QnA 10.23.20 CAGR.pdf
PDF 544 KB Posted
- Attached to
- AZ FTNP CAGR 10(2) Entrance Road
- Solicitation number
- 6982AF20B000035
About this file
This document contains questions and answers related to a federal solicitation for road rehabilitation work at Casa Grande National Monument Park in Pinal County, Arizona. The solicitation seeks bids to pulverize and repave approximately 0.65 miles of entrance road and 0.12 miles of an administration road with 4 inches of asphalt. Significant line items include 10,000 tons of hot asphalt concrete paving for the entrance road and 3,100 tons for the administration road, as well as roadway aggregate. The pre-bid questions provide clarification on issues such as the availability of site visits, use of blotter material, stormwater permitting requirements, construction schedule and completion date, project personnel, surveying requirements, as-built drawings, temporary road markings, and the option to propose alternative surface treatments. The anticipated award date is within two weeks of the October 23, 2020 bid opening, with the contract completion date of February 24, 2021. The solicitation is a total small business set-aside being conducted by the Federal Highway Administration.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for AZ FTNP CAGR 10(2), Entrance Road
6982AF20B000035
October 13, 2020
Questions Answers 1 See Note to Bidders in Answer section. NOTE TO BIDDERS: U.S. Mailing providers such as: FedEx; UPS and USPS, have been experiencing a large volume due to COVID-
19. Please plan the mailing of your bids accordingly. Late bids will not be considered and processed in accordance with FAR provision 52.214-7.
2 Can you guide me to whom I could schedule a site visit? Scheduling is not necessary, you can visit the site during the park’s operational hours.
3 Could you clarify the below Line Items, what are these items, and where and how will they be utilized?
A0170 Blotter. Sheet B1 | 25 Tons X0140 Blotter. Sheet B3 | 10 Tons
The Blotter will be used on both Schedule A and Option X. If the prime hasn’t fully cured out before traffic is allowed travel on the prime surface will require Blotter material. The PE will make the decision whether to use the Blotter or not on the primed surface during construction.
4 Does the project need an (SWPP) Storm Water Pollution Prevention Plan?
Yes, refer to section 107.10 of the SCRs.
5 Section 108.01 of the SCRs states that the contract completion date is February 24, 2021.
o What is the anticipated Award date?
o What is the anticipated NTP date?
o Has the Government allowed a reasonable amount of time for construction?
o Has the Government considered the Federal
Holidays and Surrounding Days in the completion time?
The Award date is typically within two weeks of the Bid Opening.
This is tentative.
For the NTP refer to the clauses section of the IFB, 52.211-10 and Section 108 of the SCRs.
There is a reasonable amount of time to complete this project between the NTP and completion date.
Refer to Section 108 for information regarding Holidays.
6 Who is designated as the Construction Operations Engineer (COE)?
The Government will notify the awardee of any project personnel at time of award.
7 Who is designated as the Project Engineer (PE)?
The Government will notify the awardee of any project personnel at time of award.
8 The paving depth is 3”, Ai is in error. This is corrected in Amendment A001
In the notice to bidders document A-i Under Project Overview. Paragraph:
The rehabilitation project consists of pulverizing the existing asphalt for additional base and repaving with approximately 4” of asphalt. The asphalt thickness is different than the plans on Sheets A5 and A6. Which of the asphalt thicknesses does the government want to utilize, the 4 inches or the 3 inches?
9 Is there water on-site to use for the water trucks during construction?
No water is not available at the Park.
10 Can we get an electronic copy of the drawings for the surveyors? Electronic copy of the plans will be sent to the contractor after award of the contract.
11 Is there a construction phase plan? Contractor will submit a construction phasing plan per Special Contract Requirements (SCR) 108 and 156 for PE approval.
12 Is the entrance road going to be closed during the reconstruction of the entrance road?
No, the entrance road will not be closed. See SCRs 108 and 156, public travel through the project work area.
13 Regarding the Surveying; Does it need to be a tie-in to a specific horizontal/vertical datum.
The project will be built using local control to tolerance the roadway before paving. See the SCRs, section 152
14 Are As-Build Drawing required, if necessary, does an AutoCAD drawing suffice, or do printed copies needed? If Printed Copies are required it, what size, and how many copies?
Electronic As-Builts are required
15 Does Temporary Road Marking necessary Yes, the Temporary Road Markings are necessary.
16 Can the Asphalt Paving be performed in a single layer per the specified 3" depth? Asphalt Concrete Pavement Type 1, this task concerns that paving 1.5 inches (compacted) may compromise material layers when the asphalt compactors roll the asphalt material, producing what is knowing in the industry Asphalt Checking or Roller Checking. (Checking; can be defined as short transverse cracks, usually, 1 to 4 inches in length and 1 to 3 inches apart, which occur in the asphalt concrete mat) Other factors can contribute to Asphalt Checking, such as the deflection of the pavement structure under the compaction equipment, deficiency in the asphalt mix design, the asphalt mix tends to shove by the roller instead of tucking under the drum of the compacting equipment, etc.) Another concern is that the first asphalt mat layer of 1.5 inches compacted may be compromised by the Asphalt Paving Machine's weight and the Asphalt Delivering Trucks weight.
DAP's recommendation is to place the asphalt mat as a single 3" inches compacted layer, as a single lane from Center Line to the edge of the road.
The Asphalt Paving cannot be performed in a single layer; the plans call for two equal lifts of asphalt be placed. Refer to the typical section.
Provide an asphalt mix design that will meet or exceed project specifications
October 21, 2020
17 We are concerned that micro-surfacing may not be the most cost-effective approach to the parking area. The existing surface of the visitor parking area displays obvious signs of pavement fatigue and distress that is at least as bad or worse than the Entrance Road. Has the government considered complete pavement replacement as an option in lieu of micro-surfacing?
The plans state the visitor center parking lot will be micro surfaced per the plans and specifications. The winning contractor can also propose VALUE Engineering proposal for consideration to CFL.
18 Regarding Section 108.01 (a) is working at night mandatory for pulverizing and paving operations?
No it is not mandatory but the Park will be closed to the public for night operations.
October 23, 2020
19 Based on our review of the subject Invitation of Bid, it is our understanding that there is no minimum percentage self-performance requirement for the prime (small business) on this project. Please confirm.
Confirmed. FAR Clause 52.236-1 is not included in this solicitation.