This document contains questions and answers regarding a solicitation for the AZ FTNP CAGR 10(2) Entrance Road project. The project provides 3R rehabilitation treatment for 0.65 miles of entrance roadway and 0.12 miles of an administration road at the Casa Grande National Monument Park. Work includes full depth reclamation of existing pavement, asphalt concrete paving totaling approximately 13,100 tons, roadway aggregate totaling 100 tons, and traffic control. A stormwater pollution prevention plan is required. The anticipated award date is within two weeks of the bid opening, with a notice to proceed according to the contract clauses. The completion date is February 24, 2021 and sufficient time has been allotted between notice to proceed and completion while accounting for federal holidays. The government will identify the construction operations engineer and project engineer at time of award.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for AZ FTNP CAGR 10(2), Entrance Road
6982AF20B000035
October 9, 2020
Questions Answers 1 See Note to Bidders in Answer section. NOTE TO BIDDERS: U.S. Mailing providers such as: FedEx; UPS and USPS, have been experiencing a large volume due to COVID-
19. Please plan the mailing of your bids accordingly. Late bids will not be considered and processed in accordance with FAR provision 52.214-7.
2 Can you guide me to whom I could schedule a site visit? Scheduling is not necessary, you can visit the site during the park’s operational hours.
3 Could you clarify the below Line Items, what are these items, and where and how will they be utilized?
A0170 Blotter. Sheet B1 | 25 Tons X0140 Blotter. Sheet B3 | 10 Tons
The Blotter will be used on both Schedule A and Option X. If the prime hasn’t fully cured out before traffic is allowed travel on the prime surface will require Blotter material. The PE will make the decision whether to use the Blotter or not on the primed surface during construction.
4 Does the project need an (SWPP) Storm Water Pollution Prevention Plan?
Yes, refer to section 107.10 of the SCRs.
5 • Section 108.01 of the SCRs states that the contract completion date is February 24, 2021.
o What is the anticipated Award date?
o What is the anticipated NTP date?
o Has the Government allowed a reasonable amount of time for construction?
o Has the Government considered the Federal
Holidays and Surrounding Days in the completion time?
• The Award date is typically within two weeks of the Bid Opening.
This is tentative.
• For the NTP refer to the clauses section of the IFB, 52.211-10 and Section 108 of the SCRs.
• There is a reasonable amount of time to complete this project between the NTP and completion date.
• Refer to Section 108 for information regarding Holidays.
6 • Who is designated as the Construction Operations Engineer (COE)?
The Government will notify the awardee of any project personnel at time of award.
7 • Who is designated as the Project Engineer (PE)?
The Government will notify the awardee of any project personnel at time of award.