado State Plane, South Zone US Foot; and no geotechnical reports are available for the project. These responses provide important guidance to contractors regarding specification compliance, material sourcing flexibility, and project scheduling considerations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment A002.pdf | ||
| QnA 09.29.2026 South Rim .pdf | ||
| Amendment A001.pdf | ||
| QnA 09.24.2026 South Rim (3).pdf | ||
| Interested Vendors List - 9 23 2026.pdf | ||
| CO NP BLCA 10(1) South Rim Drive Plans.pdf | ||
| 6982AF26Q000022.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for
CO NP BLCA 10(1) SOUTH RIM DRIVE IMPROVEMENT
September 24, 2026
Questions Answers 1 Will the Government accept out of state professional services for this project? For example, can the RLS used for survey or the PE used for material testing be licensed in a state other than Colorado?
Yes, out-of-state professional licenses and technical certifications are generally acceptable, provided personnel meet the specific credentialing, experience, and submittal requirements set forth in the FP-24 Standard Specifications and project SCRs.
2 Would the Government consider increasing the project time by 2 weeks (fixed complete date of June 29, 2027) or allow work on weekends? The current time frame to complete the project will be extremely tight.
Yes, the Government would consider.
3 Due to the small quantity of crushed aggregate required for the project, please confirm that statistical analysis (QL Pay) will not be used on this project and acceptance will be based upon pass/fail of the requirements of FP-24 Section 703.
QL Pay does not apply. See 302.06 for acceptance.
4 Roadway aggregate, method 2 provides the compaction method (method 2) but no grading designation was provided. Please provide the grading designation required from FP-24 Section 703, Table 703-1. Due to the small quantity of aggregate base required for this project, would the Government consider allowing a CODOT or local municipality aggregate base? It is unlikely that local suppliers will want to adjust their screens to produce 125 TN of aggregate base.
Yes, see FP Section 703.06.
September 29, 2026
5 The project plans require roadway excavation and ditch reconditioning. These scopes do not have a pay item and are listed as for information only. Please provide the contract pay item that this work is incidental to or provide a pay item for these scopes.
Plan Note 9 on page D.10 indicate: “Roadway Excavation and Ditch Recondition are subsidiary to Terminal System, Type MGS Tangent Pay item.”
Pay item 61701-4500
6 Please clarify Q&A No. 5. The response states that Roadway Excavation and Ditch Reconditioning are subsidiary to the Terminal System, Type MGS Tangent pay item, but references Pay Item 61701-4500. Please confirm the correct pay item(s) to which Roadway Excavation and Ditch Reconditioning are subsidiary.
Yes the 61701-4500 pay item is the correct item.
7 Increase in project time/completion date move? The completion date has been moved, see Amendment A001.
October 01, 2026
8 What survey system are the listed horizontal coordinates based on?
The coordinate system’s name is CO83-SF, NAD, description NAD83 Colorado State Plane, South Zone US Foot.
9 Are there any geotechnical reports available from this or past projects? Much of the guardrail is going into locations that are solid rock and cliff faces. We would be looking for any geotechnical data available that details the rock hardness and soundness, particularly if any seismic testing has been collected for any past projects. Any geotechnical data that could be provided would be appreciated.
There are no Geotech reports.