This document contains the Questions and Answers from the advertisement for the CO FLAP LAR 10(1) Horsetooth Reservoir and Carter Lake federal contract opportunity.

The key details are:

  • There is an "Interested Vendors" tab on SAM.gov where vendors can view the list of interested parties, but no separate plan holders list is maintained.
  • For the past performance requirement, the prime contractor should only list their own completed projects, not subcontractor projects.
  • No organized site visit will be held for this project.
  • The bid form will be posted on SAM.gov in .xls format to allow for efficient data entry.

The underlying federal contract opportunity is for the rehabilitation and reconstruction of various parking lots and access routes at the Horsetooth and Carter Lake Reservoirs in Colorado. The project is being managed by the Federal Highway Administration. The scope includes roadway, concrete, drainage, and signage work to improve vehicular, cyclist, and pedestrian access and safety at these high-use recreational facilities.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for CO FLAP LAR 10(1) Horsetooth Res and Carter Lake

November 6, 2024

Questions Answers 1 Is there a bidders list on Sam.gov for this project? There is an interested vendors tab on SAM.gov. You have to be signed in and have tied your entity to your registration when you signed up. If both of those things don’t happen the interested vendors list tab won’t be visible.

We don’t maintain a separate plan holders list. You can call the federal service desk if you need further assistance. The number is1‐866‐ 606‐7828.

2 Past performance requirement (9.a.) “list up to five of the largest jobs you have completed in the last five years which are similar in project work scope to this project.”

a. Is the General Contractor able to submit sub-contractors jobs for past performance requirement?

b. Can the General Contractor submit projects that took place over the “five years” stated in the requirement?

The information provided is used to determine the prime contractor responsible in accordance with FAR Subpart 9.1. Please list contracts completed as prime contractor. Sheet B-5 is for active contracts in force.

Sheet B-6 is for contracts completed sometime in the last 5 years that are similar in project work and scope to this project.

3 In regards to this project, will there be any type of pre-bid meeting or site walk?

Refer to FAR Provision 52.236-27 Site Visit (Construction). No organized site visit will be held.

4 Would it be possible to receive the bid form in a .xls file format to key in more efficiently?

Yes, it will be posted on sam.gov