Bid Opening Summary AZ FTNP CAGR 10(2) Entrance Road.pdf

PDF 185 KB Posted

Attached to
AZ FTNP CAGR 10(2) Entrance Road
Solicitation number
6982AF20B000035
Issued by

About this file

This document contains a bid opening summary for a federal construction contract opportunity. The contract is for rehabilitation of 0.65 miles of entrance roadway and 0.12 miles of an administration road at Casa Grande National Monument in Pinal County, Arizona. Work includes pulverizing the existing asphalt roadway, adding 4 inches of new asphalt, and addressing grading of side slopes. Schedule A covers the entrance roadwork for a bid range of $467,920.10 to $995,730.00. Option X covers the administration road for a bid range of $104,455.00 to $279,990.00. The total combined bid range was $609,514.45 to $1,275,720.00. The engineer's estimate was $1,030,000.00. The soliciting agency is the Department of Transportation Federal Highway Administration. The procurement is a total small business set-aside.

View the file

Other files

File Type Posted
Bid Tabs - AZ FTNP CAGR 10(2).pdf PDF
QnA 10.29.20 CAGR.pdf PDF
Interested Vendor List 10 27 2020.pdf PDF
QnA 10.23.20 CAGR.pdf PDF
QnA 10.21.20 CAGR.pdf PDF
QnA 10.13.2020 CAGR.pdf PDF
A001 20B000035.pdf PDF
QnA 10.9.2020 CAGR.pdf PDF
FP-14_Eng.pdf PDF
AZ FTNP CAGR10(2)_Plans.pdf PDF
6982AF20B000035.pdf PDF
AZ FTNP CAGR 10(2) Plan Title sheet signed.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Opening Summary

Project Name: Entrance Road Project Number: AZ FTNP CAGR 10(2)

Bid Opening Date: 11/3/2020 Time: 2:00 p.m.

Bid Opening Location: Lakewood, CO Bid Opening Officer: Jorey Deml

Amendments: (1) 10/13/2020

Bidder’s Name Bid Total

Hauser Engineering Group Glendale, AZ

A: $390,684.80 X: $104,455.00 Total: $495,139.80

Genesis Design and Development Rio Rancho, NM

A: $995,730.00 X: $279,990.00 Total: $1,275,720.00

SWP Contracting & Paving Glendale, AZ

A: $608,540.00 X: $181,200.00 Total: $789,740.00

Meridian Engineering Company Tucson, AZ

A: $589,829.00 X: $135,050.00 Total: $724,879.00

Crowley Holdings New Orleans, LA

A: $467,920.10 X: $141,594.35 Total: $609,514.45

Arrow Indian Contractors Tempe, AZ

A: $508,284.64 X: $170,705.31 Total: $678,989.95

Standard Construction Company Avondale, AZ

A: $602,324.00 X: $218,156.00 Total: $820,480.00

Engineer’s Estimate

A: $800,000.00 X: $230,000.00 Total: $1,030,000.00

All bids subject to verification