697DCK-22-R-00531_Amendment 01.pdf

PDF 88 KB Posted

Attached to
DFWA and DFWB Raised Floor Replacement Federal contract opportunity
Solicitation number
697DCK-22-R-00531
Issued by
Department of Transportation Federal Aviation Administration Southwestern Region

About this file

This is an amendment to a solicitation for a federal contract. The solicitation is seeking to replace the raised flooring in the air traffic control towers at Dallas-Fort Worth Airport. The amendment provides an updated project milestone schedule, shifting the site visit, question deadline, and proposal due date to later dates. It also clarifies the period of performance in the commencement, prosecution and completion of work clause, changing it from 80 to 120 days. The solicitation is seeking proposals to remove and replace the existing raised floor systems and carpet tile, install proper grounding, and perform other work as defined in the contract documents to modernize the raised flooring in the air traffic control towers at DFW Airport. Proposals are due by October 21, 2022.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 2

0001 08/22/2022

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

10101 HILLWOOD PARKWAY

FORT WORTH TX 76177-1524

AAQ520FTW-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

697DCK-22-R-00531

1 copies to the issuing office.

08/22/2022

(x)

LIST OF CHANGES:

Purpose of modification to Solicitation 697DCK-22-R-00531 is to provide an updated milestone plan and provide clarification on clause 3.2.2.3-71 as described below:

FIRST: The following updated milestone plan is hereby updated and incorporated by the following:

FROM:

MILESTONES:

SITE VISIT: September 12th, 2022.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Joni L. Haynes

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

697DCK-22-R-00531/0001

QUESTIONS DUE: September 16th, 2022 at 05:00PM CT

RFP DUE DATE: September 30th, 2022 at 05:00PM CT

TO:

MILESTONES:

SITE VISIT: September 28, 2022

QUESTIONS DUE: October 5th, 2022 at 05:00PM CT

RFP DUE DATE: October 21st, 2022 at 05:00PM CT

SECOND: The date found in AMS Clause 3.2.2.3-71

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(OCT 2021) is hereby corrected to match block 7 for the number of days for completion:

FROM: 80 days

TO: 120 days

THIRD: All other terms and conditions remain unchanged and in full effect.

File details come from the government source that posted it. Updated .