- UPDATE - Bean Ridge Tower Remediation - RFI / Responses and ADDITIONAL PHOTOS Federal contract opportunity
- Solicitation number
- 6973GH-26-R-00074
About this file
This is a Solicitation, Offer, and Award form (SF 1449) for a construction alteration or repair contract issued by the FAA Aeronautical Center's AAQ-710 Logistics Center Acquisition office on February 17, 2026. The solicitation number is 6973GH-26-R-00074/0001, and sealed offers are due on February 24, 2026 at 1700 hours local time to the FAA Aeronautical Center, PO Box 25082, Building 014-AHQ, Room 233A, Oklahoma City, OK 73125. The primary point of contact is Edward Wright (405-954-7861). The work required involves Bean Ridge Tower Remediation for the U.S. Forest Service Region 1, as detailed in the Statement of Work (SOW) provided.
The contract consists of repairs and site-specific requirements including installation of four Rohn 55 guy bracket assemblies, removal and termination of transmission lines, and replacement of existing barbed wire on the compound perimeter fence. A modification to the solicitation extended the proposal due date from February 18, 2026 to February 24, 2026 to provide responses to Requests for Information (RFIs) and additional photographs. The contractor must begin performance within zero calendar days of receiving the notice to proceed and complete the work within zero calendar days after receipt. An offer guarantee is not required, and the contractor must furnish any required performance and payment bonds. The contracting officer is Raymond A. Lena. Offers will be accepted for zero calendar days after the date they are due, with the minimum requirement of zero calendar days for Contract Authority acceptance after offers are submitted.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| P1120025.JPG | JPG image | |
| IMG_0762.JPG | JPG image | |
| 6973GH-26-R-00074.pdf | ||
| Bean Ridge Photo Deck. 2.docx | DOCX document | |
| Bean Ridge Photo Deck.docx | DOCX document | |
| SOW - Bean Ridge Tower Remediation - USFS R1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
A. NAME B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder"
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED BID (RFP)
AAQ-710 LOGISTICS CENTER ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ710-AFN
OKLAHOMA CITY OK 73125
Edward Wright 405-954-7861
102/17/2026 7
PURCHASE REQUEST NO.
6973GH-26-R-00074/0001
10. THE CONTRACT AUTHORITY REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
SOW - Bean Ridge Tower Remediation - USFS R1
11. The Contractor shall begin performance within
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award notice to proceed. The performance period is mandatory, negotiable. (See ________________________________________________ .)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and is not required.is, B. An offer guarantee
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers must be publicly opened at that time . Sealed envelopes containing offers shall be marked to show the offeror's name and address. The solicitation number, and the date and time offers are due.
D. Offers providing less than
12B. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in item 12B.)
0 0 calendar days and complete it within ________________ ________________ calendar days after receiving
1 1700
02/24/2026 x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Contract Authority acceptance after the date offers are due will not be considered and will _________________ be rejected.
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Contract Authority in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13D. Failure to insert any number means the offeror accepts the minimum in item 13D.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (MUST BE FULLY COMPLETED BY OFFEROR)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Contract Authority)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Contract Authority solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE 30C. DATE 31B. CONTRACT AUTHORITY 31C. AWARD DATE
BY
2PAGE OF
AAQ-710 LOGISTICS CENTER ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ710-AFN
OKLAHOMA CITY OK 73125
Raymond A. Lena
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
Continued...
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
6973GH-26-R-00074/0001
(A) (B) (C) (D) (E) (F)
Attachments
* SOW - Bean Ridge Tower Remediation - USFS R1
* Bean Ridge Photo Deck
* IMG_0762
* P112002
LIST OF CHANGES:
The purpose of this modification is to provide responses to submitted RFIs and provide additional photos not originally provided. As a result, the RFIs with responses, and additional photos will be provided, and the proposal due date is hereby extended from 18 February 2026 to
24 February 2026.
• SOW Requirement 2.b, Repairs, bullet 5 states:
Install new security wire on the perimeter fence of the compound.
o Can the Government confirm that torque arm assemblies are the preferred solution to this requirement? If not, please confirm if 3-runs of barbed wire across the top of the fence is an acceptable solution?
¿ Replace existing barbed wire at the top of the compound fence with new barbed wire. Picture of existing attached.
• SOW Requirement 2.e, Site Specific Requirements, bullet 1 states: Installation of four guy wire bracket assemblies on tower.
o Question: Can the Government provide additional information on the current brackets such as make/model or provide a product cut sheet?
¿ No brackets are currently installed, and guy wires are wrapped around the tower leg. The requirement is for four new Rohn
55 guy bracket assemblies to be installed.
Picture of existing guy attachment attached.
• SOW Requirement 2.e, bullet 5 states: Remove and trim excess transmission line as required and re-terminate the line.
Continued ...
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
4 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
6973GH-26-R-00074/0001
(A) (B) (C) (D) (E) (F) o Question: Are the current connectors re-usable?
¿ No o If not, can the Government provide the current connector brand model and connector type?
¿ The connector brand model and type is not currently available.
All other terms and conditions remain in full force and effect.