This document is an Invitation for Bid (IFB) for the Romero Creek Bridge Replacement project located in the Gila National Forest, New Mexico. The solicitation is a total small business set-aside with a size standard of $45 million, issued by the U.S. Department of Transportation Federal Highway Administration Central Federal Lands Highway Division. The project involves replacing an existing bridge structure on Forest Route 220, with key work items including removal of existing structures, embankment construction, roadway aggregate, asphalt pavement, a 14' x 48' prefabricated steel bridge, structural concrete, and guardrail installation.
The bid is scheduled to be opened on September 16, 2025, at 2:00 p.m. local time, with an estimated project cost range between $700,000 and $2,000,000. The contract requires a 10% bid guarantee, performance and payment bonds, and completion by November 5, 2026. Bidders must be registered in the System for Award Management (SAM), submit original bid bonds with corporate seals, and comply with Buy American Act requirements. The project is anticipated to begin construction in Fall 2025, with no onsite work occurring from early March to early May due to weather constraints.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BidTabulationReport NM FS 220(1) Romero Creek Bridge LK.pdf | ||
| 6982AF25B000012 Bid Opening Summary.pdf | ||
| SAM.gov Interested Vendors 09.15.25.pdf | ||
| 20180829_220-7.5_Inspection_report.pdf | ||
| QnA _09.08.25.pdf | ||
| 20110101_220-7.325_BridgeGeometry.pdf | ||
| A001.pdf | ||
| Technical Memorandum Pavement Materials Recommendations - November 9 2025.pdf | ||
| FINAL Geotechnical Report March 2023.pdf | ||
| NM FS 220(1) Plan Update 7-3-2025.pdf | ||
| Final Hydraulics Report January 14 2021.pdf | ||
| NM FS 220 1 Borrow Pits.pdf | ||
| 11.12.4 Design Physical Data and Reports.zip | ZIP file |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BID
SOLICITATION NUMBER: 6982AF25B000012
SOLICITATION TYPE: TOTAL SMALL BUSINESS SET ASIDE
PROJECT NUMBER: NM FS 220(1)
PROJECT NAME: ROMERO CREEK BRIDGE
BID OPENING DATE:
See Page A-1, Item 13A
This solicitation cites Standard Specifications for Construction of Roads and Bridges on
Federal Highway Projects, FP-14 US Customary Units
ISSUING OFFICE:
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 W. DAKOTA AVENUE, SUITE 360
LAKEWOOD, CO 80228
Web site: https://highways.dot.gov/federal-lands E-mail: CFLContracts@dot.gov
PROJECT NM FS 220(1)
LOCATION GILA NATIONAL FOREST
COUNTY CATRON
STATE NEW MEXICO
LENGTH SCHEDULE A: 0.05 MILES
TYPE OF IMPROVEMENT BRIDGE REPLACEMENT
TABLE OF CONTENTS
Notice to Bidders ............................................................................................................. A-i
Solicitation, Offer, and Award ........................................................................................ A-1
Basis for Award and Bid Schedule ................................................................................ A-6
Solicitation Provisions .....................................................................................................B-7
Contract Clauses ..............................................................................................................C-1
Construction Wage Rate Requirement............................................................................ D-1
Division 100 ..................................................................................................................... E-2 Division 150 ................................................................................................................... E-18 Division 200 ................................................................................................................... E-28 Division 300 ................................................................................................................... E-30 Division 400 ................................................................................................................... E-31 Division 500 ................................................................................................................... E-34 Division 600 ................................................................................................................... E-41 Division 700 ................................................................................................................... E-52
APPENDICES
Appendix A .............................................................................................................Fire Plan
Appendix B ............................................................................................................. Permits
PROJECT OVERVIEW
This project is located in the Gila National Forest in western-central New Mexico. The terrain is rolling and mountainous with elevations ranging up to 8300 ft. The Romero Creek Bridge deck has large areas (approximately 60%) of delamination that are deep (2” to 10”). The most recent bridge inspection results indicate the structural evaluation of the bridge to be in poor to serious condition.
This project would replace this bridge with a similar structure, add bridge rail/guardrail and pave the approaches 100' on each side of the bridge to keep rocks/debris/soil off the deck and to prevent sediment from entering the stream.
SPECIAL CONTRACT REQUIREMENTS (SCRs)
The following Special Contract Requirements amend and supplement the Standard Specification for Construction of Roads and Bridges on Federal Highway Projects
NOTICE TO BIDDERS
A-i
I. PRE-BID INFORMATION
ELECTRONIC BIDS WILL NOT BE ACCEPTED. Submit a printed copy of your bid to the address listed on the SF-1442 (Page A-1, Item 8). Submit the following documents with your Bid Package–
• SF-1442, Solicitation, Offer & Award, Pages A-1 and A-2
• Indication of interest in formal Partnering, Page A-5
• Bid Schedule Pages A-6 through A-8
• Completed an applicable Authority to Bind certificate, pages A-9 through A-13
• Buy American Act & Hazardous Materials, Pages A-14 through A-15
• Bid Guarantee (see FAR Clause 52.228-1), Pages B-1 and B-2. Bid bonds must be originals with original signatures and corporate seals. Photocopies and Faxed copies are NOT acceptable and will make your bid non-responsive.
o Digital copies may be downloaded at https://www.gsa.gov/forms-library/bid-bond
• Completed the VETS-4212 declaration, Page A-ii; Bidders’ Information, Pages B-3 through B-6.
Bidders should retain all other pages for their information. Bids should be submitted in a sealed envelope and include the Contractor’s Name, Solicitation Number and the Project Number/Name.
It is the responsibility of the bidder to verify that this solicitation document, including the plans, are complete as listed in the table of contents and the index to sheets. Plan sheets can be found at https://sam.gov and viewed by individual sections, downloaded by individual sections, or the entire plan set downloaded in a zip file. Physical data relevant to this solicitation may also be viewed or downloaded at the above site.
This solicitation and subsequent contract are governed by the Federal Acquisition Regulations (FAR), agency supplemental regulations, and the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14.
The FP-14 was utilized for the design of this project. Paper copies of the FP-14 will not be provided to bidders or the awarded Prime Contractor. The FP-14 is available electronically at https://flh.fhwa.dot.gov/resources/specs/ and a copy is uploaded with this solicitation.
Applicable FAR/TAR provisions and clauses in this IFB are incorporated by reference or full text.
FAR provisions and clauses incorporated by reference can be accessed on the Internet at https://www.acquisition.gov/content/regulations.
https://www.gsa.gov/forms-library/bid-bond https://sam.gov/ https://flh.fhwa.dot.gov/resources/specs/ https://www.acquisition.gov/content/regulations
A-ii
Notice of SAM Registration – you must be registered in the System for Award Management (SAM) prior to submission of a bid in response to this solicitation. Failure to register prior to submission of a bid may require award to the next successful registered offeror. See FAR Subpart
4.1102. Register online at www.sam.gov.
“System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in DOT solicitations.
Examples include:
• 52.222-25, Affirmative Action Compliance, and
• 52.212-3(d), Offeror Representations and Certifications—Commercial Products and Commercial Services.
• 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals— Representation, and Page 3 of 28
• 52.212-3(t), Offeror Representations and Certifications—Commercial Products and Commercial Services.
Contracting officers will not need to consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.”
Representations and Certifications – This solicitation is issued under NAICS 237310 – Highway, Street & Bridge Construction with a small business size standard of $45 million. If your average annual gross receipts for the past 5 years are above $45 million, you are a large business for this solicitation. If they are below $45 million you are a small business. Before submitting bids, you must ensure you have completed your annual representations and certifications electronically at the SAM website at www.sam.gov. Include NAICS 237310 in your SAM profile.
Vets-4212 Reporting: - The Contractor must complete the report if required. See reporting requirements at: https://www.dol.gov/agencies/vets/programs/vets4212
• My firm had a qualifying Federal Contract in 2024 and has complied with the reporting requirements.
• My firm did not have a qualifying Federal Contract in 2024 and is therefore exempt from the reporting requirements.
http://www.sam.gov/ http://www.sam.gov/ https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.dol.gov%2Fagencies%2Fvets%2Fprograms%2Fvets4212&data=05%7C01%7Cryan.d.phillips%40dot.gov%7C09d955a274d74e8474dc08dbc51eeb3d%7Cc4cd245b44f04395a1aa3848d258f78b%7C0%7C0%7C638320508951679944%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=gIALto4XEaeYAJrJxNNxKww0nAj0lFMpA2G36Z3hVxc%3D&reserved=0
A-iii
Bid Guarantee – Follow the requirements of FAR Clause 52.228-1 Bid Guarantee and Subpart
102.03 of the FP-14. Bid bonds must be originals and have original signatures and corporate seals.
Photocopied and faxed copies of bonds will be rejected and cause your bid to be non-responsive.
Accuracy and Completeness of Bid- The Contractor is fully responsible to verify that all data is correct when an offer is submitted. Failure to properly update your data may cause the offer to be rejected.
Request for Technical Information – Questions relative to the plans and SCRs for this solicitation will only be accepted in writing (see Item 9 on Page A-3).
TECHNICAL QUESTIONS REGARDING THIS SOLICITATION WILL NOT BE
ACCEPTED AFTER 4 P.M. ON September 8, 2025
Consolidate all questions on a single word document and submit NLT the deadline to submit technical questions.
Questions can be submitted to CFLContracts@dot.gov. Questions and answers will be posted at https://sam.gov
Modifications to Bids - Bids may be modified or withdrawn by regular mail, electronic commerce (email), if such notice is received prior to the time specified for receipt of bids. The Government will not be responsible for ANY failure attributable to the transmission or receipt of electronic commerce (email).
For all modifications, we STRONGLY ENCOURAGE you to resubmit the entire bid schedule with a unit price and amount for every bid item, and a Schedule Total. See FAR Provision 52.214-5, Submission of Bids. Modifications which make the bid ambiguous, indefinite, or uncertain as to any essential requirement of the contract will cause the bid to be rejected as nonresponsive.
Email Address to submit modifications to bids for this project is cflcontracts@dot.gov
FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts.
It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.
Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.
There are no agency-specific additional policies and procedures that exist at this time.
The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).
mailto:CFLContracts@dot.gov https://sam.gov/ https://www.acquisition.gov/far/part-52#FAR_52_243_4 https://www.acquisition.gov/far/part-52#FAR_52_243_4
A-iv
Time to definitize after receipt of an adequate change order definitization proposal under construction contracts
Number of change order proposals definitized under construction contracts
FY 2022 FY 2023 FY 2024
0 to 30 days 0 0 0 31 to 60 days 1 0 1 61 to 90 days 0 0 0 91 to 180 days 2 1 4 181 to 365 days 0 1 2 366 or more days 2 0 0 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance
0 0 0
II. POST AWARD INFORMATION
CFLHD will no longer be providing paper copies of the conformed contract to the Awarded Prime Contractor.
Subcontracting - FAR Clause 52.219-8, Utilization of Small Business Concerns states that Prime Contractors afford small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns the maximum practicable opportunity to participate in performing contracts let by any Federal agency.
Insurance requirements - See Subsection 107.05 of the FP-14.
Masterworks - Contractors shall use the Government’s web-based system Masterworks to prepare all “Inspector’s Daily Record of Construction Operations” (Contractors Daily Reports) and measurement notes (pay notes).
The Contractor shall be required to attend a training session on the use of Masterworks. The virtual training sessions will be either a video presentation or live training as determined by the CO. The Contractor shall be responsible for training additional staff.
The Contractor shall be required to submit a user account form to gain access to the Masterworks. See Subsection 104.04.
New Mexico Gross Receipts and Compensating Tax Act – Contractors are responsible to understand the tax laws associated with the New Mexico gross receipts tax, pursuant to the Gross Receipts and Compensating Tax Act of New Mexico.
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration or Repair)
1. SOLICITATION NO.
6982AF25B000012
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
08/15/2025
PAGE OF
PAGES
IMPORTANT - THE "OFFER SECTION ON THE REVERSE MUST BE FULLY COMPLETED BY OFFEROR.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
HFLCEO250287PR
6. PROJECT NO.
NM FS 220(1)
7. ISSUED BY:
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS DIVISION
12300 WEST DAKOTA AVENUE, SUITE 167
LAKEWOOD, COLORADO 80228
CODE: 69050001 8. ADDRESS OFFER TO:
Laura Slauter, Contract Specialist Federal Highway Administration Central Federal Lands Division Office 12300 W. Dakota Avenue Lakewood, CO 80228
9. FOR INFORMATION CALL
SEE PAGE A-3
A. NAME:
SEE PAGE A-3
B. TELEPHONE NO. (Include area code)
SEE PAGE A-3
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS:
ROADWAY CONSTRUCTION PROJECT IN STRICT ACCORDANCE WITH:
1. FEDERAL ACQUISITION AND TRANSPORATION ACQUISITION REGULATIONS (FAR & TAR)
2. DEPARTMENT OF LABOR, CONSTRUCTION WAGE RATE REQUIREMENT RATES
3. SPECIAL CONTRACT REQUIREMENTS
4. PLANS
5. BID SCHEDULE
6. STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY
PROJECTS, FP-14, U.S. CUSTOMARY UNITS
See Subsection 104.04 of the FP-14 for governing order of precedence
11. The Contractor shall begin performance within 10 calendar days and complete it within * calendar days after receiving award notice to proceed. The performance period is mandatory negotiable. *Refer to Subsection 108.01 as amended in the Special Contract Requirements.
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.) YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8. by 2:00 p.m. (hour) local time on 9/16/25 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is is not required.
C. All offers are subject to the (1) work requirements and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA
FAR (48 CFR) 53.236-1(d)
X
X
X
X
X
A-1
STANDARD FORM 1442 (REV. 12/2022) BACK
OFFEROR (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
UEI.
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing with calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS
SEE INDIVIDUAL BID SCHEDULE(S)
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED
TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 27
(4 copies unless otherwise specified)
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
□ 10 U.S.C. 2304(c)( ) □ 41 U.S.C. 3304(a)( )
26. ADMINISTERED BY CODE:
27. PAYMENT WILL BE MADE BY
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 W. DAKOTA AVENUE, SUITE 167
LAKEWOOD, COLORADO 80228
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.)
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by
(a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON
AUTHORIZED TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE 31B. UNITED STATES OF AMERICA
BY
31C. AWARD
DATE
A-2
Item 8: LOCATION OF PUBLIC BID OPENING: Offers must be received by designated date and time as stated in Item 13A.
Item 9: FOR GENERAL INFORMATION: E-mail us at CFLContracts@dot.gov.
FOR TECHNICAL INFORMATION (plans and specifications): Questions must be submitted in writing by e-mail at CFLContracts@dot.gov .
Item 11: COMPLETION DATE: The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than November 5, 2026 subject to such extensions as may be authorized. The time stated for completion shall include final cleanup of the premises.
Work shall be completed on or before the date specified above, subject to such extensions as may be authorized by the terms of the contract and the specifications made a part thereof.
Item 12A: PERFORMANCE AND PAYMENT BONDS: See FAR Clause 52.228-15 Performance and Payment Bonds-Construction (Clauses begin on Page C-1) and Subsection 102.06 of the FP-14.
Item 13B: BID BOND AMOUNT: See FAR Provision 52.228-1 Bid Guarantee (Provisions begin on Page B-1) and Subsection 102.03 Bid Guarantee of the FP-
14. All bid guarantees must have original signatures with original corporate seals.
Item 19: ACKNOWLEDGMENT OF AMENDMENTS: FAILURE TO
ACKNOWLEDGE AMENDMENTS, IN ITEM 19 OF THE SF-1442, BY THE
DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY
RESULT IN REJECTION OF YOUR BID. If amendments are issued, they will be posted to https://sam.gov.
Item 24: SUBMITTING INVOICES: See Subsection 109.08 Progress Payments of the
FP-14.
ESTIMATED PRICE: The price range of the project work is between $700,000 and $2,000,000.
A-3 mailto:CFLContracts@dot.gov mailto:CFLContracts@dot.gov https://sam.gov/
Bid Schedule Instructions
BIDDERS, PLEASE NOTE: This Bid Proposal is comprised of one schedule. Before preparing the bid, carefully read the Solicitation Provisions and the following:
• Insert a numeric unit bid price for each pay item for which a quantity appears in the bid schedule. Unit bid prices should be quoted no more precisely than the nearest cent (2 decimal places). Unit bid prices quoted more precisely will be rounded up to the nearest cent by the Government
• Multiply the unit price by the quantity for each pay item and show the amount bid.
When the words “Lump Sum” appear as a unit bid price, insert an amount for each lump sum pay item.
• Total all amounts bid for each pay item and show the Construction Cost Total on the space provided on the last page of each schedule or option.
• Also show the Construction Cost Total for each schedule/option as well as the combined Total of each Schedule and the Option in the spaces provided on the Bid Summary page.
NOTE: If the amount bid for a pay item is inconsistent with the product of the unit price provided by the bidder and the quantity provided by the Government, the unit price will govern and the Government will determine a corrected amount bid for the pay item by multiplying the unit price by the quantity.
Basis for Award
To be eligible for award of contract, the offeror shall submit prices for each item necessary to complete all contract work in Schedule A.
Accordingly, award of contract, if made, will be made to the lowest responsive, responsible bidder, if funds are available.
A-4
Partnering
A Partnership recognizes the Government and the Contractor are both responsible and can affect the successful completion of this project. Partnering is a vehicle to ensure the partnership has structure and quality. It recognizes the strengths of each party and uses those strengths to identify and achieve shared goals. One of the primary objectives of Partnering is to facilitate the resolution of disputes in a timely, professional, and non-adversarial manner with the outcome focused on achieving those shared goals.
CFLHD supports the concepts and tenets of Partnering and as such is encouraging the Contractors and it’s subcontractors to establish a Partnering relationship on this project.
A formal Partnering meeting can help facilitate this relationship by helping do document the parties’ common purpose and goals, and ensuring alignment. The goals are mutually agreed upon and address effective and efficient performance within the scope of the contract.
Participation in a formal Partnering meeting is voluntary. Costs of implementing and maintaining the partnership would be agreed to by both parties as described in Subsection 103.05 Partnering of the FP-14. Costs of partnering would be in addition to the contract award amount.
Please indicate your desire to participate in a formal partnering meeting on this project.
(___) We would like to participate in a formal partnering meeting.
(___) We do not want to participate in a formal partnering meeting.
A-5
Bidder/Offeror please note: Before preparing the bid, carefully read the Solicitation Provisions. Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the corrected unit price extension shall govern. When the word "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item. When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount. Total all of the amounts bid for each pay item and show the total bid amount.
A-6
Project No : NM FS 220(1) Schedule : Schedule Type : Base
Project
Line Item Number
Pay Item Number Description
Quantity Unit Price
A0020 15101-0000 MOBILIZATION ALL
A0040 15214-1000 SURVEY AND STAKING, BRIDGE ALL
A0060 15225-0000 SLOPE, REFERENCE, AND CLEARING AND
GRUBBING CONTROL 0.041
A0080 15236-2000 SURVEY CONTROL, GRADE FINISHING 0.082
A0100 15301-0000 CONTRACTOR QUALITY CONTROL ALL
A0120 15401-0000 CONTRACTOR TESTING ALL
A0140 15501-0000 CONSTRUCTION SCHEDULE ALL
A0160 15701-0000 SOIL EROSION CONTROL ALL
A0180 20101-0000 CLEARING AND GRUBBING 0.320
A0200 20304-2000 REMOVAL OF BRIDGE ALL
A0220 20420-0000 EMBANKMENT CONSTRUCTION 320.000
A0240 20801-0000 STRUCTURE EXCAVATION 210.000
A0260 20803-0000 STRUCTURAL BACKFILL 70.000
A0280 30202-2000 ROADWAY AGGREGATE, METHOD 2 220.000
A0300 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 82.000
A0320 41201-0000 TACK COAT 0.320
A0340 55201-0100 STRUCTURAL CONCRETE, CLASS A 46.000
A0360 55401-1000 REINFORCING STEEL 4,900.000
A0380 55504-0000 PRE-FABRICATED STEEL BRIDGE (14' x 48' modular steel vehicular bridge) ALL
A0400 60101-0000 CONCRETE 10.000
A0420 61701-4550 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A
WOOD POSTS 50.000
A0440 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT 4.000
A0460 61707-0000 STRUCTURE TRANSITION RAILING 50.000
Unit
LPSM
A
Amount
ROMERO CREEK BRIDGE
LPSM
MILE
MILE
LPSM
LPSM
LPSM
LPSM
ACRE
LPSM
CUYD
CUYD
CUYD
TON
TON
TON
CUYD
LB
LPSM
CUYD
LNFT
EACH
LNFT
A-7
A0480 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY 20.000
A0500 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM
RATED CAPACITY BUCKET, 24-INCH WIDTH 20.000
A0520 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED
CAPACITY 20.000
A0540 62201-2750 MOTOR GRADER 20.000
A0560 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD
MINIMUM CAPACITY 20.000
A0580 62301-0000 GENERAL LABOR 20.000
A0600 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES 20.000
A0620 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH 0.300
A0640 62510-1000 SEEDING, DRY METHOD 0.300
A0660 62515-1000 MULCHING, DRY METHOD 0.300
A0680 63316-1000 REMOVE AND RESET SIGN 2.000
A0700 63501-0000 TEMPORARY TRAFFIC CONTROL ALL
A0720 63701-0000 FIELD OFFICE 1.000
Schedule
Schedule A - Base
HOUR
HOUR
HOUR
HOUR
HOUR
HOUR
HOUR
ACRE
Bid Total
Schedule Total:
ACRE
ACRE
EACH
LPSM
EACH
Submitted by:
A-8
INSTRUCTIONS: When the offeror/principal is a corporation, include this certification with your offer/bid.
Corporate Certificate
I, (name), certify that I am the
(title), of the corporation named as the
Offeror/Principal herein;
that (name), who signed this offer and/or bid bond on behalf of (company name) is
(title) of this corporation;
that the offer was duly signed for and on behalf of said corporation by authority and scope of its governing body, and within the scope of its corporate powers.
(signature) Affix Corporate Seal
(title)
A-9
INSTRUCTIONS: When the offeror/principal is a limited liability corporation, include this certification with your offer/bid.
Limited Liability Certificate
I, (name), certify that I am the
(title), of the limited liability company named as the Offeror/Principal herein;
that (name), who signed this offer and/or bid bond on behalf of (company name) is
(title) of this company;
that the offer was duly signed for and on behalf of said company by authority and scope of its governing body, and within the scope of its powers.
(signature) Affix Company Seal
(as applicable) (title)
A-10
INSTRUCTIONS: When the offeror/principal is a partnership, include this certification with your offer/bid.
Authority to Bind Partnership
This certifies that the names and signatures of all partners are listed below, and that the person signing the proposal has the authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting
Officer.
(Include names and signatures of all partners)
A-11
INSTRUCTIONS: When the offeror/principal is a joint venture, include this certification with your offer/bid.
Authority to Bind Joint Venture
This certifies that the person signing the proposal has the authority to actually bind the joint venture pursuant to its joint venture agreement, and that each of the named persons listed below individually has full authority to enter into and execute contractual instruments on behalf of said joint venture, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting
Officer.
(Include names and signatures of all applicable individuals)
A-12
INSTRUCTIONS: When the offeror/principal is a sole proprietorship, include this certification with your offer/bid.
Sole Proprietorship Requirement
An Offeror/Principal that is a sole proprietorship must submit an offer/bid and a bond signed by the sole proprietor, or by one duly authorized to sign for the sole proprietor. If the signature is by someone other than the sole proprietor, a copy of the power of attorney authorizing the individual to sign must be provided with the offer/bid.
A-13
BUY AMERICAN ACT- CONSTRUCTION MATERIALS
It is understood and agreed that the materials and components listed in Subparts 25.1 and 25.2 of the FAR are a part of this contract and are deemed to be Domestic Construction Material for the purposes of this contract.
NOTE TO CONTRACTOR:
The following information and any applicable supporting data is required for evaluation of requests under FAR Clause 52.225-9 Paragraph (c) & (d) and FAR Provision 52.225-10 Paragraph (b).
Material and/or Component
Construction Material Description
Unit of Measure
Quantity
*Cost Delivered to Job Site
Foreign Construction Material
Comparable Domestic Material
Material and/or Component
Construction Material Description
Unit of Measure
Quantity
*Cost Delivered to Job Site
Foreign Construction Material
Comparable Domestic Material
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).] [Please include name, address, telephone number and contact for suppliers surveyed. Attach copy of response; if oral, attach summary. Include all applicable supporting information.]
A-14
HAZARDOUS MATERIALS
As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data - Alternate I, the apparent low bidder must submit prior to award a Material Safety Data Sheet (MSDS) for all hazardous materials that the bidder identifies in paragraph (b) of the FAR clause and defined under the latest version of Federal Standard No. 313.
Hazardous Material
Identification Number
BIOBASED PRODUCTS AND SUSTAINABLE PRODUCTS AND SERVICES
See FAR Provision 52.223-1 Biobased Product Certification and 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts for usage, certification, and reporting requirements.
USE OF RECOVERED MATERIALS ON FEDERAL LANDS HIGHWAY PROJECTS
Section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act (RCRA) of 1976, as amended (42 U.S.C. 6901 et seq.), requires Federal, State, and local procuring agencies using appropriated Federal funds to purchase items composed of the highest percentage of recovered materials practical. Use of recovered materials is strongly encouraged on Federal Lands Highway Projects. Highway construction items covered by the Environmental Protection Agency’s Comprehensive Guidelines for Procurement of Products Containing Recovered Materials include fly ash, ground granulated blast furnace slag, traffic barricades, traffic cones, hydraulic mulch and compost for mulch.
Use of fly ash and ground granulated blast furnace slag and construction materials containing fly ash and ground granulated blast furnace slag on Federal Lands Highway Projects:
It is the policy of the United States Government that fly ash and ground granulated blast furnace slag and materials containing fly ash and ground granulated blast furnace slag shall have maximum practicable opportunity for incorporation into its construction projects.
The Contractor agrees to investigate the use of fly ash and ground granulated blast furnace slag and materials containing fly ash and ground granulated blast furnace slag to the fullest extent consistent with the efficient performance of this contract. Both the contractor and the subcontractors are urged to seek out suppliers of fly ash and ground granulated blast furnace slag, cement and concrete containing fly ash and ground granulated blast furnace slag and to solicit bids for these materials.
Names of firms that supply fly ash and ground granulated blast furnace slag and materials containing fly ash and ground granulated blast furnace slag are available from the American Coal Ash Association and the National Slag Association.
A-15
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 24 (REV. 10/2023)
Previous edition is NOT usable Prescribed by GSA - FAR (48 CFR) 53.228(a)
BID BOND
(See instructions on reverse)
DATE BOND EXECUTED (Must not be later than bid opening date) OMB Control Number: 9000-0001
Expiration Date: 1/31/2027
Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0045. We estimate that it will take 1 hour to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F
Street, NW, Washington, DC 20405.
SURETY(IES) (Name and business address)
PENAL SUM OF BOND BID IDENTIFICATION
PERCENT
OF BID
PRICE
20%
AMOUNT NOT TO EXCEED BID DATE INVITATION NUMBER
6982AF25B000012 MILLION(S)
THOUSAND(S)
HUNDRED(S)
CENTS
00 FOR (Construction, Supplies or Services)
Construction
OBLIGATION:
We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.
CONDITIONS:
The Principal has submitted the bid identified above.
THEREFORE:
The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.
Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government.
Notice to the surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.
WITNESS:
The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.
PRINCIPAL
SIGNATURE(S)
1.
(Seal)
2.
3.
Corporate Seal
NAME(S) &
TITLE(S)
(Typed)
1. 2. 3.
INDIVIDUALSURETY(IES)
SIGNATURE(S)
1.
(Seal) 2.
(Seal)
NAME(S)
(Typed)
1. 2.
CORPORATE SURETY(IES)
S U
R E
T Y
A
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
Seal SIGNATURE(S) 1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
PRINCIPAL (Legal name and business address) TYPE OF ORGANIZATION ("X" one)
INDIVIDUAL PARTNERSHIP JOINT VENTURE
CORPORATION OTHER (Specify)
STATE OF INCORPORATION
B-1
STANDARD FORM 24 (REV. 10/2023) BACK
INSTRUCTIONS
1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.
2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.
3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).
4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the LIABILITY LIMIT block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.
(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed
"CORPORATE SURETY(IES)." In the space designated "SURETY(IES)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.
(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond. The Government may require the surety to furnish additional substantiating information concerning its financial capability.
5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals.
6. Type the name and title of each person signing this bond in the space provided.
7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and "offeror."
S U
R E
T Y
B
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
Corporate Seal SIGNATURE(S)
1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
S U
R E
T Y
C
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
Corporate
Seal SIGNATURE(S) 1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
S U
R E
T Y
D
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
Corporate Seal SIGNATURE(S)
1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
S U
R E
T Y
E
NAME &
SIGNATURE(S)
1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
S U
R E
T
F
SIGNATURE(S)
1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
S U
R E
T
G
SIGNATURE(S)
1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
B-2
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
BIDDER’S INFORMATION
INSTRUCTIONS: Answer all questions on this form inserting "none" or "not applicable" where appropriate. If more space is required attach additional sheets. Return the signed, dated and completed form with the bid to the address shown in the invitation for bids on or before the time set for bid opening. The prospective bidder shall provide any additional information requested by the Government during evaluation of the bids.
If the prospective bidder is a joint venture or general partnership, a separate Bidder's Qualifications form shall be provided individually for each joint venture participant or partner.
1. Name and address of business:
Name Unique Entity ID (See FAR Provision 52.204-6) *
Street Employer ID Number (EIN)*
City State Zip Code
* Necessary for Government reporting purposes only.
County
Telephone Number (Include Area Code)
Fax Number (Include Area Code) E-mail address
2. a. Type of organization (check appropriate box):
If a Foreign entity:
Individual
Non-profit organization
Corporation
Partnership
Joint Venture
Registered in:
b. Size and type of Business Concern (check appropriate boxes):
Large Business Concern
Small Disadvantaged Business Concern
Emerging Small Business
Small Business Concern
Women-Owned Small Business
SBA 8(a) Certified
HUB Zone Business Concern
Veteran Owned Business Concern
Service-Disabled Veteran-Owned Business Concern
Individual
Non-profit organization
Corporation
Partnership
Joint Venture
Incorporated in:
B-3
3. If a joint venture or general partnership:
a. Provide the name under which the project will be bid, the home office address, and name of the principal who will represent the company with regard to this project if different from "1." above.
Principal
Business Name
Street
City State Zip Code
b. Provide the name and home office addresses of each of the joint venture partners; indicate which partner is the sponsoring partner. Attach a separate sheet for additional partners.
Sponsoring Partner Other Partner
Street Street
City State Zip Code City State Zip Code
4. Date organization established: _______________________
5. Name of succeeded business, if any: _________________________________________________________
6. How many years have you been in business as:
a. General contractor years.
b. Subcontractor years.
7. a. Furnish the following information concerning the owner, partners, officers and directors:
Percent of Business Owned
Years of Business Experience
Name
Title
Contracting
Other
b. Attach resumes of these key personnel as well as the on-site project manager(s) and superintendent(s), and specifically identify the following:
- Present position, responsibility, and length of employment.
- Amount and type of construction experience.
- Amount and type of highway construction experience, including position, responsibility, and a brief project description of each period of employment.
- Formal education and training, professional or technical registrations or licenses.
B-4
8. a. Contracts in force. (Attach additional sheets if necessary)
Project Name and Contract Numbers
Owner's Name, Address, and Contact Name, Email and
Telephone #
Scope of Work Performed
Contract Amount
Estimated
Completion Date
Name of Surety
b. Are there any unresolved claims or lawsuits associated with these projects? If so, state the amount in dispute, parties involved, nature and circumstances of the dispute, and status of the matter on a separate sheet.
B-5
9. a. List up to five of the largest jobs you have completed in the last five years which are similar in project work scope to this project. (Attach additional sheets if necessary)
Project Name and Contract Numbers
Owner's Name, Address, Contact Name, Email and
Telephone # Scope of Work
Performed Original and Final Contract Amounts
Original and Final Completion Dates
Names of On-site Project Manager and Superintendent
Name of Surety
b. Are there any unresolved claims or lawsuits associated with these projects? If so, state the amount in dispute, parties involved, nature and circumstances of the dispute, and status of the matter on a separate sheet
B-6
B-7
Solicitation Provisions
52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. (SEP 2024)
52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements-Representation. (JAN 2017)
52.204-7 System for Award Management. (NOV 2024)
52.204-8 Annual Representations and Certifications. (JAN 2025)(DEVIATION FEB 2025)
52.204-16 Commercial and Government Entity Code Reporting (AUG 2020)
52.204-17 Ownership or Control of Offeror (AUG 2020)
52.204-20 Predecessor or Offeror (AUG 2020)
52.204-22 Alternative Line Item Proposal (JAN 2017)
52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)
52.204-26 Covered Telecommunications Equipment or Services-Representation. (OCT 2020)
52.209-5 Certification Regarding Responsibility Matters. (AUG 2020)
52.209-7 Information Regarding Responsibility Matters (OCT 2018)
52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law (FEB 2016)
52.209-13 Violation of Arms Control Treaties or Agreements – Certification (NOV 2021)
52.214-3 Amendments to Invitations for Bids. (DEC 2016)
52.214-4 False Statements in Bids. (APR 1984)
52.214-5 Submission of Bids. (DEC 2016)
52.214-6 Explanation to Prospective Bidders. (APR 1984)
52.214-7 Late Submissions, Modifications, and Withdrawals of Bids. (NOV 1999)
52.214-18 Preparation of Bids - Construction. (APR 1984)
B-8
52.214-19 Contract Award - Sealed Bidding - Construction. (AUG 1996)
52.214-34 Submission of Offers in the English Language. (APR 1991)
52.214-35 Submission of Offers in U.S. Currency. (APR 1991)
52.216-1 Type of Contract. (APR 1984)
The Government contemplates award of a FIRM FIXED PRICE contract resulting from this solicitation.
(End of provision)
52.219-1 Small Business Program Representations (FEB 2024)
52.222-5 Construction Wage Rate Requirements Secondary Site of the Work. (MAY 2014)
52.222-38 Compliance with Veterans' Employment Reporting Requirements. (FEB 2016)
52.223-1 Bio based Product Certification (MAY 2024)(DEVIATION FEB 2025)
As required by the Farm Security and Rural Investment Act of 2002 ( 7 U.S.C. 8101(4)) and the Energy Policy Act of 2005 ( 7 U.S.C. 8102(a)(2)(F)), the offeror certifies, by signing this offer, that biobased products (within categories of products listed by the United States Department of Agriculture in 7 CFR part 3201, subpart B) [at https://www.biopreferred.gov/resources/categories.html]) to be used or delivered in the performance of the contract, other than biobased products that are not purchased by the offeror as a direct result of this contract, will comply with the applicable specifications or other contractual requirements.
(End of provision)
52.225-10 Notice of Buy American Requirement—Construction Materials (MAY 2014)
52.225-20 Prohibition on Conducting Restricted Business Operations in Sudan-- Certification. (AUG 2009)
52.228-1 Bid Guarantee. (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title7-section8101&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title7-section8102&num=0&edition=prelim
B-9 than bid bonds -
(1) To unsuccessful bidders as soon as practicable after the opening of bids;
and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be twenty (20%) percent of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.233-2 Service of Protest. (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Mr. Ryan Phillips Acquisitions Branch Chief Federal Highway Administration 12300 West Dakota Avenue, Suite 360 Lakewood, Colorado 80228
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 Site Visit (Construction). (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
B-10
(b) Site visits may be arranged during normal duty hours by contacting: No organized site visit will be held.
52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .