TX QnA 10-22-25.pdf

PDF 69 KB Posted

Attached to
TX FLAP UV CR203(1) Fish Hatchery Road
Solicitation number
6982AF25B000022
Issued by

About this file

The document is a Questions and Answers (Q&A) file for the TX FLAP UV CR203(1) Fish Hatchery Road project, dated October 21-22, 2025. Two questions were addressed during the advertisement period: the first inquired about a site visit, to which the response was that no site visit is scheduled but the site is open and accessible to the public. The second question sought details about polyurethane foam usage, and the response clarified that polyurethane foam is not needed for this project and will not be used for stabilizing or void filling under concrete.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for TX FLAP UV CR203(1) Fish Hatchery Road

October 21, 2025

Questions Answers 1 Will there be a site visit? I don’t see any details on the solicitation documents, I just want to make sure.

There is no site visit scheduled. The site is open and accessible to the public.

October 22, 2025

Questions Answers 2 I was looking through the plans, but I don't see a summary of quantity for the polyurethane foam. Can you tell me how much foam is estimated for this job? Also, how is the foam going to be used for this project? Stabilizing/void filling under concrete? Any information is greatly appreciated.

Polyurethane foam is not needed on this project and there is no stabilizing/void filling under concrete.