This document is a Questions and Answers (Q&A) file for the NM FTBL 2004(2) Wild Rivers Road federal contract opportunity dated April 23-24, 2025. The Q&A covers 31 technical and procedural questions from potential contractors about the road rehabilitation project, with responses referencing specific Federal Acquisition Regulation (FAR) clauses, Standard Construction Requirements (SCR), and Federal-aid Procedures (FP-14) sections. Key topics addressed include aggregate base and asphalt concrete pavement specifications, seeding and mulching requirements, site logistics, testing, surveying, traffic control, temporary fencing, and project performance details.
The project involves rehabilitating and reconstructing 3.21 miles of road within the Wild Rivers Recreation Area in New Mexico, with an estimated project cost between $5-10 million. The work includes widening the road surface to 34 feet with two 11-foot lanes and two 6-foot shoulders, placing 3-inch asphalt pavement over 8 inches of aggregate base. Contractors are directed to consult various referenced specifications and plan sheets for detailed requirements, and while some cost-saving alternative specifications were requested, the government indicated that value engineering proposals may be considered after contract award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Tabulation NM FTBL 2004(2) Wild Rivers Road LK.pdf | ||
| Bid Opening Summary NM FTBL 2004(2) Wild Rivers Road.pdf | ||
| QnA 04.23.25 Wild Rivers.pdf | ||
| A001 04.11.2025 Wild Rivers.pdf | ||
| XS-NMFTBL2004(2)WildRiver-Sealed Flat.pdf | ||
| FINAL-PVMNTReport-NMFTBL2004(2)WildRiver.pdf | ||
| FP-14_Eng.pdf | ||
| 6982AF24B000005 NM FTBL 2004(2) Wild Rivers Road.pdf | ||
| Plans-NMFTBL2004(2)WildRiver-250304-Sealed Flat.pdf | ||
| FINAL-HYDReport-NMFTBL2004(2)(3)WildRiver.pdf | ||
| ARPA_218-8152-25-1 TB.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for NM FTBL 2004(2) Wild Rivers Road
April 23, 2025
Questions Answers 1 The project documentation refers to FP-14 for Seeding, Mulching, and RECPs. But FP-14 provides guidelines for methods of seeding and mulching, not specific products and rates. Will you please provide a seed mixture to be used on this project as well as materials and rates for mulching?
Refer to FP-14 Subsection 625.07 and SCR Subsection 713.04 for seed mix and rates.
Refer to SCR Subsection 625.08 and FP-14 Subsection 713.05 for mulch requirements.
2 This project specifies the use of FP-14 Section 301 Aggregate Base and FP-14 Section 401 Asphalt Concrete Pavement. These specifications produce the highest quality but are also significantly more expensive, especially in this remote mountain region. These specifications are generally more applicable to higher speeds, more frequent vehicles, and more heavily loaded roadways. Since this project provides roads in a park setting with lower speeds and lighter vehicles, we believe the use FP-14 Section 302 Minor Crushed Aggregate and FP-14 Section 403 Asphalt Concrete would be more appropriate.
We believe the project, as currently proposed, will exceed the $10 million upper limit of the government range. Would the FHWA consider an amendment to revise the specifications to use FP-14 Section 302 Minor Crushed Aggregate and FP-14 Section 403 Asphalt Concrete in an attempt to control cost?
No, but a value engineering proposal may be considered after contract award.
Refer to FAR Clause 52.248-3 Value Engineering - Construction
3 Please let me know what other information/prequalification is needed in order for us to submit our proposal.
Contractor is required to comply with FAR Clause 52.236-7 Permits and Responsibilities (NOV 1991).
Required information to be submitted with your bid is outlined in the solicitation, with a listing on Sheet A-i.
April 24, 2025
Questions Answers 4 Is the base course gradation “Designation D” acceptable for item
30101 Aggregate Base?
Grading D meeting FP-14 Standard Specifications Table 703-2 is acceptable.
5 Can Type 1 Antistrip (Evotherm) be used in lieu of lime for item 40101 Asphalt Concrete Pavement?
Comply with SCR 401.01 for Type 3 Antistrip Additive. A Value Engineering proposal can be submitted after award. Refer to FAR Clause 52.248-3 Value Engineering – Construction
6 Do the Superintendent, and QC Manager need to be separate individuals?
See FP-14 and SCR Section 153
7 Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project? Please provide bidding quantities for the deteriorated base course.
Refer to FAR Clause 52.211-13 Time Extensions.
8 Please provide the site visit registration information.
There is no organized site visit. Refer to FAR Clause 52.236-27 Site Visit (Construction). (FEB 1995)
9 Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?
See SCR 158.03 (C)
10 Does this project require phasing?
No
11 Please provide lay down/staging area for construction.
Refer to plan sheet A6, and SCR Subsection 105.04
12 Can we shut down roadway access or do we need to maintain one lane for travel?
See SCR 156.07
13 What are the limitations for construction intervals (for proposed road work)?
Refer to SCR Sections 108 and 156
14 Is there an anticipated start date?
Refer to FAR Clause 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alternate I (APR 1984)
15 Is testing required?
Refer to SCR 154.04 testing
16 Is surveying required?
Refer to SCR section 152, and 623 for engineering survey requirements
17 What is the anticipated period of performance for each schedule?
Refer to FAR Clause 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alternate I (APR 1984) and SCR’s Subsection 108.01.
18 Will an extension be granted if both schedules are awarded?
Refer to SCR’s Subsection 108.01
19 With this project carrying a hard copy submission, would you consider an extension for subcontractors to put together a comprehensive proposal?
No
20 Can we spread spoils from excavation on site or do they need to be hauled off site?
Refer SCR and FP-14 section 204, and plan sheet B6
21 What is the average diameter of the trees to be removed?
Refer to Plan sheet B5, SCR Section 202
22 With no silt fencing called out on the plans should we assume the line for soil erosion control in the pricing schedule to be a silt fence running the duration of the road?
Refer to SCR section 157
23 Will wooden stakes for the silt fence suffice or is there another preferred type of silt fencing?
Refer to FP-14 713.16
24 Please further define the blotter pay line item.
Refer to FP-14 Section 411.
25 Please define the line item Special Labor, Hired Technical Service (pay item 62302¬1000).
Refer to SCR’s Section 623.
26 Do all materials need to be weed free?
Refer to SCR and FP Sections 105, 107, 157, and 713
27 Is there a signage schedule that can be provided?
Refer to plan sheet B10.
28 Can Quality Control serve and Contractor Testing serve as the same individual?
Refer FP-14 153.02(1)
29 Does the contractor need to provide anything for the government furnished field office? If so, is there power available nearby?
Refer to SCR Section 637 for information on what is to provided for the field office, as well as requirements for power source.
30 Is there any irrigation necessary? No, other than what is required by permits
31 Please provide details for pay item number (635031000)
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
(Protective Fence).
Refer to SCR and FP-14 Section 635, and Subsection 710.11.