Questions and Answers During Advertisement for CO FLAP PIT 82(1) 10182022.pdf

PDF 150 KB Posted

Attached to
CO FLAP PIT 82(1) Brush Creek Parking Area
Solicitation number
6982AF22B000026
Issued by

About this file

This document contains questions and answers regarding the advertisement for Colorado Federal Lands Access Program Project Number 82(1) Brush Creek Parking Area. The project involves construction of a parking area and requires the installation of a window system, which may be either aluminum storefront or steel windows. Approved window manufacturers were not specified so submitted manufacturers must meet performance criteria. Restroom ceilings are to be tongue and groove. Effluent from the project is to be discharged into a leach field in accordance with specified construction and development standards.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers During Advertisement for CO FLAP PIT 82(1) Brush Creek Parking Area

Tuesday, October 18, 2022

Questions Answers

1 Can you clarify what the window system is? Metal, Aluminum Storefront, Curtain Wall?

Regarding the window system. All details were drafted off Hope steel windows that can be custom. So we have aluminum storefront spec and this certainly may be attempted as storefront, but we went steel for durability and wanted to minimize window sitelines. We will need to decide if going aluminum storefront or steel windows and if storefront, details will need to be revisited.

2 What are the approved window manufacturers? Approved manufactures were removed. Submitted manufactures will need to comply with performance criteria.

3 What is the size of the window system? Per the plans, it appears to be 2" x 8-1/2" which isn’t a typical storefront dimension

The drawings note 6.5” and 8.5” depths. That is possible with Hope windows. If going storefront, I think the deepest we can go is 6.5” and that is quickly looking at Kawneer, YKK, and Tubelite.

There are limitations on hopper windows W3 and W4 and W5, they are too long and may need to be broken apart. 60" wide is max for storefront hopper windows. Please confirm

Pending mfr this is true and a split down the center on the hopper is acceptable.

5 There are a few general notes and flags for fire alarm, but we don’t see it called out specifically. Is fire alarm required?

2015 IBC Chapter 9 (907) doesn’t stipulate the need in a Group U building, which this building was designed under. If there are comments from the building permitting regarding this, those comments would need to be addressed.

6 E-602 – We are assuming the transformer is by others, please confirm

**** I believe this is the case, but I need to confirm it with the electrical Lead, who has been out. Please stand by on this one.

7 A-103 – Reflected Ceiling Plan doesn’t have a keynote for the ceiling in the restrooms, please confirm they are T&G.C12 They are T&G

8 What is the effluent discharge standard for this project?

a. The domestic effluent is to be discharged into ground water (i.e., leech field), not to surface water or municipal sewage treatment plant. Please, see Section 612.03 for on-site treatment system design requirements.

Construction and Development effluent standards are addressed in Section 157.