TX QnA 10-28-25.pdf
PDF 102 KB Posted
- Attached to
- TX FLAP UV CR203(1) Fish Hatchery Road
- Solicitation number
- 6982AF25B000022
About this file
This document is a Questions and Answers (Q&A) file for the TX FLAP UV CR203(1) Fish Hatchery Road project, covering inquiries from October 21-28, 2025. The Q&A addresses multiple project-specific details, including clarifications on project requirements such as site access, water utilities, permits, project phasing, and administrative considerations. Key points include: no site visit is scheduled, the site is publicly accessible, the project requires compliance with the Buy American Act, and contractors must source their own water utilities.
Notable technical and administrative clarifications cover personnel requirements (referencing SCR Subsection 153.04 about Superintendent, SSHO, and QC Manager roles), project phasing flexibility, and electronic data availability. Specific references were provided for various project details, including tax considerations (FAR Clause 52.229-3), and electronic files are available in the "OneDrive_2025-08-01.zip" file posted on SAM.Gov. The document does not specify the exact nature of the construction work beyond being related to a Fish Hatchery Road project.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for TX FLAP UV CR203(1) Fish Hatchery Road
October 21, 2025
Questions Answers 1 Will there be a site visit? I don’t see any details on the solicitation documents, I just want to make sure.
There is no site visit scheduled. The site is open and accessible to the public.
October 22, 2025
2 I was looking through the plans, but I don't see a summary of quantity for the polyurethane foam. Can you tell me how much foam is estimated for this job? Also, how is the foam going to be used for this project? Stabilizing/void filling under concrete? Any information is greatly appreciated.
Polyurethane foam is not needed on this project and there is no stabilizing/void filling under concrete.
October 28, 2025
3 Are there any other permits required for this project. Refer to SCR Subsection 107.01.
4 Is there a specific project phasing we are required to follow or does the contractor have the flexibility to phase the project as needed?
No specific project phasing is required, refer to SCR Section 108 and 156 for limitations of operations.
5 Will the contractor have access to water utilities for construction at no cost or will the contractor be required to pay for water?
Contractor required to source water in accordance with FP-25 Section 105 and Subsection 725.01(c)
6 Will this project need to comply with the buy American act or similar requirements?
Yes, see page A-13 of the solicitation.
7 Will this project be tax exempt? See FAR Clause 52.229-3 Federal, State, and Local Taxes
8 Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
Refer to SCR Subsection 153.04.
9 Please clarify the item A0270- Blotter in bid schedule. Refer to FP-24 Section 411 and Subsection 703.12.
10 Is there a CAD file available for this project. Available electronic data is listed in SCR Subsection 152.04 and provided in the “OneDrive_2025-08-01.zip” file posted in SAM.Gov.