OAKZ RTR SOW 07272024 FINAL.pdf
PDF 698 KB Posted
- Attached to
- Roof Repair and Refurbish in Oakland, CA
- Solicitation number
- 697DCK-24-R-00463
About this file
This document is a Statement of Work (SOW) for roof repairs and refurbishment at the OAKZ RTR building located in Oakland, California. The SOW outlines the scope of work, which includes removing and disposing of the existing HVAC system, patching and repairing duct and pipe openings, and installing new roofing materials such as Duro-Last EPS "Fan Fold Board" and a 60 mil white Duro-Last membrane. The work must be completed within 21 calendar days, with restrictions on work hours and the requirement to coordinate with the Contracting Officer Representative (COR). The contractor must submit various documents, such as a project schedule, health and safety plan, and material specifications. The SOW also includes details on site restrictions, safety requirements, inspections, and cleanup.
The related federal contract opportunity is for roof repair and refurbishment at three locations around the Oakland International Airport, with an estimated construction magnitude between $450,000 and $600,000. A one-time site visit is scheduled for July 18, 2024, and offers are due by July 30, 2024. The solicitation is being issued by the Department of Transportation Federal Aviation Administration Enroute Terminal Contracts division.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
FAA WESTERN SERVICE AREAS - ES
STATEMENT OF WORK
ROOF REPAIRS / REFURBISHMENT
OAKZ RTR
1029 GRUMMAN ST. OAKLAND, CA
JULY2024
37º 44’ 27” N 122º 13’ 6” W
2 | P a g e
1-0 GENERAL
Provide all necessary labor, materials, equipment, transportation, and other services required to repair and refurbish the roof at the OAKZ RTR building located at 1029 Grumman Street in Oakland California.
The roof is comprised of 3 separated structures (Environmental Section, Telco/Equipment Room, and Operation Section) but connected buildings approximately 20,000 SF, which must be field verified. The roof surfaces is a flat with low slop structure and is an asphalt based roofing system with Styrene- Butadiene- System (SBS) Roofing Membrane and or Modified Bitumen/Asphalt Roofing either torch- down or mopped on the asphalt which has tear and wear, cracks, and bubbling on the roof surface, and on parapets corner. The parapet is approximately 18” high with sheet metal wrapping.
The roof over environmental section includes an open mechanical equipment, piping, and ducting well, and roof over Telco/Equipment room includes an A/C system, and over operation section contains antenna poles.
1-2 SCOPE OF WORK
Contractor must provide all necessary labor, materials, equipment and other services needed to repair and refurbish the roof surfaces as described below: No conduits directly running under the existing steel deck.
• Remove and dispose the entire AC system located on roof of Telco/Equipment roof. Patch and repair all ducts and pipe oenings,
• Remove and dispose of all walking pads.
• Prior to start of the work all rubbish, waste shall be removed, repair the damaged areas as needed and leave the surface clean and in proper condition for resurfacing the roof.
• Inspect roof for any wet insulation and notify COR if found.
• Provide and install one layer of Duro-Last EPS ½” Fan Fold Board (or equal) mechanically attached.
• Provide and install one layer of Single-Ply 60 mil white Duro Last (or equal) membrane over the roof surface and fully adhered.
• Provide and install one layer of Duro-Last 60 mil over entire parapets extended under existing SS copping. Use a separate sheet for the parapet walls fully adhered.
• Provide and install all curb, pipe and antenna base boot flashings.
• Provide and install all other accessories required by manufacturer for complete watertight roofing system.
3 | P a g e
• Provide and install walking pad.
• Remove all trash and debris from the roof and dispose per requirements of state and local authorities.
Note :
In lieu of installing “Duro-Last EPS ½”Fan Fold Board and membrane”, apply 1 coat of Duro-Shield Silicon coating (or Equal) to Open Mechanical Equipment well on the roof of Environmental section.
1-3 TECHNICAL REQUIREMENTS.
All works under this contract shall meet the manufacturer’s requirements for storage, handling and installation of the products used in the project, and shall be in accordance with the IBC,IRC, NAICS rules and regulations.
1-4 SUBMITTALS
The contractor shall provide to COR 2 weeks after the award of contract the following documents.
1. Project Health & Safety Plan.
2. Project Schedule
3. Emergency contact list
4. Brochure, specification for all material used for the project.
5. MSDS for adhesive and other chemicals.
1-5 SITE RESTRICTIONS
The contractor is hereby notified that the RTR building resides electronics and electrical equipment systems and devices in support of National Air Space (NAS) and therefore the contractor workinginthis project must avoid disturbing the normal operation of the facility. Therefore, all activities must be coordinated with the Contracting Officer Representative (COR) –and shall be performed under his/hers supervision al all time.
1-6 SAFETY REQUIREMENTS
The contractor is solely responsible for the safety and welfare of workmen on the project and the public around the construction site. All workers working around the edge of the roof and parapet shall be equipped with fall protection apparatus – and shall take precautions to adequately safeguard the conditions of all persons on or near the site. Comply with the regulations of the Occupational Safety and Health Standards (OSHA), 29 CFR Part 1926. If the COR deems that the Contractor is not safe, he has the right to stop all work until the Contractor corrects the safety violation. Contractor shall submit a Health and Safety Plan for this project. The Health and Safety Plan shall identify the competent safety individual for the project to monitor safety and identify safety hazards. Contractor
4 | P a g e shall hold frequent safety tailgate meetings to identify and discuss safety measures for scheduled work.
All existing equipment and materials removed from the project area shall become property of the contractor which must be remove from the site immediately after removal. Contractor shall adhere to local government disposal regulations.
The Contractor and his Subcontractors shall maintain the job site in a neat and orderly condition;
this includes the daily removal of rubbish, waste and tools, equipment, and materials not required for the workin progress.
1-7 PERFORMANCE TIME
Work shall start no more than 3 weeks after the award and be done diligently and completed no later than 21 calendar days. The working hours should be scheduled from 7:30 to 5:00 PM Monday Through Friday. No work shall be schedule for the weekends and official holidays. However, in order of inclement weather or to expedite the project work may be allowed on weekend and longer hours on weekdays with approval of the COR in advance with approved by the COR – and with no additional cost to government.
The contractor shall confine operations, activities, material storage and employee parking within the area approve by the COR.
1-8 SCHEDULING
The Contractor shall submit a project schedule to the COR 3 weeks after award. The schedule shall be in the format of a Microsoft project or similar format.
1-9 PROJECT SUPERVISION
The Contractor shall always have a designated project superintendent at the project site during the course of work.
1-10 AVAILABLIBILITY OF UTILITIES
Limited electricity and water are available to the Contractor at the site. But a temporary sanitary shall be provided by contractor with proper ventilation and enclosure for use of all workers. Such a facility shall be kept clean and properly maintained and meet the requirements of state and local authorities.
The location must be coordinated by the COR.
1-11 INSPECTIONS
The COR will inspect all work in progress up to completion and final Contractor’s Acceptance Inspection (CAI) including all materials, tools, and equipment. Such inspection may extend to all or a part of the work for the preparation, and materials to be used.
When the Contractor or subcontractors are notified by the COR of any non-compliance with the
5 | P a g e provisions of the contract and the action(s) to be taken, the Contractor shall correct the unsafe or unhealthy condition. The CO may stop the work with a “stop work order” if the Contractor fails to comply promptly with all or any part of the work being performed. When satisfactory corrective action has been taken to correct the unsafe and unhealthy condition, the Contractor may resume work when approved by the CO. The Contractor shall not be allowed any extension of time or compensation for damages by reason of or in connection with such work stoppage.
1-12 PROTECTION OF EXISTING FACILITY
The Contractor shall take all precautions necessary to protect the existing facilities, equipment, buildings, vegetation, etc., during construction. Any areas damaged by the Contractor or subcontractors, shall be repaired or replaced to their original conditions by the Contractor at no additional cost to the government. Repairs shall be approved by the COR and shall match to original finish. The Contractor shall provide all temporary covers, enclosures, barricades, etc., required to protect the existing facilities.
1-13 JOB WALK
Not used,\
1-14 PRE-CONSTRUCTION MEET
The CO will schedule a pre-construction meeting after Notice of Award. The required attendance should include contractor, subcontractor and the superintendent who supervise the project. The purpose of this meeting is to review the submittal provided by the contractor and review of the plan for executing the project.
1-15 CLEAN UP
Immediately before the final inspection, the surrounding areas shall be thoroughly cleaned and all debris, rubbish shall be removed from the site and dispose of according to local regulations
1-16 PICTURES
6 | P a g e
REMOVE AND DISPOSE AC SYSTEM ON TELCO/EQUIPMENT ROOF
ANOTHER VIEW OF AC SYSRWM ON TELCO/EQUIPMENT ROOF
DOCUMENT END
| 1-2 SCOPE OF WORK |
| 1-4 SUBMITTALS |
| 1-5 SITE RESTRICTIONS |
| 1-6 SAFETY REQUIREMENTS |
| 1-7 PERFORMANCE TIME |
| 1-8 SCHEDULING |
| 1-9 PROJECT SUPERVISION |
| 1-10 AVAILABLIBILITY OF UTILITIES |
| 1-11 INSPECTIONS |
| 1-12 PROTECTION OF EXISTING FACILITY |
| 1-13 JOB WALK |
| 1-14 PRE-CONSTRUCTION MEET |
| 1-15 CLEAN UP |