Results of Bid Opening - VA ERFO FS GWJEF808 2020-2(1).pdf
PDF 178 KB Posted
- Attached to
- George Washington and Jefferson National Forests
- Solicitation number
- 693C73-26-B-000007
About this file
This is a Results of Bid Opening document for a Federal Highway Administration (FHWA) Eastern Federal Lands Highway Division construction project. The solicitation number is 693C73-26-B-000007 for project VA ERFO FS GWJEF808 2020-2(1) located in the George Washington and Jefferson National Forests. The bid opening occurred on April 28, 2026, at 2:00 p.m. in Ashburn, Virginia.
Eight bidders submitted proposals with prices ranging from $5,067,150.00 to $12,107,115.00 for the combined schedule work. The low bidder is JWM Enterprises, LLC at $5,067,150.00, consisting of Schedule A ($1,271,845.00), Schedule B ($1,462,530.00), Schedule C ($700,410.00), Schedule D ($777,880.00), and Schedule E ($854,485.00). The project performance period for all combined schedules is 652 calendar days, with individual performance periods of 141 days for Schedule A, 146 days for Schedule B, 100 days for Schedule C, 79 days for Schedule D, and 107 days for Schedule E if awarded separately. Additional bidders included Abrams Group Construction LLC ($5,151,432.21), Central Southern Construction Corp. ($12,107,115.00), Estes Bros. Const. Inc. ($7,957,265.17), King General Contractors, Inc. ($10,540,310.53), Kovilic Construction Co Inc ($9,687,750.00), Structural Engineering Group Inc ($9,399,638.70), and an Engineer's Estimate of $7,787,000.00. The FHWA is currently reviewing and verifying all information, with notification to the low bidder pending completion of the thorough review process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Results of Bid Opening
George Washington and
Jefferson National Forests
PROJECT: VA ERFO FS GWJEF808 2020-2(1)
SOLICITATION NO. 693C73-26-B-000007
April 28, 2026, at 2:00 p.m.
Ashburn, VA
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
BIDDER SCHEDULE TOTAL TOTAL PRICE
Abrams Group Construction LLC SCHEDULE A
$687,479.38
SCHEDULE B
$1,260,612.72
SCHEDULE C
$872,210.65
SCHEDULE D
$1,001,879.76
SCHEDULE E
$1,329,249.70
SCHEDULE A + SCHEDULE B + SCHEDULE C +
SCHEDULE D + SCHEDULE E =
$5,151,432.21
Central Southern Construction
Corp.
SCHEDULE A
$3,577,600.00
SCHEDULE B
$2,764,450.00
SCHEDULE C
$1,736,415.00
SCHEDULE D
$1,915,850.00
SCHEDULE E
$2,112,800.00
SCHEDULE A + SCHEDULE B + SCHEDULE C +
SCHEDULE D + SCHEDULE E =
$12,107,115.00
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-26-B-000007
Project: VA ERFO FS GWJEF808 2020-2(1)
April 28, 2026, 2:00 p.m. local time
The performance period for the completion of Schedule A+B+C+D+E is 652 calendar days.
The performance period if schedules are awarded separately: 141 calendar days for Schedule A, 146 calendar days for Schedule B, 100 calendar days for Schedule C, 79 calendar days for Schedule D, and 107 calendar days for Schedule E.
Estes Bros. Const. Inc. SCHEDULE A
$1,514,832.20
SCHEDULE B
$1,719,072.30
SCHEDULE C
$945,934.40
SCHEDULE D
$1,162,799.79
SCHEDULE E
$2,614,626.48
SCHEDULE A + SCHEDULE B + SCHEDULE C +
SCHEDULE D + SCHEDULE E =
$7,957,265.17
JWM Enterprises, LLC SCHEDULE A
$1,271,845.00
SCHEDULE B
$1,462,530.00
SCHEDULE C
$700,410.00
SCHEDULE D
$777,880.00
SCHEDULE E
$854,485.00
SCHEDULE A + SCHEDULE B + SCHEDULE C +
SCHEDULE D + SCHEDULE E =
$5,067,150.00
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-26-B-000007
Project: VA ERFO FS GWJEF808 2020-2(1)
April 28, 2026, 2:00 p.m. local time
The performance period for the completion of Schedule A+B+C+D+E is 652 calendar days.
The performance period if schedules are awarded separately: 141 calendar days for Schedule A, King General Contractors, Inc. SCHEDULE A
$2,520,307.07
SCHEDULE B
$3,542,815.28
SCHEDULE C
$1,626,995.05
SCHEDULE D
$1,492,449.35
SCHEDULE E
$1,375,743.78
SCHEDULE A + SCHEDULE B + SCHEDULE C +
SCHEDULE D + SCHEDULE E =
$10,540,310.53
Kovilic Construction Co Inc SCHEDULE A
$1,816,100.00
SCHEDULE B
$2,970,200.00
SCHEDULE C
$1,574,200.00
SCHEDULE D
$1,945,650.00
SCHEDULE E
$1,381,600.00
SCHEDULE A + SCHEDULE B + SCHEDULE C +
SCHEDULE D + SCHEDULE E =
$9,687,750.00
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-26-B-000007
Project: VA ERFO FS GWJEF808 2020-2(1)
April 28, 2026, 2:00 p.m. local time
The performance period for the completion of Schedule A+B+C+D+E is 652 calendar days.
The performance period if schedules are awarded separately: 141 calendar days for Schedule A, Structural Engineering Group Inc SCHEDULE A
$1,092,983.20
SCHEDULE B
$2,572,145.60
SCHEDULE C
$1,269,505.50
SCHEDULE D
$2,503,410.30
SCHEDULE E
$1,961,594,10
SCHEDULE A + SCHEDULE B + SCHEDULE C +
SCHEDULE D + SCHEDULE E =
$9,399,638.70
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-26-B-000007
Project: VA ERFO FS GWJEF808 2020-2(1)
April 28, 2026, 2:00 p.m. local time
The performance period for the completion of Schedule A+B+C+D+E is 652 calendar days.
The performance period if schedules are awarded separately: 141 calendar days for Schedule A, Engineer’s Estimate SCHEDULE A
$1,570,000.00
SCHEDULE B
$2,065,000.00
SCHEDULE C
$1,012,000.00
SCHEDULE D
$1,795,000.00
SCHEDULE E
$1,345,000.00
SCHEDULE A + SCHEDULE B + SCHEDULE C +
SCHEDULE D + SCHEDULE E =
$7,787,000.00
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-26-B-000007
Project: VA ERFO FS GWJEF808 2020-2(1)
April 28, 2026, 2:00 p.m. local time
The performance period for the completion of Schedule A+B+C+D+E is 652 calendar days.
The performance period if schedules are awarded separately: 141 calendar days for Schedule A,
| Slide 1 |
| Slide 2: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-26-B-000007 Project: VA ERFO FS GWJEF808 2020-2(1) April 28, 2026, 2:00 p.m. local time The performance period for the completion of Sch |
| Slide 3: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-26-B-000007 Project: VA ERFO FS GWJEF808 2020-2(1) April 28, 2026, 2:00 p.m. local time The performance period for the completion of Sch |
| Slide 4: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-26-B-000007 Project: VA ERFO FS GWJEF808 2020-2(1) April 28, 2026, 2:00 p.m. local time The performance period for the completion of Sch |
| Slide 5: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-26-B-000007 Project: VA ERFO FS GWJEF808 2020-2(1) April 28, 2026, 2:00 p.m. local time The performance period for the completion of Sch |
| Slide 6: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-26-B-000007 Project: VA ERFO FS GWJEF808 2020-2(1) April 28, 2026, 2:00 p.m. local time The performance period for the completion of Sch |
File details come from the government source that posted it. Updated .