This document is an amendment to a solicitation for a federal roadway construction project. The project, known as AZ FLAP NAV FR136(1) Joe Tank Road, involves widening and reconstructing approximately 0.6 miles of Joe Tank Road northwest of Show Low, Arizona. The scope includes removing the existing asphalt surface and base, constructing a new roadway with wider shoulders, improving drainage, extending or replacing culverts, replacing a cattle guard, adjusting utilities, and installing new signage. The estimated bid range is $2,000,000 to $5,000,000. Key dates are an advertisement in late February 2024, an award in late March 2024, and construction from May through August 2024. The solicitation is being issued by the Federal Highway Administration, Central Federal Lands Highway Division. This amendment revises several pages of the original solicitation, including the bid schedule, plans, and contract clauses.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Sheet and Description
B6 B7 B7 B7 B8 B8 B9 B9 B10 B10 B10
Survey Summary
Grading Summary
Draiange Summary
Utility Summary
Surfacing Summary
Curb and Gutter
Summary
Fence Summary
Clearing and Grubbing and
Seeding Summary
Permanent Sign
Summary
Construction Sign
Summary
Temporary Traffic Control
ALLOWANCE
Bid
Schedule
A1000 15101-0000 MOBILIZATION LPSM ALL
A1010 15215-3000 SURVEY AND STAKING, DRAINAGE
STRUCTURE EACH 11 11
A1020 15225-0000 SLOPE, REFERENCE, AND
CLEARING AND GRUBBING CONTROL MILE 0.317 0.317
A1030 15236-2000 SURVEY CONTROL, GRADE
FINISHING MILE 0.634 0.634
A1040 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL
A1050 15401-0000 CONTRACTOR TESTING LPSM ALL
A1060 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
A1070 15701-0000 SOIL EROSION CONTROL LPSM ALL
A1080 15720-0000 STORM WATER POLLUTION
PREVENTION PLAN LPSM ALL
A1090 15802-0000 WATERING FOR DUST CONTROL LPSM ALL
A1100 20101-0000 CLEARING AND GRUBBING ACRE 1.6 0.1 1.7
A1110 20301-0600 REMOVAL OF CATTLE GUARD EACH 1 1
A1120 20301-1400 REMOVAL OF INLET EACH 1 1
A1130 20301-1700 REMOVAL OF MANHOLE EACH 1 1
A1140 20301-1800 REMOVAL OF MONUMENT EACH 1 1
A1150 20301-1900 REMOVAL OF PIPE CULVERT EACH 9 9
A1160 20301-2000 REMOVAL OF PIPE END SECTION EACH 2 2
A1170 20301-2400 REMOVAL OF SIGN EACH 5 5
A1175 20302-0200 REMOVAL OF CURB LNFT 92 92
A1180 20302-0800 REMOVAL OF FENCE, BARBED WIRE LNFT 121 9 130
A1190 20401-0000 ROADWAY EXCAVATION CUYD 2,507 293 2,800
A1200 20402-0000 SUBEXCAVATION CUYD 150 As directed by CO
A1210 20441-0000 WASTE CUYD 2,635 265 2,900
A1220 20702-0100 GEOTEXTILE FILTER, CLASS 1,
TYPE A SQYD 99 6 105
A1230 20703-0000 GEOGRID SQYD 5,017 283 5,300
A1240 25101-0200 PLACED RIPRAP, METHOD A,
CLASS 2 CUYD 13 2 15
A1250 25101-0300 PLACED RIPRAP, METHOD A,
CLASS 3 CUYD 21 4 25
A1260 30202-2000 ROADWAY AGGREGATE, METHOD 2 TON 2,542 158 2,700
A1270 40301-0100 ASPHALT CONCRETE PAVEMENT,
TYPE 1 TON 956 44 1,000
A1280 40601-0000 FOG SEAL TON 2.2 0.3 2.5
A1290 41102-1000 PRIME COAT, METHOD 1 SQYD 5,017 253 5,270
A1300 41105-0000 BLOTTER TON 7.4 2.6 10.0
MileStone: Amendment 002 Date Completed: 03/21/24 Report Date: 03/21/24
A M E N D
Line Item No.
Pay Item Number
SUMMARY OF QUANTITIES - Schedule A -M a r-
:5 A
M
Remarks and/or Determination of Estimated
Quantity Pay Item Description Unit
Estimated Quantities h tt p s:
w sp o n lin en a m
-m y.
sh a re p o in t.
co m /p er so n a l/ d o u g la s_ em m o n s_ w sp co m /D o cu m en ts /D o cu m en ts /C
FL
H
D /J o e
T a n k
R o a d /R ev is ed S u b m it ta l/ u n d er a d /A m en d m en t
A Z
FL
A P N
A V F
R
S O
Q .x ls m
]S h ee t
PROJECT
B1FLAP NAV FR 136 (1)
SHEET
NUMBERA002
03/26/2024
USDE668715
Originator Text
USDE668715
Polygon
USDE668715
Originator Text
USDE668715
Polygon
USDE668715
Rectangle
USDE668715
Originator Text AMENDMENT 002 Added REMOVAL OF CURB
USDE668715
Rectangle
USDE668715
Verifier Text
REVISED: 03/22/24
USDE668715
AZ PE Emmons w Signature
USDE668715
Verifier Text 3/25/24
Survey Summary
Grading Summary
Draiange Summary
Utility Summary
Surfacing Summary
Curb and Gutter
Summary
Fence Summary
Clearing and Grubbing and
Seeding Summary
Permanent Sign
Summary
Construction Sign
Summary
Temporary Traffic Control
ALLOWANCE
Bid
Schedule
A1310 41201-0000 TACK COAT TON 2.2 0.3 2.5
A1320 60201-0600 18-INCH PIPE CULVERT LNFT 136 9 145
A1330 60201-0800 24-INCH PIPE CULVERT LNFT 501 29 530
A1340 60201-0900 30-INCH PIPE CULVERT LNFT 281 19 300
A1350 60210-0600 END SECTION FOR 18-INCH PIPE
CULVERT EACH 7 7
A1360 60210-0800 END SECTION FOR 24-INCH PIPE
CULVERT EACH 2 2
A1370 60210-0900 END SECTION FOR 30-INCH PIPE
CULVERT EACH 4 4
A1380 60401-0000 MANHOLE EACH 2 2
A1390 60403-0000 INLET EACH 2 2
A1400 60404-0000 CATCH BASIN EACH 1 1
A1410 60901-0600 CURB, CONCRETE, 8-INCH DEPTH LNFT 2,581 169 2,750
A1420 60902-1000 CURB AND GUTTER, CONCRETE,
12-INCH DEPTH LNFT 659 41 700
A1430 61108-1000 ADJUST WATER VALVE EACH 3 3
A1440 61901-0600 FENCE, BARBED WIRE LNFT 93 7 100
A1450 61902-2300 GATE, BARBED WIRE EACH 1 1
A1460 61903-0900 CATTLE GUARD, 28 FEET EACH 1 1
A1470 61920-2000 REMOVE AND RESET GATE EACH 1 1
A1480 62201-0200 DUMP TRUCK, 8 CUBIC YARD
MINIMUM CAPACITY HOUR 10
A1490 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT
MINIMUM RATED CAPACITY
BUCKET, 24-INCH WIDTH HOUR 10
A1500 62201-0950 WHEEL LOADER, 3 CUBIC YARD
MINIMUM RATED CAPACITY HOUR 15
A1510 62201-1450 BULLDOZER, 350HP MINIMUM
FLYWHEEL POWER HOUR 5
A1520 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM
BLADE HOUR 10
A1530 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC
YARD MINIMUM CAPACITY HOUR 10
A1540 62301-0000 GENERAL LABOR HOUR 100
A1550 62302-1000 SPECIAL LABOR, HIRED
TECHNICAL SERVICES HOUR 20
A1560 62302-1100 SPECIAL LABOR, HIRED SURVEY
SERVICES HOUR 30
-M a r-
:5 A
M
MileStone: Amendment 002 Date Completed: 03/21/24 Report Date: 03/21/24 h tt p s:
w sp o n lin en a m
-m y.
sh a re p o in t.
co m /p er so n a l/ d o u g la s_ em m o n s_ w sp co m /D o cu m en ts /D o cu m en ts /C
FL
H
D /J o e
T a n k
R o a d /R ev is ed S u b m it ta l/ u n d er a d /A m en d m en t
A Z
FL
A P N
A V F
R
S O
Q .x ls m
]S h ee t (2
) SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
PROJECT
B2FLAP NAV FR 136 (1)
SHEET
NUMBERA002
03/26/2024
USDE668715
Originator Text
USDE668715
Polygon
USDE668715
Originator Text AMENDMENT 002 Added REMOVAL OF CURB
USDE668715
Rectangle
USDE668715
Verifier Text
REVISED: 03/22/24
USDE668715
AZ PE Emmons w Signature
USDE668715
Survey Summary
Grading Summary
Draiange Summary
Utility Summary
Surfacing Summary
Curb and Gutter
Summary
Fence Summary
Clearing and Grubbing and
Seeding Summary
Permanent Sign
Summary
Construction Sign
Summary
Temporary Traffic Control
ALLOWANCE
Bid
Schedule
A1570 62406-0300 PLACING CONSERVED TOPSOIL,
4-INCH DEPTH ACRE 1.4 0.1 1.5
A1580 62510-1000 SEEDING, DRY METHOD ACRE 1.4 0.1 1.5
A1590 62515-1000 MULCHING, DRY METHOD ACRE 1.3 0.1 1.4
A1600 62901-0300 ROLLED EROSION CONTROL
PRODUCT, TYPE 1.C SQYD 609 31 640
A1610 63301-0000 SIGN SYSTEM EACH 17 17
A1620 63316-1000 REMOVE AND RESET SIGN EACH 1 1
A1630 63501-2000 TEMPORARY TRAFFIC CONTROL,
TRAFFIC SIGNAL SYSTEM LPSM All ALL
A1640 63502-0700 TEMPORARY TRAFFIC CONTROL,
CONE EACH 27 27
A1650 63502-1300 TEMPORARY TRAFFIC CONTROL,
DRUM EACH 70 70
A1660 63502-1600 TEMPORARY TRAFFIC CONTROL,
WARNING LIGHT TYPE B EACH 4 4
A1670 63502-2000 TEMPORARY TRAFFIC CONTROL,
PORTABLE CHANGEABLE MESSAGE
SIGN EACH 2 2
A1680 63504-1000 TEMPORARY TRAFFIC CONTROL,
CONSTRUCTION SIGN SQFT 56 56
A1690 63506-0500 TEMPORARY TRAFFIC CONTROL,
FLAGGER HOUR 690 690
A1700 63701-0000 FIELD OFFICE EACH 1
-M a r-
:5 A
M
MileStone: Amendment 002 Date Completed: 03/21/24 Report Date: 03/21/24 h tt p s:
w sp o n lin en a m
-m y.
sh a re p o in t.
co m /p er so n a l/ d o u g la s_ em m o n s_ w sp co m /D o cu m en ts /D o cu m en ts /C
FL
H
D /J o e
T a n k
R o a d /R ev is ed S u b m it ta l/ u n d er a d /A m en d m en t
A Z
FL
A P N
A V F
R
S O
Q .x ls m
]S h ee t (3
) SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
PROJECT
B3FLAP NAV FR 136 (1)
SHEET
NUMBERA002
03/26/2024
USDE668715
Originator Text
USDE668715
Polygon
USDE668715
Originator Text AMENDMENT 002 Added REMOVAL OF CURB
USDE668715
Rectangle
USDE668715
Verifier Text
REVISED: 03/22/24
USDE668715
AZ PE Emmons w Signature
USDE668715
STATE PROJECT
T
IM
E
D
G N
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
D A
T E
U
S E
R
NUMBER
SHEET
AZ
Joe Tank Road
FLAP NAV FR136 (1)
GUTTER SUMMARY
SURFACING, CURB AND
B8
AMENDMENT A002
3/22/24 Add Removal of Curb2
REVISED: MARCH 22,2024
A002 03/26/2024
USDE668715
AZ PE Emmons w Signature
USDE668715
3/22/24
SD
W V
WATER
+T
T
TP
TP
W V
W V
SS+
SS++
W V
TP
SS+
TP
G
PS
W
W V
W V
SS+
N69°41'19"E N40° 29'4
1"E
N55°29'59"E
N69°41'19"E N40° 29'4
1"E
N55°29'59"E
N
200'100'0
Scale in Feet
LC Joe Tank Road
Profile grade
E 722314.76
N 1189159.82
Station 136+18.95
Joe Tank Road
End Schedule A place
Protect Manhole in
R ip r a p c la s s
L t.
E n d s e c ti o n s
I s ta ll x
C
M P c u lv e r t e a c h
L t.
R e m o v e e x is ti g
R ip r a p c la s s
L t.
E n d s e c ti o n s L t.
a n d R t.
I n s ta ll x
C
M P
R e m o v e e x is ti n g c u lv e r t c a tc h b a s in
L t.
T ie i n to p r o p o s d
E d s e c ti o n
R t.
I n s ta ll x
R
C P m o v e e x is ti n g c u lv e r t
Match existing
131+80.01
Match existing curb concrete, 12-inch depth.
Begin curb and gutter, 129+46
Protect manhole in place
131+39
Protect manhole in place
131+43 to avoid manhole
Steepen back slope p r o p o s e d c a tc h b a s in
E n d s e c ti o n L t.
T ie i to s ta ll x
R
C P m o v e e n d s e c ti o n s L t.
R e m o v e e x is ti n g c u lv e r t pavement from SR260
Sawcut 2' from edge of
Existing ground
A
A
A sewer system sections for storm
See drainage cross
R e m o v e e x is ti n g c u lv e r t
61.47' Rt.
PT 135+64.34'
72.79' Lt.
PT 136+17.20
PC 135+27.46
PC 135+33.11
Apache-Sitgreaves National Forest Bison Ridge Development
Bison Ridge Development
135+91
End Schedule A Surfacing
127+34
Raise 0.10 ft.
Adjust water valve (2 ea.)
128+94 to avoid manhole
Steepen back slope
131+02
Raise 0.54 ft.
Adjust water valve
132+29 valves in place
Protect water
A
129+23
Remove monument
131+08.16
Match existing curb
End curb m a n h o le
L t.
c a tc h b a s in
L t a
T ie i n to p r o p o s s ta ll x
R
C P
R e m o v e e x is ti n g c u lv e r t m a n h o le s
L t.
T ie i n to p r o p o s
I n s ta ll x
R
C P
R ip r a p c la s s
L t.
m a n h o le s
L t.
T ie i n to p r o p o s d s e c ti o n
L t.
I n s ta ll x
R
C P c a tc h b a s in s L t.
R t.
T ie i n to p r o p o s
I n s ta ll x
R
C P m a n h o le
L t.
c a tc h b a s in
L t.
a n d
T ie i n to p r o p o s
I n s ta ll x
R
C P
133+44.65 concrete, 12-inch depth.
Begin curb and gutter, depth to curb, concrete 8-inch depth after inlet, both sides
5-foot transition from curb and gutter, concrete, 12-inch m a n h o le c u lv e r t a x is ti g m o v at 6342.24 Rt.
section at 129+70.00
Grade ditch to end
Transition from 4' to 5'
Transition from 2.5' to 4' at 132+03.35 at 6337.40 Lt.
Grade ditch to end section
ADOT R/W
AMENDEMNT A002
2 ADDED REMOVAL OF CURB
of Curb
Remove 45 LNFT of Curb
Remove 47 LNFT
REVISED 03/22/24
N69°41'19"E N40° 29'4
1"E
N55°29'59"E
'133.81L =
'68.48T =
'255.00R =
(RT)30°03'58"Δ =
126+97.26PI
'87.73L = '44.12T = '335.00R =
(RT)15°00'18"Δ =
135+16.98PI
'313.36L = '160.16T = '615.00R =
(LT)29°11'38"Δ =
130+79.53PI
.3
.7
.5
.8
.5
.9
P
O
-1.752%
-7.003%
-1.752%
-1.556%
.1
.1
' VC200
38.09K =
'158.39SSD =
' VC95
17K =
'124.14HLSD =
127+00 128+00 129+00 130+00 131+00 132+00 133+00 134+00 135+00 136+00
6,290 6,290
6,300 6,300
6,310 6,310
6,320 6,320
6,330 6,330
6,340 6,340
6,350 6,350
6,360 6,360
6,370 6,370
.0
Trasition from 1.41' to 1.5'Ditch Depth Rt. = 1.44' + .0
.1
.1
Lt. = 4.0' Ditch Depth +
Lt. = 2.5' Ditch Depth
.7
2'
35' R
100' R
2"
:0
M
M a rc h
J o e T a n k R o a d C
L
P la n
S h e t] c b m s \w s p -u s -p w -c o \d m s \p n p (a z jt )j o e ta n k .d g n
Sta 127+00 to 136+20 Plan and Profile Joe Tank Road
STATE PROJECT
NUMBER
SHEET
AZ
Joe Tank Road
FLAP NAV FR136 (1)
C3
3/2 5/2
A002 03/26/2024
USDE668715
AZ PE Emmons w Signature
USDE668715
3/22/24
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
PAGE OF PAGES1. SOLICITATION NUMBER
6982AF24B000004 1 OF 2
3. DATE ISSUED
02/23/2024
HFLCEO240095PR AZ FLAP NAV FR136(1)
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENUE
LAKEWOOD, CO 80228
Laura Vallejos, Contract Specialist
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENUE
LAKEWOOD, CO 80228
SEE PAGE A-3 SEE PAGE A-3
ROADWAY CONSTRUCTION PROJECT IN STRICT ACCORDANCE WITH:
1. FEDERAL ACQUISITION AND TRANSPORTATION ACQUISITION REGULATIONS (FAR & TAR)
2. DEPARTMENT OF LABOR, CONSTRUCTION WAGE RATE REQUIREMENTS
3. SPECIAL CONTRACT REQUIREMENTS
4. PLANS
5. BID SCHEDULE
6. STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS, FP-14, U.S. CUSTOMARY UNITS
7. SUBCONTRACTING PLAN (IF APPLICABLE)
See Subsection 104.04 of the FP-14 for governing order of precedence.
10 * X X 108.01 as amended in the
Special Contract Requirements.
X
0 2:00 pm local time 03/28/2024
X
X
A-1 A002 03/26/2023
04/04/2024 laura.vallejos Cross-Out
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A1000 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A1010 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
11 EACH $____________ $____________
A1020 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL
0.317 MILE $____________ $____________
A1030 15236-2000 SURVEY CONTROL, GRADE FINISHING
0.634 MILE $____________ $____________
A1040 15301-0000 CONTRACTOR QUALITY CONTROL
ALL LPSM $___LPSM_____ $____________
A1050 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A1060 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
A1070 15701-0000 SOIL EROSION CONTROL
ALL LPSM $___LPSM_____ $____________
A1080 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
A1090 15802-0000 WATERING FOR DUST CONTROL
ALL LPSM $___LPSM_____ $____________
A1100 20101-0000 CLEARING AND GRUBBING
1.7 ACRE $____________ $____________
A1110 20301-0600 REMOVAL OF CATTLE GUARD
1 EACH $____________ $____________
A1120 20301-1400 REMOVAL OF INLET
1 EACH $____________ $____________
A1130 20301-1700 REMOVAL OF MANHOLE
1 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:AZ FLAP NAV FR136(1)
Project Name:Joe Tank Road
A7 A002 03/26/2024
A1140 20301-1800 REMOVAL OF MONUMENT
1 EACH $____________ $____________
A1150 20301-1900 REMOVAL OF PIPE CULVERT
9 EACH $____________ $____________
A1160 20301-2000 REMOVAL OF PIPE END SECTION
2 EACH $____________ $____________
A1170 20301-2400 REMOVAL OF SIGN
5 EACH $____________ $____________
A002 A1175 20302-0200 REMOVAL OF CURB
92 LNFT $____________ $____________
A1180 20302-0800 REMOVAL OF FENCE, BARBED WIRE
130 LNFT $____________ $____________
A1190 20401-0000 ROADWAY EXCAVATION
2,800 CUYD $____________ $____________
A1200 20402-0000 SUBEXCAVATION
150 CUYD $____________ $____________
A1210 20441-0000 WASTE
2,900 CUYD $____________ $____________
A1220 20702-0100 GEOTEXTILE FILTER, CLASS 1, TYPE A
105 SQYD $____________ $____________
A1230 20703-0000 GEOGRID
5,300 SQYD $____________ $____________
A1240 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2
15 CUYD $____________ $____________
A1250 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3
25 CUYD $____________ $____________
A1260 30202-2000 ROADWAY AGGREGATE, METHOD 2
2,700 TON $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:AZ FLAP NAV FR136(1)
Project Name:Joe Tank Road
A8 A002
A1270 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
1,000 TON $____________ $____________
A1280 40601-0000 FOG SEAL
2.5 TON $____________ $____________
A1290 41102-1000 PRIME COAT, METHOD 1
5,270 SQYD $____________ $____________
A1300 41105-0000 BLOTTER
10.0 TON $____________ $____________
A1310 41201-0000 TACK COAT
2.5 TON $____________ $____________
A1320 60201-0600 18-INCH PIPE CULVERT
145 LNFT $____________ $____________
A1330 60201-0800 24-INCH PIPE CULVERT
530 LNFT $____________ $____________
A1340 60201-0900 30-INCH PIPE CULVERT
300 LNFT $____________ $____________
A1350 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT
7 EACH $____________ $____________
A1360 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT
2 EACH $____________ $____________
A1370 60210-0900 END SECTION FOR 30-INCH PIPE CULVERT
4 EACH $____________ $____________
A1380 60401-0000 MANHOLE
2 EACH $____________ $____________
A1390 60403-0000 INLET
2 EACH $____________ $____________
A1400 60404-0000 CATCH BASIN
1 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:AZ FLAP NAV FR136(1)
Project Name:Joe Tank Road
A9 A002
A1410 60901-0600 CURB, CONCRETE, 8-INCH DEPTH
2,750 LNFT $____________ $____________
A1420 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH
700 LNFT $____________ $____________
A1430 61108-1000 ADJUST WATER VALVE
3 EACH $____________ $____________
A1440 61901-0600 FENCE, BARBED WIRE
100 LNFT $____________ $____________
A1450 61902-2300 GATE, BARBED WIRE
1 EACH $____________ $____________
A1460 61903-0900 CATTLE GUARD, 28 FEET
1 EACH $____________ $____________
A1470 61920-2000 REMOVE AND RESET GATE
1 EACH $____________ $____________
A1480 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
10 HOUR $____________ $____________
A1490 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET,
24-INCH WIDTH
10 HOUR $____________ $____________
A1500 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
15 HOUR $____________ $____________
A1510 62201-1450 BULLDOZER, 350HP MINIMUM FLYWHEEL POWER
5 HOUR $____________ $____________
A1520 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
10 HOUR $____________ $____________
A1530 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
10 HOUR $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:AZ FLAP NAV FR136(1)
Project Name:Joe Tank Road
A10 A002
A1540 62301-0000 GENERAL LABOR
100 HOUR $____________ $____________
A1550 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
20 HOUR $____________ $____________
A1560 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
30 HOUR $____________ $____________
A1570 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
1.5 ACRE $____________ $____________
A1580 62510-1000 SEEDING, DRY METHOD
1.5 ACRE $____________ $____________
A1590 62515-1000 MULCHING, DRY METHOD
1.4 ACRE $____________ $____________
A1600 62901-0300 ROLLED EROSION CONTROL PRODUCT, TYPE 1.C
640 SQYD $____________ $____________
A1610 63301-0000 SIGN SYSTEM
17 EACH $____________ $____________
A1620 63316-1000 REMOVE AND RESET SIGN
1 EACH $____________ $____________
A1630 63501-2000 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
ALL LPSM $___LPSM_____ $____________
A1640 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
27 EACH $____________ $____________
A1650 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
70 EACH $____________ $____________
A1660 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
4 EACH $____________ $____________
A1670 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
2 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:AZ FLAP NAV FR136(1)
Project Name:Joe Tank Road
A11 A002
A1680 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
56 SQFT $____________ $____________
A1690 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
690 HOUR $____________ $____________
A1700 63701-0000 FIELD OFFICE
1 EACH $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:AZ FLAP NAV FR136(1)
Project Name:Joe Tank Road
A12 A002
Bid Schedule Instructions
BIDDERS, PLEASE NOTE: This Bid Proposal is comprised of one schedule and one option. Before preparing the bid, carefully read the Solicitation Provisions and the following:
• Insert a numeric unit bid price for each pay item for which a quantity appears in the bid schedule. Unit bid prices should be quoted no more precisely than the nearest cent (2 decimal places). Unit bid prices quoted more precisely will be rounded up to the nearest cent by the Government
• Multiply the unit price by the quantity for each pay item and show the amount bid.
When the words “Lump Sum” appear as a unit bid price, insert an amount for each lump sum pay item.
• Total all amounts bid for each pay item and show the Construction Cost Total on the space provided on the last page of each schedule or option.
• Also show the Construction Cost Total for each schedule/option as well as the combined Total of each Schedule and the Option in the spaces provided on the Bid Summary page.
NOTE: If the amount bid for a pay item is inconsistent with the product of the unit price provided by the bidder and the quantity provided by the Government, the unit price will govern and the Government will determine a corrected amount bid for the pay item by multiplying the unit price by the quantity.
Basis for Award
To be eligible for award of contract, the offeror shall submit prices for each item in Bid Schedule A and Option X. Accordingly, contract award will be made to the lowest responsible bidder conforming to the solicitation, provided funds are available and the Contracting Officer determines the price to be reasonable.
Per FAR provision 52.217-5, Evaluation of Options (JULY 1990), the Government will evaluate offers for award purposes by adding the total price for all options to the total price for Schedule A. Evaluation of options will not obligate the Government to exercise the option(s). If the determination is made to exercise any of the Options, the Contracting Officer will provide the contractor with written notice no later than 90 60 days after contract award, per FAR clause 52.217-7, Option for Increased Quantity- Separately Priced Line Item
(MAR 1989).
A-4 A002 03/26/2024
C-4
52.211-18 Variation in Estimated Quantity. (APR 1984)
52.214-26 Audit and Records – Sealed Bidding. (JUN 2020)
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data – Modifications – Sealed Bidding. (JUN 2020)
52.214-28 Subcontractor Certified Cost or Pricing Data – Modifications – Sealed Bidding.
(JUN 2020)
52.217-7 Option for Increased Quantity - Separately Priced Line Item. (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 90 60 days after award. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns. (OCT 2022)
(a) Evaluation preference. (1) Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except-
(i) Offers from HUBZone small business concerns that have not waived the evaluation preference; and
(ii) Otherwise successful offers from small business concerns.
(2) The factor of 10 percent shall be applied on a line item basis or to any group of items on which award may be made. Other evaluation factors described in the solicitation shall be applied before application of the factor.
(3) When the two highest rated offerors are a HUBZone small business concern and a large business, and the evaluated offer of the HUBZone small business concern is equal to the evaluated offer of the large business after considering the price evaluation preference, award will be made to the HUBZone small business concern.
(b) Waiver of evaluation preference. A HUBZone small business concern may elect to waive the evaluation preference, in which case the factor will be added to its offer for evaluation purposes.
□ Offeror elects to waive the evaluation preference.
A002 03/26/2024
| topmostSubform[0]: |
| Page1[0]: |
| ContractIDCode[0]: |
| Page[0]: 1 |
| Pages[0]: 15 |
| AmendmentNo[0]: A002 |
| EffectiveDate[0]: 03/26/2024 |
| ReqNumber[0]: HFLCEO240095PR |
| ProjectNo[0]: AZ FLAP NAV FR136(1) |
| IssuedBy[0]: FEDERAL HIGHWAY ADMINISTRATION |
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENUE, SUITE 360
LAKEWOOD, COLORADO 80228
ATTENTION: CONTRACT SPECIALIST NAME
| Code[0]: 6905001 |
| AdministeredBy[0]: |
| Code[2]: |
| NameandAddress[0]: |
| Code[1]: |
| FacilityCode[0]: |
| CheckBox9[0]: 1 |
| AmendmentNo[1]: 6982AF24B000004 |
| Dated9B[0]: 02/23/2024 |
| CheckBox10[0]: Off |
| ModificationNo[0]: |
| Dated10B[0]: |
| CheckBox11[0]: 1 |
| Extended[0]: 1 |
| NotExtended[0]: Off |
| Copies[0]: 0* |
| AccountingData[0]: |
| CheckBox13A[0]: Off |
| A13[0]: |
| CheckBox13B[0]: Off |
| CheckBox13C[0]: Off |
| C13[0]: |
| CheckBox13D[0]: Off |
| D13[0]: |
| IsNot[0]: Off |
| Is[0]: 1 |
| CopiesReturned[0]: *See Item 14 |
| Description[0]: PLANS |
Remove and replace pages B1, B2, B3, B8 and C3 with the attached corresponding page.
INVITATION FOR BID- A-Section Replace page A-1, 1442 with attached amended page A-1.
Replace page A-4 with attached amended page A-4.
Replace page A-7 to page A-12 with attached amended page A-7 to page A-12.
INVITATION FOR BID- C - Section Replace page C-4 with attached amended page C-4.
*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)
| NameandTitleSigner[0]: |
| DateSigned[0]: |
| NameandTitleOfficer[0]: |
| DateSigned[1]: |
File details come from the government source that posted it. Updated .