Amendment A003 .pdf
PDF 827 KB Posted
- Attached to
- OK ERFO SEQU T500(1)Horton Slough Trail
- Solicitation number
- 6982AF21B000012
About this file
This document provides details for a federal contract solicitation to perform construction improvements on the Horton Slough Trail located in the Sequoyah National Wildlife Refuge in Oklahoma. The solicitation is seeking bids for repairs to three sites damaged in 2019 flooding, including clearing and grubbing, pedestrian bridge construction, trail construction, observation deck construction, and pavement patching. Significant line items include 250 cubic yards of embankment construction, 425 cubic yards of riprap, 120 tons of asphalt concrete pavement, 30 cubic yards of structural concrete, 2150 pounds of structural steel, one pre-fabricated steel bridge, and 18 helical piles installed. The estimated total cost of the project is between $1,000,000 to $1,500,000. The solicitation number is 6982AF21B000012 and was issued by the Department of Transportation Federal Highway Administration to perform the work. The notice to proceed will be issued before commencement of any work and the contract completion date is December 17, 2021.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E-12
OK ERFO SEQU T500(1)
Horton Slough Trail Limit operations according to Subsection 107.10(e) and Section 156.
Limit operations as follows:
(a) Construction access at Horton Slough trail is allowed along existing paved trail for smaller construction vehicles (ATV, skid steer, etc.) when the trail is closed to the public.
For larger-sized vehicles, use the proposed access routes as shown in the plans. Submit construction access plans to CO for approval prior to using existing paved trail or disturbing ground at proposed access routes. See Section 156.07 for closure details.
(b) Do not begin ground disturbing activities until August 16, 2021.
Perform no work except to maintain traffic control devices, erosion control devices, the roadway driving surface, and to control dust 5:00 pm Friday to 6:00 am Monday and during the listed Federal holidays and surrounding days as shown in Table 108-2.
Table 108-2 Federal Holidays and Surrounding Days
Federal Holiday
Time Remarks
Memorial Day 12:00 Noon Friday to 6:00 am Tuesday
Independence Day
12:00 Noon July 3 to 6:00 am July 6
If July 4 falls on a weekend, Friday, or Monday, do not work the weekend or July 5th.
Labor Day 12:00 Noon Friday to 6:00 am Tuesday
Thanksgiving 12:00 Noon
Wednesday to 6:00 am Monday
Christmas / New Year’s
12:00 Noon December 23 to
6:00 am January 2
If December 23 or January 1 falls on a Monday, do not work the adjacent weekend and do not work on December 23. If January 1 falls on a Friday, do not work the weekend.
Schedule at least 2 non-work days out of every 14 calendar days. The selected non-work days do not need to be consecutive, but they must be scheduled. Notify the CO at least 2 weeks before changing the scheduled days off.
The CO may grant written approval for exemptions to scheduled days off for specific project operations and for periods of limited duration.
Add the following:
The CO will issue a Notice to Proceed before commencement of any work. The contract completion date is December 17, 2021.
A003 06/03/2021