69727621Q000018 GEN RUDDER FY21 DRY DOCK.pdf
PDF 1 MB Posted
- Attached to
- TS GENERAL RUDDER FY21 REFURBUSH/REPAIR DRY DOCK
- Solicitation number
- 69727621Q000018
About this file
This is a solicitation for ship repair and drydocking services. The U.S. Maritime Administration seeks a contractor to perform refurbishment, repair, and drydocking of the training ship T.S. General Rudder from September 10, 2021 to October 31, 2021. Services include hull cleaning and preparation, coating application, inspection of rudders and stern frame, maintenance of the anti-biofouling system, and other work items detailed in the attached statement of work and specifications. The solicitation is set aside for small businesses with a NAICS code of 336611 and size standard of 1,250 employees. Quotes are due by August 17, 2021 and award will be made by September 9, 2021. The contractor must visit the vessel on July 26, 2021 and is encouraged to ask any questions by August 3, 2021. The contractor must perform to regulatory and specification requirements and provide deliverables including reports and records of inspections or testing.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUMIS CHECKED
CODE 18a. PAYMENT WILL BE MADE BY
CODE
FACILITYCODE
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
OFFEROR
697276
NEW ORLEANS LA 70130-3394
500 POYDRAS STREET ROOM 1223
DIVISION OF GULF OPERATIONS
MARITIME ADMINISTRATION
CODE 16. ADMINISTERED BYCODE
X
X
X
336611
SIZE STANDARD:
100.00 % FOR:SET ASIDE:UNRESTRICTED OR697276
RFPIFB
10. THIS ACQUISITION ISCODE
RFQ
14. METHOD OF SOLICITATION
13b. RATING
NAICS:
SMALL BUSINESS
08/17/2021 1500 CT
07/01/2021
504-589-3641Carolyn Quinn (No collect calls)
INFORMATION CALL:
FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME
4. ORDER NUMBER3. AWARD/ 6. SOLICITATION
69727621Q000018
5. SOLICITATION NUMBER
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF
1 126 MAPR61621000313OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
TELEPHONE NO.
17a. CONTRACTOR/
15. DELIVER TO
NEW ORLEANS LA 70130-3394
500 POYDRAS STREET ROOM 1223
DIVISION OF GULF OPERATIONS
9. ISSUED BY
7.
2. CONTRACT NO.
EFFECTIVE DATE
1,250
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
ISSUE DATE
DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
11.
SEE SCHEDULEX
12. DISCOUNT TERMS
THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13a.
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
8(A)
MARITIME ADMINISTRATION
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
TS GENERAL RUDDER FY21 REFURBUSH/REPAIR AND
DRYDOCK
The U.S. Department of Transportation, U.S.
Maritime Administration, New Orleans, LA requires a contractor to dry dock the Training Ship (TS) GENERAL RUDDER. The contractor shall provide all requested supplies and services in accordance with the attached TS GENERAL RUDDER FY21 REFURBUSH/REPAIR AND DRYDOCK SPECIFICATIONS. This will be a firm fixed price award.
(Use Reverse and/or Attach Additional Sheets as Necessary)
HEREIN, IS ACCEPTED AS TO ITEMS:
X
XX
DATED . YOUR OFFER ON SOLICITATION (BLOCK 5),
INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER
ARE
ARE
31c. DATE SIGNED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)
ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL
SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
OFFER
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
ARE NOT ATTACHED.
ARE NOT ATTACHED.
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
30b. NAME AND TITLE OF SIGNER (Type or print)
30a. SIGNATURE OF OFFEROR/CONTRACTOR
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
25. ACCOUNTING AND APPROPRIATION DATA
29. AWARD OF CONTRACT:
REF.
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER
37. CHECK NUMBER
FINALPARTIAL
36. PAYMENT
FINALPARTIAL
35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER33. SHIP NUMBER
COMPLETE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)
42b. RECEIVED AT (Location)
42a. RECEIVED BY (Print)
41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
STANDARD FORM 1449 (REV. 2/2012) BACK
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
Work performed will be subject to a Service
Contract Act Wage Determination applicable to the locale of the awardee's dry dock facility.
Terms and conditions are set forth in the attached documents.
ATTACHMENTS FOR THIS SOLICITATION INCLUDE:
RFQ 69727621Q000018 SF-1449
Solicitation Provisions Clauses
TSGR FY21 DD Repair Specifications
TSGR Quotation Pricing Sheet
Drawings
Period of Performance: 09/10/2021 to 10/31/2021
00001 GENERAL RUDDER - FY21 DRYDOCK PACKAGE
32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
126 2 of
TS GENERAL RUDDER
FY21 – REFURBUSH/REPAIR AND DRYDOCK
SPECIFICATIONS
Intermediate Hull Survey No.: 8
15 June 2021
Prepared by: JON CRAMPTON
U.S. Department of Transportation Maritime Administration - Division of Gulf Operations (DGO)
650 Fannin St. Suite 650 Beaumont, TX 77701
VESSEL PARTICULARS
VESSEL NAME: T/S GENERAL RUDDER
(ex-Kings Pointer)
RADIO CALL SIGN: WTDL
TYPE: Twin Screw; Diesel-
OFFICIAL NUMBER: CG002248
USCG CERTIFICATION: Public Nautical School ship CLASSIFICATION: ABS – AMS, ACCU, Ice Class
ABS CLASS NUMBER: 8502561
IMO NUMBER: 8835451
BUILDER: Tacoma Boat Building Co.
KEEL LAID: 10 January 1983 COMMISSIONED: 29 July 1984 LENGTH OVERALL: 224 Feet 00 Inches BEAM: 43 Feet 00 Inches DESIGN DRAFT: 15 Feet 01 Inches VERT CLEARANCE (Air Draft): 71 Feet 00 Inches DEADWEIGHT: 2,250 Long Tons USCG GROSS TONNAGE: 1,914 Long Tons USCG NET TONNAGE: 574 Long Tons CRUISING SPEED: 10 Knots MAIN ENGINES: Four Caterpillar D398TA: 970 HP MAIN GENERATORS: Four Kato 600KW, 600VAC, 3-Phase PROPULSION MOTORS: Two Gen. Electric, 800HP, 750 VDC BOW THRUSTERS: Harbormaster: 48-Inch Tunnel, 550 HP DIESEL FUEL CAPACITY: 228,615 U.S gallons SALT WATER BALLAST CAP.: 146,642 U.S. gallons FRESH WATER CAP.: 5,099 US gallons
LIST OF REFERENCES
1 33 CFR Parts 1-124 COLREGS (Navigation) 2 46 CFR Part 167 (Public Nautical School Ships) 3 ABS Approved Equipment List 4 ABS Rules for Building and Classing Steel Vessels, Part 1, Classification, Testing and Surveys 5 ABS Rules for Survey after Construction 2018, Part 7 6 ABS Rules Part 1 Rules for building and Classing Steel Vessels (Conditions of Classification) 7 ABS Rules Part 2, Rules for building and Classing Steel Vessels (Materials and Welding) 8 ABS Rules Part 3, Rules for building and Classing Steel Vessels (Hull construction and Equipment)
9 DWG 53711-243-0000225 - SHAFTING ASSY 1,2,& 3)
10 DWG 243-0000224 - Shafting Details - Stern tube and Closure Tube Details, Seals and Bearings Install, and Rope Guards Details. Part (1 of 2)
11 DWG 242-0000224 - Shafting Detail Arrangement Part (2 of 2) 12 DWG 243-000228 - Propulsion System Shafting Alignment Procedure 13 DWG 505-6241614 - List of Sea Valves 14 DWG 114-0000023C - Skeg 15 DWG 561-0000222F - Steering Gear Arrangement & Details 16 DWG 562-0000030 - Rudder & Rudder Trunk Arrangement & Details 17 DWG 633-0000120B - Catholic Protection Schedule 18 DWG 801-0000036 - Guidance Docking Plan (Available On Board) 19 DWG 801-0000155 - Inboard Profile, Inner Bottom
20 DWG 801 5988703 - General Arrangement Above Main Deck
21 DWG 801-5988702 - General Arrangement Main Deck & Below 22 DWG 1355-S62-1-1 - Electrical One Line Diagram (Rev B) 23 Fire and Safety Plans (Available on Board)
24 DWG 835-5988704 - Inboard Profile
25 DWG 835-5988706 - Outboard Profile
26 DWG 111-0000007 - Scantling Profile
27 DWG 5987287-D - Aux Sea Water System
28 DWG 101-0000008 - Scantling Profile C
29 Good Painting Practice, SSPC Painting Manual, The Society for Protective Coatings, Volume 1, 4th Edition
30 IEEE Standard 45 (Guide to Electrical Installations on Shipboard) 31 MARAD Coatings Guidelines (January 2018)
32 NFPA 306, NFPA 312, 29 CFR 1915.12 and 29 CFR 1915.7 (c) or other applicable NFPA Publication for Confined Space Entry/Hot Work.
33 OSHA 29 CFR, Part 1915 34 Technical Manual, T9311-AH-MMC-020 – General Electric Technical Manual, Volume III 35 Technical Manual, Northern Line Model 3423 EHAW, #158 – Onboard 36 Technical Manual, Waukesha:58H102799 (Available On Board) 37 TS GENERAL RUDDER - Trim and Stability Booklet (Available on Board) 38 TS GENERAL RUDDER - Capacity Plan. (Available on Board)
TABLE of CONTENTS
VESSEL PARTICULARS
LIST OF REFERENCES
SECTION 100: GENERAL SERVICES / REQUIREMENT
ITEM No. 101 – OFFICE AND ADMINISTRATIVE SERVICES
ITEM No. 102 – SHORE POWER SERVICES
ITEM No. 103 – WHARFAGE AND LINEHANDLERS
ITEM No. 104 – POTABLE WATER
ITEM No. 105 – BILGES AND DRAIN WELLS
ITEM No. 106 – GARBAGE AND TRASH REMOVAL
ITEM No. 107 – PROTECTIVE FLOOR COVERING
ITEM No. 108 – SECURITY/WATCHMAN
ITEM No. 109 – GAS FREE INSPECTIONS AND CERTIFICATES
ITEM No. 110 – FIRE PROTECTION
ITEM No. 111 – PORTABLE TOILETS/TEMPORARY FACILITIES
ITEM No. 112 – COOLING WATER
ITEM No. 113 – TEMPORARY LIGHTING
ITEM No. 114 – CRANE SERVICE
ITEM No. 115 – STAGING REQUIREMENT
ITEM No. 116 – OFF LOAD OF LIQUIDS AND STORAGE
SECTION 200: DRY DOCK WORK ITEMS
ITEM No. 201 – DRY-DOCKING AND UNDOCKING OF THE VESSEL
ITEM No. 202 – DOCK TRIALS
ITEM No. 203 – HULL PREPARATION AND COATING
ITEM No. 204 – RENEW ZINC ANODES
ITEM No. 205 – ANTI-BIOFOULING SYSTEM MAINTENANCE
ITEM No. 206 – RUDDER AND STERN FRAME EXAMINATION
ITEM No. 207 – PROPELLER INSPECTION, MAINTENANCE AND REPAIRS (ABS)
ITEM No. 208 – PROPELLER SHAFT WEAR DOWN READINGS, (ABS)
ITEM No. 209 – TANK CLEANING AND INSPECTIONS
ITEM No. 210 - SEA VALVES: INSPECTION AND REPAIR, (ABS & USCG)
ITEM No. 211 – ANCHOR CHAIN PRESERVATION AND CHAIN LOCKER INSPECTION
ITEM No. 212 – BOW THRUSTER EXAMINATION AND MAINTENANCE
ITEM No. 213 – ULTRASONIC/AUDIO HULL GAUGING
ITEM No. 214 – WASTER PIECE: EXAMINATION
ITEM No. 215 – SWITCHBOARD METER CALIBRATION
ITEM NO.: 216 - SWITCHBOARD CLEANING
ITEM No. 217 – PRESSURE VESSEL INSPECTIONS
ITEM No. 218 – MAIN PROPULSION MOTORS MAINTENANCE ABSTRACT
ITEM No. 219 – GENERATOR MAINTENANCE
ITEM NO.: 220 - ELECTRIC MOTOR MAINTENANCE
ITEM No. 221 – THRUST & JOURNAL BEARING(S) INSPECTION & RENEWAL
ITEM No. 222 –PROPELLER SHAFT BEARING LUBE OIL TANK AND DELIVERY SYSTEM -
INSPECTION/CLEAN AND RENEWAL
ITEM NO.: 223 – AFT MAST BALST AND COAT
ITEM NO.: 224 – FORWARD MAST BLAST AND COAT
SECTION 300: REPAIR ITEMS
ITEM No. 301 – TOP END OVERHAUL - MAIN GENERATOR NO. 1
ITEM No. 302 – REPLACE GALLEY/MESS’/PASSAGE WAY DOORS TO A-60 FIRE RATED DOORS . 66
ITEM No. 303 – FABRIACTE AND INSTALL GRAB RAILS ON ALL CONTROL ROOM AND SSDG
ROOM ELECTRICAL PANELS
ITEM No. 304 – REPLOCATE SSDG ROOM REMOTE FUEL CUT OFF’S TO A LOCATION THAT
ALLOWS UNOBSTRUCTED ACTIVATION
ITEM No. 305 – REMOVE – PREP AND INSTALL ELETRICAL MATTING (ECR), IN SSDG CONTROL
ROOM
ITEM NO. 305 – OPTIONAL – BLAST AND COAT FANTAIL DECKING AND RENEW GRATING
ITEM No. 306 – TBD
SECTION 400: COST ITEMS
ITEM No. 401 - SUPPLEMENTAL WORK: MAN-HOURS LABOR
ITEM No. 402 - SUPPLEMENTAL WORK: MATERIAL REQUIREMENTS
ITEM No. 403 – DRYDOCK AND WET BERTH DAYS
ITEM No. 500 – OPTIONAL ITEMS
ITEM No. 501 – PORT / STBD STERN TUBE & TAILSHAFT REMOVAL
ITEM No. 502 – PROVIDE ACCESS, THEN REMOVE EXISTING A/C MOTORS & COMPRESSORS
AND INSTALL NEW A/C UNITS
TEM No. 600 - DRY DOCK DRAWING
SECTION 100: GENERAL SERVICES / REQUIREMENT
1.0 ABSTRACT
1.1 This Item describes the general requirements, intent, scope and definitions that shall apply to all aspects of this Specification Work Package.
2.0 REFERENCES:
2.1 American Bureau of Shipping “Rules for Building and Classing Steel Vessels.” (Latest
Version)
2.2 United States Coast Guard regulations, including all applicable CFR and NAVICs.
3.0 GENERAL
3.1 This Work Package, accompanying Contract, and Contract guidance drawings define the scope of work to be performed.
3.2 It is the intent of these specifications that the Contractor shall satisfactorily perform all work and details throughout this work package to the required standards and shall provide all necessary plant facilities, engineering, services, labor, materials, tools, appliances, crane service, fittings, equipment, transportation, communication, light, air and water.
3.3 Contractor responsibility for compliance is limited to the extent that the Contractor is not responsible for items that are not within the scope of the modification and repair work delineated in the Contract Document All authorized work accomplished by the Contractor to correct the cited deficiencies will be accomplished on a delivery order basis.
3.4 Where laws, regulations, requirements or commercial standards are referred to herein, the latest revision that is in effect on the date of the solicitation shall be applicable.
3.5 At no time, shall the ship’s equipment be used for carrying out any part of these specifications, unless otherwise mentioned in these specifications or unless express consent has been given by the Owner’s representative. When ship’s equipment is desired to be used, the owner’s representative shall be requested at least twenty-four hours prior to the use of the equipment.
3.6 The Contractor will be held to have carefully surveyed the ship during the bidders’ inspection, and the associated ship/equipment specifications and drawings prior to bidding and to be satisfied as to conditions, nature, character, quality and quantity of work required to complete the ship as described herein. No warranties, expressed or implied are made as to the accuracy of any of the reference drawings for the ships.
Should the Contractor require the removal or shifting of any parts of the ship’s fittings, stores, fuel, water outfit, equipment, or piping for carrying out the work specified or implied, the same shall be done by him, and all such removals shall be subsequently replaced in a satisfactory manner. Any damage or loss resulting therefore shall be made good by the Contractor at his expense. Should any portion of the vessel’s structure, housing, fixtures, equipment, piping, ducting, etc. require alteration or removal in order to carry out the work or any part thereof, even though not specifically mentioned herein, the Contractor shall make such alteration, removal, replacement, etc. without additional cost to the Owner.
3.7 Care has been taken in the preparation of the Specifications to make them complete and accurate. The Specifications are, however, not intended to cover in detail each system, component and part thereof, nor are they intended to preclude the possibility of modifications to equipment/system characteristics being required during the detail design development and actual accomplishment of the required modification. Any inadvertent omission or inclusion in the specifications which is inconsistent with the general intent of the specifications shall promptly be brought to the attention of the Owner with the view of reconciling the requirements with the intent of the specifications.
3.8 The Owner reserves the right to alter or delete any items of work contained in the specifications.
3.9 Any damage caused by the Contractor’s performance which arises during the time of repairs or during shifting of the ship shall be renewed or repaired by the yard without extra charge.
4.0 MATERIAL AND WORKMANSHIP
4.1 Unless specifically identified as government furnished material, equipment or services
(GFM/GFE/GFS), all materials, equipment and labor shall be Contractor furnished.
4.2 Removed materials which require disposal as a hazardous waste shall be disposed of in accordance with all applicable federal, state and local requirements for disposal of hazardous waste.
4.3 Unless otherwise specified, all materials shall be furnished by the Contractor. All such materials shall be new and of commercial marine quality, conforming to the requirements of the various regulatory bodies.
4.4 New items of equipment or fittings furnished by the Contractor, but not manufactured by him, shall meet the Owner’s approval and such manufacturers’ plans and specifications as necessary for the determination of same shall be furnished to the Owner. Any orders placed by the Contractor before the approval of items covered thereon shall be done entirely at the Contractor’s risk.
4.5 All transportation of materials, machinery parts, tools, steel, etc. and stowage of new equipment and/or spare parts shall be carried out as necessary by the contractor.
4.6 The owner shall submit all pertinent information on Owner furnished equipment that is required by the Contractor for engineering and installation of equipment in sufficient time to meet the engineering production schedule. All materials, equipment, etc. intended for the vessel in any form, shall be adequately stowed and protected by the Contractor while in his possession.
4.7 Except as otherwise specified, stainless steel (CRES or SUS) in this specification shall mean AISI alloy 304 or 316 or equivalent for interior applications and AISI alloy 316 or equivalent for weather locations.
4.8 The Contractor shall be held responsible for the protection of all existing and newly installed equipment and materials. Any equipment that is damaged by the Contractor shall be replaced, repaired or restored at the Contractor’s expense.
4.9 All materials and workmanship shall be subject to inspection and approval by the owner’s representative at all times. Workmanship and materials found to be defective or not in conformity with good marine practice, regulatory requirements, or this Work Package and its associated approved drawings shall be cause for rejection and removal at the Contractor’s expense.
4.10 Install new gaskets, seals, wicking and fasteners when closing up manholes, bolted inspection plates and flanges. All gaskets, seals, wicking and fasteners shall comply with the design service requirements (i.e. pressure and temperature) of the systems or components for which they are installed. All new fasteners installed on exterior systems or components shall be stainless, except where stainless would not be appropriate for certain design requirements.
4.11 All access for work, staging and cleaning in way of repairs necessary for safe burning, welding, etc. shall be performed by the Contractor.
4.12 Remove and replace all interferences necessary to accomplish all of the specification work such as new paneling, piping, galley, stair tower, etc.
4.13 Should the Contractor require the removal or shifting of any part of the vessel or its fittings, stores, fuel, water, outfit, or equipment in order for work to be carried out, this shall be done by him and all such removals shall be subsequently replaced in satisfactory manner. Any damage or loss resulting from such removals or replacements or while the affected portions of the ship are in the care of the Contractor shall be made good by the Contractor at his expense. Should any portion of the vessel’s structure, machinery, fittings or equipment require removal in order to carry out the work of any part thereof, even though not specifically mentioned herein, the Contractor shall make such removals and replacements without additional cost to the owner.
4.14 All new and disturbed areas for each work item carried out by the Contractor shall be prepared and coated in accordance with the MARAD Coating Guidelines as amended, unless otherwise specified in these specifications. Coating manufacturers may be substituted on an as equal basis, with Owner’s prior written approval.
5.0 INSULATION
5.1 Insulation which is damaged, disturbed or removed as a result of modification, new installation, or removal of piping and machinery shall be replaced. Replacement insulating materials shall be of the same type, thickness, R-Value and appearance of the removed/damaged insulation.
5.2 Insulating material(s) with protective and/or confining lagging shall generally be applied to bare metal surfaces attaining temperatures of more than 125 deg F. Pipe surfaces of 55 deg F and less during any operational condition shall have an anti-sweat insulation applied. Where surface temperatures are normally between 125 deg F and 150 deg F and the omission of insulation will not adversely affect operational efficiency, non-metallic lagging only may be applied where necessary to protect personnel from contact with hot metal surfaces.
5.3 Insulation thickness shall be selected so that insulated and fabric-lagged surface temperatures shall not exceed 150 deg. F. Metal or metallic type lagging surface temperatures should not exceed 125 deg. F when in areas susceptible to personnel contact.
6.0 ELECTRICAL GENERAL
6.1 Wiring fittings and fixtures installed in locations exposed to weather, condensation or excessive dampness shall be made of brass or bronze.
6.2 All new electrical equipment shall be located so as to be readily accessible for repairs and removal and so as to reduce to a minimum any likelihood that the equipment may be exposed to injury or damage caused by leaking oil, water, steam or by excessive heat, etc.
7.0 INSPECTION
7.1 The Contractor shall establish and maintain strict quality control procedures and staff
(including inspection force) as may be required to ensure that the quality of workmanship and material provided by the Contractor, subcontractors and vendors conforms to the requirements of the Contract and the specifications. The Contractor shall be responsible for coordinating and arranging for all inspections as required by these specifications.
7.2 All work being accomplished under the contract shall be open to inspection at all sites of work, including subcontractors’ shops, and at all proper times. The Owner is to be fully advised in every particular as to the Contractor’s program of work and the methods which the Contractor intends to pursue, in order that the interests of the Owner may be adequately protected. The Owner shall be furnished with copies of all working plans, finished plans and instruction books as mentioned herein. The Owner shall have the authority to reject any material or workmanship whenever found reasonably defective, unsuitable, not in conformity with good shipbuilding practice, or not in accordance with the specifications. Satisfactory correction and/or replacement of any rejected item is to be accomplished by the Contractor at his expense.
7.3 Upon completion of the work specified herein, all new and affected compartments, equipment, fittings, systems, pipelines, electric cable and systems, and other operable items shall be tested to demonstrate proper installation and working order, and also to demonstrate that all requirements of the specifications, and authorized changes thereto, have been fulfilled. Tests shall be performed to the approval of the Owner and the satisfaction of the various regulatory bodies as their interests may apply.
8.0 DELIVERY
8.1 When the Contractor has satisfactorily completed all work the Contractor shall deliver the vessel to the Owner in a safe and seaworthy condition. The vessel is to be delivered under the requisite formalities and contingent upon its being in satisfactory condition.
8.2 The Contractor shall deliver the ship in a fully cleaned condition with all parts of the ship thoroughly cleaned of all dunnage and dirt, with particular emphasis on the ready condition of all tanks, engineering spaces and accommodations to be immediately put to use without further preparation or cleaning. Special care shall be exercised that all surfaces in the tanks, pipelines and machinery are clean and free from any foreign substance.
8.3 To insure that the ship is in proper condition for redelivery, a final joint survey of the ship will be made by the Owner and the Contractor, at least three days prior to the scheduled delivery date, along with a review of the status of completion of deficiencies. An agreement shall be reached between the Contractor and the Owner based on this survey as to the extent of further cleaning and correction of minor deficiencies which must be completed prior to delivery of the ship.
ITEM No. 101 – OFFICE AND ADMINISTRATIVE SERVICES
1.1 This item describes the requirements for the Contractor to provide Administrative Services for the duration of the contract.
2.0 STATEMENT OF WORK
2.1 Provide the following administrative services from two (2) days before arrival of the vessel at the Contractor's facility through two (2) days following departure of the vessel from the facility:
2.2 Suitable office space, with air conditioning and heating, near the ship with work areas for MARAD COR and vessel’s Chief Engineer, including electrical service, lighting, electrical outlets for all electrical equipment specified below:
2.2.1 Three (3) desks with and locking file drawers.
2.2.2 Three (3) swivel chairs
2.2.3 One (1) plan table or drafting table
2.2.4 Two (2) office machine tables, approx. (3' x 8')
2.2.5 Coffee maker, stand-up refrigerator (15 cu. ft. minimum), microwave oven, refrigerated water cooler or bottled water sufficient for the duration of the contract. For estimating purposes allow for three (10) gallons per week.
2.2.6 Private toilet and washroom facilities, including hot and cold running water.
2.2.7 Janitorial service on a daily basis to clean office and toilet areas.
2.2.8 Four (4) changing lockers
2.2.9 Clean towels, soap, and hand cleaner on a daily basis.
2.2.10 Four (4) reserved parking spaces near office space and vessel.
2.2.11 Unobstructed access to subject office on a twenty-four hour, seven day a week basis for the duration of the contract.
2.2.12 This office shall be located within a reasonable distance of the ship’s gangway.
2.2.13 Paper shredder.
2.2.14 One (1) uninterruptible power supply with connectors and cables.
2.2.15 Internet Access either with high speed “T1” or “Wireless” connections.
2.2.16 Two (2) HP 7410 0r 7200 All-in-One Office Jet or equivalent, with all necessary supplies. To Copy/Scan/Fax/Print, capable of copying legal size and letter size paper, with reduction and enlargement modes, automatic feed, and collation capabilities.
2.2.17 Sufficient letter size and legal size paper and ink for the duration of the contract period.
2.2.18 Office supplies for two (2) people.
3.0 NOTES
3.1 Contractor should note that a minimum of two (2) crewmembers will be onboard during working hours of the contract period. Parking spaces shall be assigned near the vessel, provide parking passes, and security to be provided to accommodate vessel personnel.
ITEM No. 102 – SHORE POWER SERVICES
1.1 This item describes the requirements for the contractor to provide shore power to the vessel for the duration of contract.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Location: Midship Aft 01 Deck
2.2 Description: Shore Power Connection
3.0 STATEMENT OF WORK
3.1 The Contractor shall provide shore power services to the vessel, commencing at the time and date of the ship's arrival at the Contractor's facility until time and date of final departure.
3.1.1 Provide a minimum capacity of 400 amps of electrical power at 460VAC, 3-
Phase, 60 Hertz equipped with single phase and under and over voltage protection relays. The Contractor shall connect and disconnect electrical power to the vessel’s Pig Tail. All electrical cables utilized by the Contractor for shore power shall be in good material condition, free of torn, cracked, or poorly repaired insulation. Cables shall be clearly marked to ensure they are readily identifiable at all times. Contractor shall take and record meter readings on a daily basis.
3.2 Provide and install a voltage recording device and continuously measure and record the voltages at the shore power to ship connection on a daily basis. These records are to be taken at the ship location and provided to the Owner’s Representative.
3.3 Provide and install a kilowatt-hour meter and record the kilowatt use at the shore power to ship connection.
3.4 Upon completion of repair availability disconnect power source and remove from vessel.
4.0 GENERAL REQUIREMENTS
4.1 Provisions for shore power shall be considered on a per diem basis. As part of the initial bid, the Contractor shall allow for 4,000 KWh per day.
4.2 In the case of an adjustment for actual electrical consumption, actual cost shall be adjusted on an actual usage.
ITEM No. 103 – WHARFAGE AND LINEHANDLERS
1.1 This item describes the requirements for the Contractor to provide wharfage, mooring lines, gangway, and fire escapes.
2.0 STATEMENT OF WORK
2.1 Provide a safe berth of sufficient length and five (5) feet of under keel clearance for the duration of the Contract while not in the dry dock
2.2 All costs for sufficient-powered tugs and pilotage fees required to shift the vessel to and from the contractors working berth(s) or drydock space shall be for the account of the Contractor.
2.3 Furnish and set up a safe gangway, lighted and railed, with safety net, for movement of personnel to and from the vessel. Unship and remove the gangway upon departure of the vessel.
3.0 NOTES
3.1 Provisions for wharfage, mooring lines and gangway shall be considered on a per diem basis, and the total cost for the entire availability shall be submitted as the bid price. In the case of an increase or decrease in the length of the Contract, the cost (or credit) for wharfage, mooring lines, gangway and fire escapes shall be based on the per diem basis.
ITEM No. 104 – POTABLE WATER
1.1 It is the intent of this item is to provide potable water to the vessel, as required for testing, flushing, and ballasting.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Location:
2.1.1 Propulsion Motor Space
2.1.2 Tank Fill Line Located Aft Main Deck
2.2 Description:
2.2.1 No.1 F.W. Tank: 4,000 Gallons
2.2.2 No.2 F.W. Tank: 1,000 Gallons
3.0 STATEMENT OF WORK
3.1 Prior to departure, Contractor, at the direction of the ship’s crew, shall fill vessels’ potable water tanks as listed in 2.2 of this item. Quantities supplied shall be verified by the Chief Engineer.
3.2 Contractor shall allow for usage and disposal/removal of all water provided during the course of the availability for testing, flushing, and ballasting of the vessel.
3.2.1 Allowance: Fresh Potable Water: 100 L/T.
3.3 This allowance does not include water used during any cleaning or subsequent usage unless specified above.
4.0 GENERAL REQUIREMENTS:
4.1 Include in the contract price the full cost of providing potable water to the vessel. In the case of an adjustment, final costs shall be adjusted reflecting the actual quantities supplied during the availability. Adjustments will be made at the end of the availability via Change Order MARAD DGO Contracting Officer for that actual quantity supplied.
The Contractor must provide MARAD DGO Contracting Officer actual water meter readings, witnessed by the Chief Engineer.
ITEM No. 105 – BILGES AND DRAIN WELLS
1.1 This item describes the requirements for the Contractor to maintain dry bilges throughout the Contract Period and for the removal of oily bilge water from the vessel.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Generator Room – Four (4)
2.2 ERC Void Space – Two (2)
2.3 Motor Room – Three (3)
2.4 Steering Gear Room – One (1)
2.5 Shaft Alley – One (1)
3.0 STATEMENT OF WORK
3.1 Immediately upon the vessel's arrival at the Contractor's facility, all bilge wells are to be completely pumped down, opened, and cleaned. Once all debris is removed, all surfaces within each well are to be de-greased by hand squeegee and appropriate detergent. After approval replace strainer plates in good order. Standing and wash water shall be pumped ashore and properly disposed of by the Contractor in accordance with all applicable Federal, State, and Local Rules and Regulations.
3.2 Bilge wells shall be left clean and dry on a daily basis. Disposal of any liquids discharged during the Contract shall be in compliance with the EPA Regulations and all applicable Federal, State or Local Regulations.
3.3 All bilges and bilge wells shall be left in a clean, dry condition at departure from the repair facility.
4.0 NOTES
4.1 For estimating purposes allow for 3,000 gallons of bilge water.
4.2 The bid price shall be based on the per gallon basis.
4.3 Furnish the Owner’s Representative with a list of all pumping including amounts (as per disposal tickets), spaces pumped and dates. Final cost adjustment shall be made at the completion of contract on a prorated basis on per gallon bid price.
ITEM No. 106 – GARBAGE AND TRASH REMOVAL
1.1 This item describes the requirements for garbage and debris removal in way of work areas and general clean up throughout the vessel during the course of the availability and final clean up prior to delivery to the owners.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Throughout the vessel.
3.0 STATEMENT OF WORK
3.1 The Contractor shall clean the entire ship daily. All paint containers, chips, shavings, dirt, paper boxes, etc., shall be placed in metal containers which shall be removed daily from the ship. Oil, refuse, hazardous materials, and scrap materials shall also be removed on a daily basis and disposed of in proper manner and in accordance with all federal, state, and local laws and regulations. All garbage that has been generated by ship's crew and shipyard personnel shall be collected and removed on a daily basis (including Saturdays, Sundays, and holidays). The Contractor shall provide metal containers at appropriate locations for garbage deposit.
3.1.1 Remove all dirt and debris from the ship on a daily basis. All areas involved in work or traversed by workers or equipment shall be left clean and in good order.
3.1.2 Provide trash receptacles in work areas only to prevent trash from being littered on the vessel. Receptacles shall be emptied on a daily basis or as required.
3.1.3 Contractor and Owner shall make a joint survey of the entire vessel at least three
(3) days prior to delivery to determine final clean up.
3.1.4 Twenty–four (24) hours prior to redelivery, all weather decks shall be washed down with fresh water.
4.0 GENERAL REQUIREMENTS:
4.1 Total cost for the entire availability shall be submitted as an itemized bid price.
4.2 In the case of an adjustment, final costs shall be adjusted on a per diem basis reflecting the actual duration of the contract.
ITEM No. 107 – PROTECTIVE FLOOR COVERING
1.0 ABSTRACT
1.1 This item describes the requirements for the contractor to provide protective deck covering for the duration of the availability.
2.0 ITEM LOCATION/DESCRIPTION
2.1 All public areas on main deck, and 01 deck passageways.
2.2 Class Room
2.3 Mess Rooms – Two (2)
3.0 STATEMENT OF WORK
3.1 Contractor shall provide heavy duty template paper or equivalent, subject to approval by
MARAD COR. Deck coverings shall be furnished on the main deck, or other areas as designated where access to repairs are being done. The protective covering shall be securely fastened to all decks and bulkheads and renewed by the contractor as necessary or at the direction of the MARAD COR.
3.2 Contractor shall maintain protective covering in good condition throughout the repair period and shall replace same when it becomes defective, oil/grease stained fire hazard and/or tripping hazard. Upon completion of all repairs and prior to redelivery, the contractor shall remove all covering and securing material and clean all areas to restore as original, ready for occupancy.
ITEM No. 108 – SECURITY/WATCHMAN
1.1 This item describes requirements for the contractor to provide shipboard (gangway) security and roving patrol of the vessel.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Throughout the vessel.
3.0 STATEMENT OF WORK
3.1 Provide the services of a bonded uniformed security guard, on a 24/7 basis, stationed at the gangway for the duration of the performance period. Security guards shall be from a security service company and shall not be an employee of the Contractor.
3.2 A daily log shall be maintained by the security watch. All persons, other than Contractor personnel, shall be logged on and off the vessel. The log shall contain blocks for the printed name, organization represented, number, and time on board, time departed. A new page shall be started for each new day starting at 0001 hours.
3.3 The security guards shall insure that only authorized personnel (those directly involved with the specified work prescribed herein) are allowed on board. Visitors shall be accompanied by an authorized person.
3.4 The security guards shall be instructed that the Contractor’s personnel are forbidden access to any part of the ship not necessary to complete items listed within these specifications, except under emergency conditions, such as fire, flooding, storms, etc.
3.5 A shipyard roving patrol is required on the ship at least twice a day when workers are not present. The roving patrol shall be a separate and distinct individual from the gangway guard. The roving patrol can be a full-time employee of the contractor assigned for this task on a temporary basis.
3.6 The roving patrol shall conduct and log routine inspections at least twice a day when workers are not present. The inspections shall cover all areas of the vessel, including but not limited to machinery spaces, cargo holds and accommodations.
3.7 The roving patrol shall be aware of and alert to the signs and conditions that indicate any of the following:
3.7.1 Flooding and rising water levels in machinery spaces and holds.
3.7.2 Fire
3.7.3 Water/oil damage (from leaking or broken steam, water or oil piping or hoses)
3.7.4 Explosion dangers (from escaping welding/burning and sewage gases)
3.7.5 Live disconnected electrical lines or welding leads
3.7.6 Loose and unsecured equipment or machinery which can fall or drop from heights
3.7.7 Unauthorized persons on board the ship during non-working hours.
3.8 It shall be the responsibility of the Contractor to provide the proper training and knowledge to the roving patrol on how to identify these conditions in a shipyard work environment.
3.9 The roving patrol and gangway guard shall have access to a telephone communication at all times. In addition, communication with other shipyard security forces shall also be maintained. The roving patrol and security guards shall be provided with a listing of personnel contacts, including Owner’s and Contractor’s representatives, with day, evening, and weekend phone numbers.
4.0 PERFORMANCE CRITERIA / DELIVERABLES
4.1 Security Log shall be delivered to MARAD COR on a weekly basis.
5.0 NOTES
5.1 Provisions for a gangway security and roving patrol shall be considered on a per diem basis, and total cost for the duration of the contract shall be submitted as a bid price. In the case of an adjustment, final costs shall be adjusted on a per diem basis reflecting the actual costs duration of the contract.
5.2 Contractor shall submit a Change Order Request to MARAD DGO Contracting Officer for actual cost adjustments.
ITEM No. 109 – GAS FREE INSPECTIONS AND CERTIFICATES
1.1 This item describes the requirements to provide Gas Free Certificates aboard the vessel.
2.0 REFERENCES:
2.1 OSHA 29 CFR, Part 1915
3.0 ITEM LOCATION/DESCRIPTION
3.1 Throughout the vessel.
4.0 STATEMENT OF WORK
4.1 Furnish services of a National Fire Association Certified Marine Chemist and Competent Person to inspect vessel and issue certificates "Safe for Men" and "Safe for Hot Work" prior to any person entering space or commencement of any hot work repairs aboard the vessel. Post the original “Marine Chemist’s Certificate” and Log of Inspection and Tests by a Competent Person” (OSHA Form #73) in a protected cover at the vessel’s gangway and/or at the intended work area.
4.2 Maintain all certificates, on a daily basis, by use of a qualified Designated Competent Person who will visually inspect the vessel to ensure that the vessel's safety condition is unchanged for continuation of hot work and entry.
4.3 Provide ventilation where required, Gas-Free and provide Certificates for the following tanks and working areas:
4.3.1 All levels of the engine room including the shaft alley.
4.3.2 All accommodation spaces.
4.3.3 All machinery spaces.
4.3.4 All navigation levels.
4.3.5 All ballast tanks and voids when opened for inspection
4.3.6 All fuel oil tanks when opened for inspection
4.3.7 Two potable water tanks
4.4 All additional costs and re-certification due to shifting vessel within yard, ballasting or de-ballasting, growth work and/or additional items and sea trial departure/arrival shall be included in this item.
4.5 Copies of the original Gas-Free Certificate, and subsequent reissued certificates, are to be posted at a conspicuous location in the vicinity of the gangway; one each is to be furnished to the attending Owner's representative.
5.0 PERFORMANCE CRITERIA / DELIVERABLES
5.1 “Marine Chemist Certification” and “Log of Inspection and Tests by a Competent
Person” (OSHA form #74) posted near gangway and access points or work area.
5.2 Receipt of a certificate of Certification OSHA Form #73 for a Competent Persons.
5.3 Receipt of a legible copy of “Marine Chemist’s Certifications” and “Log of Inspections and Tests by a Competent Person” (OSHA Form #73) to the Owner’s Representative.
6.0 NOTES
6.1 Contractor’s bid price shall be quoted as per tank and/or space entry per day.
ITEM No. 110 – FIRE PROTECTION
1.1 This item describes the requirements for the contractor to provide fire protection on the vessel for the duration of the contract period.
2.0 REFERENCES:
2.1 None.
3.0 ITEM LOCATION/DESCRIPTION
3.1 Ship’s fire main manifold
4.0 STATEMENT OF WORK
4.1 The Contractor shall provide a full fire protection system on board the vessel. The
Contractor shall make-up all fire line connections to the ship and ensure that the fire main is charged at all times while work is being performed. In the event, a section of the fire main is disabled, the Contractor shall provide equivalent fire protection for the disabled area until that section of the fire main is reconnected.
4.2 Contractor shall provide a qualified Fire Protection Service Engineer to lock-out and completely disable the ship’s Halon and CO2 System upon the vessel’s arrival at the
Contractor’s facility. Upon completion of all work, the Contractor shall restore the system to a fully operational status, just prior to redelivery of the vessel.
4.3 Contractor shall provide fire watch(es) during all hot work at each work site and adjacent spaces or decks, as required by applicable Work Item(s). Provide fire extinguishers for each fire watch. Ship's fire extinguishers shall not be used for this purpose. Applicable costs for maintaining fire watches shall be included in the applicable Work Item.
5.0 PERFORMANCE CRITERIA / DELIVERABLES
5.1 Contractor shall prove to the satisfaction of the Chief Engineer and MARAD COR that the Ships’ firefighting system has been restored to a fully operational status.
6.0 NOTES
6.1 Provisions for fire protection shall be considered on a per diem basis. Total cost for the entire availability shall be submitted as an itemized bid price.
6.2 In the case of an adjustment, final costs shall be adjusted on a per diem basis reflecting the actual duration of the contract.
ITEM No. 111 – PORTABLE TOILETS/TEMPORARY FACILITIES
1.1 Provide and maintain portable toilet for shipyard workers. The MSD unit will not be operational, provide two (2) additional units for the ship’s crew. Ships toilets should be covered so they are not used during shipyard period.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Contractor’s facility next to the ship gangway areas.
3.0 STATEMENT OF WORK
3.1 Provide and maintain locked two (2) portable toilets near the vessel’s gangway area, for use by the ship’s crew only. The ship’s MSD system will not be operational during shipyard period. Provide and maintain portable toilets for shipyard workers use.
3.2 Covers shall be installed on toilets to ensure no one uses them during SY period.
3.3 All the portable toilets shall be maintained, pumped, and cleaned on daily basis.
ITEM No. 112 – COOLING WATER
1.1 This item describes the requirement to provide cooling water onboard for ship services.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Contractor’s facility and ship board engine rooms.
3.0 STATEMENT OF WORK
3.1 Upon arrival, provide all hoses and fittings, make all connections, is connections and reconnections, and supply cooling water to the vessel’s cooling water system. This cooling water will in turn be used for auxiliary machinery cooling including, but not limited to, reefers, air conditioning units, and compressors. Connection will be made via hose connections to the vessel’s cooling water system piping as designated by Chief Engineer. The temporary cooling water lines shall be maintained at 50 psig water pressure at the outlet/discharge end at a minimum water flow rate of thirty (30) gpm.
4.0 PERFORMANCE CRITERIA / DELIVERABLES
4.1 Prove all the work to the satisfactory of Chief Engineer.
ITEM No. 113 – TEMPORARY LIGHTING
1.1 This item describes the requirement to provide adequate temporary lighting at all times in all work areas as directed by the COR. Lighting will be sufficient for safe working and movement through affected areas.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Throughout the vessel.
3.0 STATEMENT OF WORK
3.1 Contractor shall provide adequate temporary lighting at all times in all work areas as directed by the COR. Lighting will be sufficient for safe working and movement through affected areas.
3.2 When tank inspection or other such work is required by the specification, lighting is to be installed and maintained to permit safe access and thorough inspections.
3.3 The fitting and cost of temporary lighting shall be included within the applicable specification item. This item will not be separately priced.
ITEM No. 114 – CRANE SERVICE
1.1 This item describes the requirement to provide crane service as directed by COR.
2.0 ITEM LOCATION/DESCRIPTION
2.1 Contractor’s facility.
3.0 STATEMENT OF WORK
3.1 In addition to providing crane services required by the items of this work package, the costs of which shall be included in each individual specification item, the Contractor shall provide an additional 100 hours of crane service (this includes crane operators, riggers, helpers, and associated rigging equipment) to be used as directed by the COR. The crane must be capable of landing a minimum of 5 tons weight on the vessel’s upper decks. The crane service will be used to load/offload stores, equipment, machinery, etc. to/from the vessel for the ship’s crew and other MARAD contractors. Only the COR will authorize use of this additional crane service item. The Contractor shall obtain written authorization from the MARAD COR prior to providing any crane service under this item. Contractor shall maintain log with hours used. This log is to be updated and provided to the COR every Friday afternoon by 1500 hrs.
3.2 Contractor shall credit back to MARAD all additional crane service hours not used.
Contractor’s bid unit price for this time shall be used to price this credit. Contractor’s bid unit price will also be used to price any additional crane service authorized by the MARAD COR over and above the bid of 100 crane hours.
ITEM No. 115 – STAGING REQUIREMENT
1.1 The intent of this work Item is to price the cost of staging, as required, to support repair requirements in this specification.
2.0 STATEMENT OF WORK
2.1 As part of this solicitation, Contractor is required to submit a cost proposal associated with staging requirements in order to complete the work described in the specification.
Contractor to quote price for work to supply any and all staging that may be required in the specification.
2.2 Included in the above is the cost of labor and material to erect and dismantle OSHA approved staging.
2.3 Any additional staging will be negotiated thru a delivery order from COR.
ITEM No. 116 – OFF LOAD OF LIQUIDS AND STORAGE
1.1 This item describes the requirement for the contractor to off load ship's service fuel oil and lube and temporary storage.
2.0 REFERENCES:
2.1 TS General Rudder - Capacity Plan.
3.0 ITEM LOCATION/DESCRIPTION
3.1 Location/Quantity:
3.1.1 NOTE: Tank capacities listed below are for informational purposes only and are not indicative of quantities to be handled.) A current sounding sheet shall be provided at the bidders conference for bidding purposes.
Description Compartment Number Tank Capacity 100% Fuel Oil Day Tank (4-52-3) 4,355 Fuel Oil Day Tank (4-52-4) 4,468 Fuel Oil Storage Tank (4-18-0) 22,317 Fuel Oil Storage Tank (4-72-1) 12,667 Fuel Oil Storage Tank (4-72-2) 22,667 Lube Oil Storage Tank (4-60-1) 1,500 Lube Oil Storage Tank (4-60-1) 1,500
3.2 Quantity: OPTION ITEM pricing shall be in accordance with Paragraph 4.1.
4.0 STATEMENT OF WORK
4.1 Fluid retention of fuel oil and lube oil
4.1.1 Provide a clean storage facility with a capacity of approximately 55,000 gallons of fuel oil and 3,000 gallons of lube oil. Contractor designated storage facility shall be inspected by MARAD COR and Chief Engineer for cleanliness and acceptability prior to any transferring of fuel oil and lube oil. Prior to offloading of liquids, the contractor, together with ship's force, shall verify quantities to be handled. Samples shall be taken by the contractor of the liquid transferred to and from each tank. These samples shall be turned over to the ships force representative. Upon completion of transferring of liquids, the contractor, in conjunction with ship's force, shall further verify quantities at the storage facility.
4.1.1.1 When directed by MARAD COR, return all fuel oil and lube oil to the vessel.
4.1.1.2 All fuel shall be centrifuged when transferring back aboard the vessel
4.1.1.3 Prior to returning of liquids, the contractor, together with ship's force, shall take sounding of all tanks verifying quantities to be handled.
4.1.1.4 Provide MARAD COR with three (3) copies of actual tank soundings verifying quantities to be handled.
4.1.1.5 For pricing purposes, estimated quantities to be off loaded are delineated in Paragraph 4.3.
4.1.1.6 Where removed, reinstall manhole covers on all tanks utilizing new gaskets and wicking, and replacing all missing or defective fasteners.
4.2 Tanks and tank locations are as cited in Paragraph 3.1 of this item together with tank capacities. Ship's equipment and systems shall not be used to off load liquids as set forth in this item. Contractor shall provide his own pumping equipment and rig as necessary in order to perform work as specified in this item.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .