Bid Tabs - OK ERFO SEQU T500(1) Horton Slough Trail.pdf

PDF 664 KB Posted

Attached to
OK ERFO SEQU T500(1)Horton Slough Trail
Solicitation number
6982AF21B000012
Issued by

About this file

This document contains a bid tabulation report for the OK ERFO SEQU T500(1) Horton Slough Trail federal construction project. Four contractors submitted bids by the June 9, 2021 deadline to provide repairs to three sites within the Sequoyah National Wildlife Refuge damaged in 2019 floods, including clearing and grubbing, pedestrian bridge and trail construction, observation deck construction, and pavement patching. The estimated total project cost was $990,000 to $1,500,000. Randy Kinder Excavating, Inc. provided the lowest bid of $1,198,000.75. Higher bids came from Federal Constructors, Inc. at $1,324,920, Steve Beam Construction, Inc. at $1,429,753.79, and Mobley Contractors, Inc. at the highest bid of $2,397,864.92. The engineer's estimate was $990,000. The bid tabulation provides unit pricing and totals for over 50 line items. No award has been made as of the June 10, 2021 tabulation report date.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 06/10/21

1 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Solcitation No:

Division: Central Federal Lands

State: OK County: Sequoyah

Federal Land: Sequoyah National Wildlife Refuge Opened at: Lakewood, CO

Opened by: Jorey Deml

Date: 06/09/21

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Randy Kinder Excavating, Inc. $1,198,000.75 12965 Carrier Lane Dexter, MO 63841

Federal Constructors, Inc. $1,324,920.00 1900 NE 36th Street Suite 102 Oklahoma City, OK 73111

Steve Beam Construction, Inc. $1,429,753.79 7201 South 28th Street Fort Smith, AR 72908

Mobley Contractors, Inc. $2,397,864.92 952 Hwy 287 Morrilton, AR 72110

Engineer's Estimate $990,000.00

2 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0050 15101-0000 MOBILIZATION

Randy Kinder Excavating, Inc. Lump Sum $186,000.00 Federal Constructors, Inc. Lump Sum $162,900.00 Steve Beam Construction, Inc. Lump Sum $87,360.00 Mobley Contractors, Inc. Lump Sum $335,533.43 Engineer's Estimate ALL LPSM Lump Sum $139,670.00

A0100 15201-0000 CONSTRUCTION SURVEY AND STAKING (OBSERVATION DECK)

Randy Kinder Excavating, Inc. Lump Sum $3,948.00 Federal Constructors, Inc. Lump Sum $8,700.00 Steve Beam Construction, Inc. Lump Sum $5,280.00 Mobley Contractors, Inc. Lump Sum $5,113.60 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

A0150 15201-0000 CONSTRUCTION SURVEY AND STAKING

Randy Kinder Excavating, Inc. Lump Sum $3,290.00 Federal Constructors, Inc. Lump Sum $11,300.00 Steve Beam Construction, Inc. Lump Sum $3,240.00 Mobley Contractors, Inc. Lump Sum $16,464.13 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

A0200 15214-1000 SURVEY AND STAKING, BRIDGE

Randy Kinder Excavating, Inc. Lump Sum $7,895.00 Federal Constructors, Inc. Lump Sum $12,400.00 Steve Beam Construction, Inc. Lump Sum $7,440.00 Mobley Contractors, Inc. Lump Sum $8,470.95 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

A0250 15301-0000 CONTRACTOR QUALITY CONTROL

Randy Kinder Excavating, Inc. Lump Sum $57,275.00 Federal Constructors, Inc. Lump Sum $146,400.00 Steve Beam Construction, Inc. Lump Sum $34,090.00 Mobley Contractors, Inc. Lump Sum $334,959.38 Engineer's Estimate ALL LPSM Lump Sum $12,000.00

A0300 15401-0000 CONTRACTOR TESTING

Randy Kinder Excavating, Inc. Lump Sum $26,315.00 Federal Constructors, Inc. Lump Sum $21,000.00 Steve Beam Construction, Inc. Lump Sum $4,820.00 Mobley Contractors, Inc. Lump Sum $56,091.65 Engineer's Estimate ALL LPSM Lump Sum $12,000.00

3 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0350 15501-0000 CONSTRUCTION SCHEDULE

Randy Kinder Excavating, Inc. Lump Sum $6,580.00 Federal Constructors, Inc. Lump Sum $9,000.00 Steve Beam Construction, Inc. Lump Sum $9,590.00 Mobley Contractors, Inc. Lump Sum $12,226.00 Engineer's Estimate ALL LPSM Lump Sum $4,000.00

A0400 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Randy Kinder Excavating, Inc. $3.57 $3,570.00 Federal Constructors, Inc. $8.20 $8,200.00 Steve Beam Construction, Inc. $9.48 $9,480.00 Mobley Contractors, Inc. $9.47 $9,470.00 Engineer's Estimate 1,000 LNFT $5.00 $5,000.00

A0450 15802-0000 WATERING FOR DUST CONTROL

Randy Kinder Excavating, Inc. Lump Sum $10,000.00 Federal Constructors, Inc. Lump Sum $29,000.00 Steve Beam Construction, Inc. Lump Sum $7,050.00 Mobley Contractors, Inc. Lump Sum $4,915.51 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

A0500 20102-0000 CLEARING AND GRUBBING

Randy Kinder Excavating, Inc. Lump Sum $89,285.00 Federal Constructors, Inc. Lump Sum $42,000.00 Steve Beam Construction, Inc. Lump Sum $20,940.00 Mobley Contractors, Inc. Lump Sum $97,016.70 Engineer's Estimate ALL LPSM Lump Sum $40,000.00

A0550 20103-0000 CLEARING AND GRUBBING

Randy Kinder Excavating, Inc. $13.00 $9,100.00 Federal Constructors, Inc. $12.00 $8,400.00 Steve Beam Construction, Inc. $20.00 $14,000.00 Mobley Contractors, Inc. $110.53 $77,371.00 Engineer's Estimate 700 SQYD $30.00 $21,000.00

A0600 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Randy Kinder Excavating, Inc. Lump Sum $5,530.00 Federal Constructors, Inc. Lump Sum $46,000.00 Steve Beam Construction, Inc. Lump Sum $6,720.00 Mobley Contractors, Inc. Lump Sum $27,284.06 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

4 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0650 20304-2000 REMOVAL OF BRIDGE

Randy Kinder Excavating, Inc. Lump Sum $8,962.00 Federal Constructors, Inc. Lump Sum $31,000.00 Steve Beam Construction, Inc. Lump Sum $34,370.00 Mobley Contractors, Inc. Lump Sum $41,524.56 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0700 20401-0000 ROADWAY EXCAVATION

Randy Kinder Excavating, Inc. $37.00 $1,295.00 Federal Constructors, Inc. $80.00 $2,800.00 Steve Beam Construction, Inc. $90.00 $3,150.00 Mobley Contractors, Inc. $146.85 $5,139.75 Engineer's Estimate 35 CUYD $80.00 $2,800.00

A0750 20420-0000 EMBANKMENT CONSTRUCTION

Randy Kinder Excavating, Inc. $47.90 $11,017.00 Federal Constructors, Inc. $122.00 $28,060.00 Steve Beam Construction, Inc. $73.50 $16,905.00 Mobley Contractors, Inc. $169.65 $39,019.50 Engineer's Estimate 230 CUYD $90.00 $20,700.00

A0800 20801-0000 STRUCTURE EXCAVATION

Randy Kinder Excavating, Inc. $63.00 $4,410.00 Federal Constructors, Inc. $93.00 $6,510.00 Steve Beam Construction, Inc. $42.50 $2,975.00 Mobley Contractors, Inc. $156.62 $10,963.40 Engineer's Estimate 70 CUYD $100.00 $7,000.00

A0850 20803-0000 STRUCTURAL BACKFILL

Randy Kinder Excavating, Inc. $112.00 $6,384.00 Federal Constructors, Inc. $130.00 $7,410.00 Steve Beam Construction, Inc. $150.00 $8,550.00 Mobley Contractors, Inc. $591.49 $33,714.93 Engineer's Estimate 57 CUYD $100.00 $5,700.00

A0900 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1

Randy Kinder Excavating, Inc. $204.20 $4,084.00 Federal Constructors, Inc. $124.00 $2,480.00 Steve Beam Construction, Inc. $217.00 $4,340.00 Mobley Contractors, Inc. $273.34 $5,466.80 Engineer's Estimate 20 CUYD $120.00 $2,400.00

5 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0950 25101-0500 PLACED RIPRAP, METHOD A, CLASS 5

Randy Kinder Excavating, Inc. $84.20 $46,310.00 Federal Constructors, Inc. $149.00 $81,950.00 Steve Beam Construction, Inc. $183.00 $100,650.00 Mobley Contractors, Inc. $146.92 $80,806.00 Engineer's Estimate 550 CUYD $160.00 $88,000.00

A1000 30202-2000 ROADWAY AGGREGATE, METHOD 2

Randy Kinder Excavating, Inc. $35.00 $4,900.00 Federal Constructors, Inc. $43.00 $6,020.00 Steve Beam Construction, Inc. $150.00 $21,000.00 Mobley Contractors, Inc. $76.07 $10,649.80 Engineer's Estimate 140 TON $80.00 $11,200.00

A1050 40301-0200 ASPHALT CONCRETE PAVEMENT, TYPE 2

Randy Kinder Excavating, Inc. $315.80 $37,896.00 Federal Constructors, Inc. $224.00 $26,880.00 Steve Beam Construction, Inc. $416.00 $49,920.00 Mobley Contractors, Inc. $268.75 $32,250.00 Engineer's Estimate 120 TON $400.00 $48,000.00

A1100 41102-1000 PRIME COAT, METHOD 1

Randy Kinder Excavating, Inc. $3.95 $2,844.00 Federal Constructors, Inc. $8.00 $5,760.00 Steve Beam Construction, Inc. $1.63 $1,173.60 Mobley Contractors, Inc. $3.75 $2,700.00 Engineer's Estimate 720 SQYD $2.50 $1,800.00

A1150 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Randy Kinder Excavating, Inc. $1,088.00 $28,288.00 Federal Constructors, Inc. $925.00 $24,050.00 Steve Beam Construction, Inc. $1,200.00 $31,200.00 Mobley Contractors, Inc. $2,017.65 $52,458.90 Engineer's Estimate 26 CUYD $2,000.00 $52,000.00

A1200 55401-1000 REINFORCING STEEL

Randy Kinder Excavating, Inc. $3.32 $9,628.00 Federal Constructors, Inc. $1.50 $4,350.00 Steve Beam Construction, Inc. $3.50 $10,150.00 Mobley Contractors, Inc. $3.66 $10,614.00 Engineer's Estimate 2,900 LB $2.00 $5,800.00

6 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1250 55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED

Randy Kinder Excavating, Inc. $23.45 $54,404.00 Federal Constructors, Inc. $13.00 $30,160.00 Steve Beam Construction, Inc. $14.52 $33,686.40 Mobley Contractors, Inc. $20.43 $47,397.60 Engineer's Estimate 2,320 LB $14.00 $32,480.00

A1300 55504-0000 PRE-FABRICATED STEEL BRIDGE (SINGLE SPAN MODULAR STEEL PEDESTRIAN BRIDGE)

Randy Kinder Excavating, Inc. Lump Sum $374,825.00 Federal Constructors, Inc. Lump Sum $431,900.00 Steve Beam Construction, Inc. Lump Sum $700,000.00 Mobley Contractors, Inc. Lump Sum $751,461.18 Engineer's Estimate ALL LPSM Lump Sum $290,000.00

A1350 55601-0900 BRIDGE RAILING, STEEL (BRIDGE)

Randy Kinder Excavating, Inc. $244.00 $8,784.00 Federal Constructors, Inc. $110.00 $3,960.00 Steve Beam Construction, Inc. $600.00 $21,600.00 Mobley Contractors, Inc. $706.11 $25,419.96 Engineer's Estimate 36 LNFT $200.00 $7,200.00

A1400 55601-0900 BRIDGE RAILING, STEEL (OBSERVATION DECK)

Randy Kinder Excavating, Inc. $146.00 $4,672.00 Federal Constructors, Inc. $110.00 $3,520.00 Steve Beam Construction, Inc. $600.00 $19,200.00 Mobley Contractors, Inc. $1,452.95 $46,494.40 Engineer's Estimate 32 LNFT $50.00 $1,600.00

A1450 55701-3000 STRUCTURAL TIMBER AND LUMBER, COMPOSITE

Randy Kinder Excavating, Inc. $21,575.00 $2,804.75 Federal Constructors, Inc. $46,000.00 $5,980.00 Steve Beam Construction, Inc. $25,352.25 $3,295.79 Mobley Contractors, Inc. $85,273.75 $11,085.59 Engineer's Estimate 0.13 MFBM $15,000.00 $1,950.00

A1500 58202-0000 HELICAL PILE, IN PLACE (Observation Decks)

Randy Kinder Excavating, Inc. $3,605.00 $28,840.00 Federal Constructors, Inc. $1,700.00 $13,600.00 Steve Beam Construction, Inc. $4,330.00 $34,640.00 Mobley Contractors, Inc. $2,315.78 $18,526.24 Engineer's Estimate 8 EACH $4,000.00 $32,000.00

7 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1550 58202-0000 HELICAL PILE, IN PLACE (Bridge)

Randy Kinder Excavating, Inc. $10,275.00 $102,750.00 Federal Constructors, Inc. $1,700.00 $17,000.00 Steve Beam Construction, Inc. $6,657.00 $66,570.00 Mobley Contractors, Inc. $4,998.39 $49,983.90 Engineer's Estimate 10 EACH $5,000.00 $50,000.00

A1600 60101-0000 CONCRETE

Randy Kinder Excavating, Inc. $828.50 $6,628.00 Federal Constructors, Inc. $900.00 $7,200.00 Steve Beam Construction, Inc. $1,700.00 $13,600.00 Mobley Contractors, Inc. $2,601.40 $20,811.20 Engineer's Estimate 8 CUYD $2,000.00 $16,000.00

A1650 60801-0400 PAVED WATERWAY, TYPE 4

Randy Kinder Excavating, Inc. $92.00 $1,840.00 Federal Constructors, Inc. $210.00 $4,200.00 Steve Beam Construction, Inc. $181.00 $3,620.00 Mobley Contractors, Inc. $125.00 $2,500.00 Engineer's Estimate 20 SQYD $300.00 $6,000.00

A1700 62201-0150 DUMP TRUCK, 7 CUBIC YARD MINIMUM CAPACITY

Randy Kinder Excavating, Inc. $111.00 $2,220.00 Federal Constructors, Inc. $120.00 $2,400.00 Steve Beam Construction, Inc. $114.00 $2,280.00 Mobley Contractors, Inc. $159.23 $3,184.60 Engineer's Estimate 20 HOUR $120.00 $2,400.00

A1750 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH

Randy Kinder Excavating, Inc. $91.00 $1,820.00 Federal Constructors, Inc. $100.00 $2,000.00 Steve Beam Construction, Inc. $104.00 $2,080.00 Mobley Contractors, Inc. $45.71 $914.20 Engineer's Estimate 20 HOUR $150.00 $3,000.00

A1800 62301-0000 GENERAL LABOR

Randy Kinder Excavating, Inc. $49.00 $1,960.00 Federal Constructors, Inc. $52.00 $2,080.00 Steve Beam Construction, Inc. $100.00 $4,000.00 Mobley Contractors, Inc. $102.95 $4,118.00 Engineer's Estimate 40 HOUR $30.00 $1,200.00

8 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1850 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Randy Kinder Excavating, Inc. $205.60 $4,112.00 Federal Constructors, Inc. $165.00 $3,300.00 Steve Beam Construction, Inc. $160.00 $3,200.00 Mobley Contractors, Inc. $98.38 $1,967.60 Engineer's Estimate 20 HOUR $125.00 $2,500.00

A1900 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Randy Kinder Excavating, Inc. $275.00 $5,500.00 Federal Constructors, Inc. $180.00 $3,600.00 Steve Beam Construction, Inc. $198.00 $3,960.00 Mobley Contractors, Inc. $1,027.87 $20,557.40 Engineer's Estimate 20 HOUR $180.00 $3,600.00

A1950 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGIST)

Randy Kinder Excavating, Inc. Lump Sum $3,290.00 Federal Constructors, Inc. Lump Sum $7,200.00 Steve Beam Construction, Inc. Lump Sum $3,600.00 Mobley Contractors, Inc. Lump Sum $1,875.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

A2000 62511-2000 SEEDING, HYDRAULIC METHOD

Randy Kinder Excavating, Inc. $0.81 $4,050.00 Federal Constructors, Inc. $1.60 $8,000.00 Steve Beam Construction, Inc. $0.54 $2,700.00 Mobley Contractors, Inc. $1.72 $8,600.00 Engineer's Estimate 5,000 SQYD $1.00 $5,000.00

A2050 62516-2000 MULCHING, HYDRAULIC METHOD

Randy Kinder Excavating, Inc. $0.81 $4,050.00 Federal Constructors, Inc. $0.85 $4,250.00 Steve Beam Construction, Inc. $0.54 $2,700.00 Mobley Contractors, Inc. $1.72 $8,600.00 Engineer's Estimate 5,000 SQYD $1.00 $5,000.00

A2100 63501-0000 TEMPORARY TRAFFIC CONTROL

Randy Kinder Excavating, Inc. Lump Sum $6,575.00 Federal Constructors, Inc. Lump Sum $13,900.00 Steve Beam Construction, Inc. Lump Sum $5,550.00 Mobley Contractors, Inc. Lump Sum $33,231.31 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

9 out of 9Source Selection Information - See FAR 2.101 & 3.104

Project No: OK ERFO SEQU T500(1)

Project Name: Horton Slough Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A2150 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE

Randy Kinder Excavating, Inc. $4.00 $800.00 Federal Constructors, Inc. $9.00 $1,800.00 Steve Beam Construction, Inc. $9.80 $1,960.00 Mobley Contractors, Inc. $12.50 $2,500.00 Engineer's Estimate 200 LNFT $5.00 $1,000.00

A2200 64620-0000 REMOVE AND RESET (OBSERVATION DECK)

Randy Kinder Excavating, Inc. $3,270.00 $3,270.00 Federal Constructors, Inc. $26,300.00 $26,300.00 Steve Beam Construction, Inc. $7,118.00 $7,118.00 Mobley Contractors, Inc. $28,412.69 $28,412.69 Engineer's Estimate 1 EACH $5,000.00 $5,000.00

Total Schedule - All Items

Randy Kinder Excavating, Inc. $1,198,000.75 Federal Constructors, Inc. $1,324,920.00 Steve Beam Construction, Inc. $1,429,753.79 Mobley Contractors, Inc. $2,397,864.92 Engineer's Estimate $990,000.00