QnA 5.20.21.pdf

PDF 147 KB Posted

Attached to
AZ FLAP 202(2) Red Cloud Mine Road Federal contract opportunity
Solicitation number
6982AF21B000007
Issued by
Department of Transportation Federal Highway Administration

About this file

This document contains questions and answers from a pre-bid meeting for a federal transportation contract. The contract is for construction of approximately one mile of new paved road leading to a national wildlife refuge in Yuma County, Arizona. Work includes excavation, embankment, paving, and culverts. Bidders must be registered in SAM.gov and all required permits are included in the solicitation. CAD files and survey control points will only be provided to the selected contractor. The completion date is January 2022 according to the provided schedule. Excess excavated material must be wasted onsite as specified.

View the file

Other files for this federal contract opportunity

Other files attached to AZ FLAP 202(2) Red Cloud Mine Road, newest first.
File Type Posted
Bid Tabulation AZ FLAP 202(2) Red Cloud Mine Road.pdf PDF
Bid Opening Summary AZ FLAP 202(2) Red Cloud MIne Road.pdf PDF
A002.pdf PDF
QnA 6.3.21.pdf PDF
QnA 5.13.21.pdf PDF
A001 Red Cloud Mine Road.pdf PDF
QnA 5.6.21.pdf PDF
QnA 4.27.21.pdf PDF
FP-14.pdf PDF
AZ FLAP 202(1)_Final Hydraulics Memo.pdf PDF
6982AF21B000007.pdf PDF
AZ FLAP 202(2)_Red Cloud Mine Road_IFB Sealed Plans.pdf PDF
AZ FLAP 202(1)_Geotech and Pavements Report.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for AZ FLAP 202(2) Red Cloud Mine Road

May 20, 2021

Questions Answers 1 What are the necessary licenses & permits associated with procuring this opportunity?

• You must be registered in SAM.gov (see sheet A-ii of the Invitation for

Bid (IFB)).

• All required permits are covered in Section 107 of the FP-14 and SCR’s.

See Sheet E-10 thru E-18. Permits are also attached in the Appendices of the IFB (see the Table of Contents of the IFB).

2 Can the CAD file and survey control points be provided now to compare a quantity take-off to the Bid Schedule?

• CAD files and survey control points will only be provided upon award to the selected contractor.

3 What is the estimated project duration? • The completion date is stated in SCR’s Subsection 108.01 on page E-20 of the IFB.

• The anticipated Notice to Proceed date is stated in clause 52.211-10 on page C-3 of the IFB.

4 For bid schedule line item A0160 Roadway excavation for 17,620 CY, is it an option to stockpile excess materials on site or does it need to be hauled away?

• Excess material should be wasted in the obliteration segment of the project per SCR sections 204 and 211.

• Staging/storage areas for use during construction are listed in Section 105 of the SCR’s.