Amendment A001 AZ FS 289(1) AZ NFSR 289 Bridge Replacement.pdf
PDF 279 KB Posted
- Attached to
- AZ FS 289(1) AZ NFSR 289 BRIDGE REPLACEMENT
- Solicitation number
- 6982AF25B000019
About this file
This document is an Amendment (A001) to an Invitation for Bid (IFB) for the AZ NFSR 289 Bridge Replacement project issued by the Federal Highway Administration's Central Federal Lands Highway Division. The amendment provides specific instructions and modifications to the original solicitation, focusing on material handling, load restrictions, and project site usage for a bridge replacement project.
Key modifications include load restrictions for the existing Tonto Creek Bridge (20-ton limit), prohibitions on water source usage from Tonto Creek, Horton Creek, and USFS Campground facilities, and detailed guidelines for material staging and storage. Contractors are instructed to use previously disturbed areas for staging, install temporary plastic fencing, coordinate with the Contracting Officer (CO) for campground use, and follow specific environmental and material handling protocols. The amendment also outlines waste material disposal procedures, including using the USFS Sharp Creek Waste Site for excess excavation materials.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENUE, SUITE 360
LAKEWOOD, COLORADO 80228
ATTENTION:
9A. AMENDMENT OF SOLICITATION NUMBER
5. PROJECT NUMBER (If applicable)
9B. DATED (SEE ITEM 11)
IFB - Section E- Special Contract Requirement
1. Replace page E-4 and E-5 with the attached amended page E-4 and E-5.
10/20/2025
E-4
AZ FS 289(1)
AZ NFSR 289 Bridge Replacement
The CO will reject documents that are unreadable, corrupted, illegible, or include malicious content.
104.08 Load Restrictions. Delete the second sentence of the third paragraph.
104.08 Load Restrictions. Add the following:
The existing Tonto Creek Bridge has a load restriction of 20 tons. The existing Tonto Creek Bridge is signed for a 20 Ton load limit. A load rating performed by the USFS in 2013 indicates that the existing bridge is adequate for legal loads. Submit a written request 14 days in advance of hauling all oversized or overweight loads exceeding 20 Tons over the existing Tonto Creek Bridge to the CO for approval. The written request will include, at minimum, vehicle and equipment type and dimensions (length, width, etc.), number of axles and axle spacing, timing of hauling, maximum speed, vehicle gross and individual axle weight.
Section 105. — CONTROL OF MATERIAL
105.01 Source of Supply and Quality Requirements. Add the following:
Materials containing petroleum-based solvents such as cutback asphalts and traffic paints may be restricted from use by local laws or ordinances in certain geographic areas. Upon presenting proof of such restrictions, alternate materials considered acceptable to the CO may be substituted for the materials specified in the contract.
Certify, according to Subsection 107.10(d), that sources of rock, sand, gravel, earth, subsoil, or other natural material imported into the project construction limits are noxious weed free.
105.02 Material Sources
(a) Government-furnished sources. Add the following:
Do not use water from the Tonto Creek or Horton Creek.
Do not use water from the USFS Campground facilities.
(c) Contractor-located sources. Add the following:
There are several boulders within the project limits that may be used for boulder placement within the Horton Trailhead parking lot.
105.04 Handling and Storing Material. Add the following after the second paragraph:
For Contractor-located, non-commercial staging, storing, and material handling areas, secure environmental clearances according to Subsection 107.10.
Add the following:
Amendment A001 dated 11.4.2025
E-5
AZ FS 289(1)
AZ NFSR 289 Bridge Replacement
The Contractor may use the Horton Creek Trailhead Parking Lot, and the Upper Tonto Creek Campground for staging and storage of materials. Prior to utilizing the campground, coordinate use limits with the CO in consultation with the USFS. Install temporary plastic fence to protect vegetation and other features at both the Horton Creek Trailhead and the Upper Tonto Creek Campground, as well as other areas within the project limits.
The contractor may use the Derrick Trailhead parking lot, located ¼ mile south of the project site on Zane Grey Road, for vehicle washing inspection following environmental protection guidelines.
Provide four-week advance notice to the CO when use of these facilities is required.
Stage construction only in previously disturbed areas to avoid disturbance of sensitive resources such as areas of intact native plant communities, wetlands, and special-status species habitat. Upon completion of the work, restore the staging areas to the same or better condition from when the work was started.
Use products according to the manufacturer’s recommendations for handling, storage, and disposal. Follow the requirements of FAR Clause 52.236-10 Operations and Storage Areas and FAR Clause 52.236-12 Cleaning Up. Maintain the staging and storage areas in a clean, neat, and orderly condition.
Store construction, building and waste materials, and containers in designated areas indoors or protect with a suitable covering.
Keep the manufacturer’s SDS, an inventory of the material, and emergency numbers near the storage area. Take appropriate measures to ensure that incompatible chemicals are not stored next to each other.
Store construction materials within the limits shown in the plans. Properly store materials according to the applicable permit. Check the storage areas weekly and according to the applicable permit.
Submit a site map showing the material storage and stockpile locations at least 14 days before the start of construction activities.
105.05 Use of Material Found in the Work. Add the following:
Waste material is the property of the Contractor. Excess excavation materials, free from organic or other waste debris, may be disposed of at the USFS Sharp Creek Waste Site. The waste site is located 2.9 miles from the project site and 2.0 miles east of the NF 289 / SR 260 intersection on SR 260. Obtain approval from the CO for the type and quantity of material to be wasted and exact footprint proposed (location, height, and side slopes) that the wasted materials will occupy. Place materials to blend with the surrounding terrain and retain drainage patterns and general appearance of the site. Provide erosion control measures to stabilize the materials placed at this stie. Do not measure the erosion control measures at the waste site for measurement.
Amendment A001 dated 11.4.2025
| A001. Page E4.pdf |
| SPECIAL CONTRACT REQUIREMENTS |
| Section 102. — BID, AWARD, AND EXECUTION OF CONTRACT |
| Section 101. — TERMS, FORMAT, AND DEFINITIONS |
| Section 104. — CONTROL OF WORK |
| Section 105. — CONTROL OF MATERIAL |
| Section 106. — ACCEPTANCE OF WORK |
| Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC |
| Section 108. — PROSECUTION AND PROGRESS |
| Section 109. — MEASUREMENT AND PAYMENT |
| Section 152. — CONSTRUCTION SURVEY AND STAKING |
| Section 153. — CONTRACTOR QUALITY CONTROL |
| Section 154. — CONTRACTOR SAMPLING AND TESTING |
| Section 155. — SCHEDULES FOR CONSTRUCTION CONTRACTS |
| Section 156. — PUBLIC TRAFFIC |
| Section 157. — SOIL EROSION CONTROL, SEDIMENT CONTROL, AND STORMWATER POLLUTION PREVENTION PLAN |
| Section 201. — CLEARING AND GRUBBING |
| Section 203. — REMOVAL OF STRUCTURES AND OBSTRUCTIONS |
| Section 204. — EXCAVATION AND EMBANKMENT |
| Section 207. — EARTHWORK GEOSYNTHETICS |
| Section 302. — CRUSHED AGGREGATE |
| Section 403. — ASPHALT CONCRETE |
| Section 501. — MINOR CONCRETE PAVEMENT |
| Section 554. — REINFORCING STEEL |
| Section 563. — COATING |
| Section 564. — BEARING DEVICES |
| Section 565. — DRILLED SHAFTS |
| Section 601. — MINOR CONCRETE |
| Section 602. — CULVERTS AND DRAINS |
| Section 608. — PAVED WATERWAYS |
| Section 610. — SIDEWALKS, PADS, AND MEDIANS |
| Section 613. — SIMULATED STONE MASONRY SURFACE |
| Section 619. — FENCES, GATES, CATTLE GUARDS, AND BOLLARDS |
| Section 623. — GENERAL LABOR |
| Section 625. — TURF ESTABLISHMENT |
| Section 628. — TEMPORARY STREAM DIVERSIONS |
| Section 633. — PERMANENT TRAFFIC CONTROL |
| Section 634. — PERMANENT PAVEMENT MARKINGS |
| Section 635. — TEMPORARY TRAFFIC CONTROL |
| Section 637. — FACILITIES AND SERVICES |
| Section 646. — ROADSIDE DEVELOPMENT |
| Section 701. — CEMENTITIOUS MATERIAL |
| Section 702. — ASPHALT MATERIAL AND ADDITIVES |
| Section 703. — AGGREGATE |
| Section 704. — SOIL |
| Section 708. — PLASTIC PIPE |
| Section 713. — ROADSIDE IMPROVEMENT MATERIAL |
| Section 714. — GEOSYNTHETIC MATERIAL |
| Section 725. — MISCELLANEOUS MATERIAL |