This document is an Amendment to a federal solicitation for Vicksburg National Military Park, Project MS ERFO NPS VICK 2020-1(2), Solicitation Number 693C73-25-B-000002.

The key changes in this amendment are:

  1. Revisions to the hauling restrictions in Subsection 104.05 of the Special Contract Requirements (SCRs), including specifying the allowed access routes and bridge load restrictions.
  2. Responses to several bidder questions, covering topics such as site access, load restrictions, materials handling, phasing, and period of performance.
  3. Rescheduling of the bid opening date to Thursday, December 5, 2024 at 2:00 p.m. EST.

The overall project consists of slide repairs on Grant Avenue and Union Avenue, including clearing, earthwork, pavement, and other related work. The project is expected to cost between $5,000,000 to $10,000,000. Bidding is open to all business concerns, with small business subcontracting goals in place.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

693C7325B000002 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ASHBURN VA 20147

ATTN: Construction

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

ASHBURN VA 20147

ATTN: Acquisitions

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

See Block 1411/22/20240002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

10/24/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project MS ERFO NPS VICK 2020-1(2)

The purpose of this Amendment is to:

1) Revise Subsection 104.05 of the Special Contract Requirements (SCRs) (see J-pages provided as part of this Solicitation) for hauling restrictions.

2) Respond to bidder questions.

3) The bid opening date will be rescheduled to Thursday, December 5, 2024, 2:00 p.m. EST.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment 0002

Info Page 1 of 4

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Amendment No. 0002

Project MS ERFO NPS VICK 2020-1(2)

Vicksburg National Military Park

Solicitation: 693C73-25-B-000002

The purpose of this Amendment is to:

1) Revise Subsection 104.05 of the Special Contract Requirements (SCRs) (see J-pages provided as part of this Solicitation) for hauling restrictions.

2) Respond to bidder questions.

3) The bid opening date will be rescheduled to Thursday, December 5, 2024, 2:00 p.m.

EST.

Special Contract Requirement Changes

1) Delete the first, second and third paragraph of Subsection 104.05 of the SCRs (page J-3) and substitute the following:

For hauling to Grant’s Avenue Site 5, enter and exit only via Howe Lane.

For Union Avenue Sites 7, 8, and 9, use Given Hill Road (Cairo Museum) for the entering and exiting of the heaviest and largest equipment only as needed. Given Hill Road is an unmaintained, steep gravel road, thus probably not allowing to access the sites with the weight of the delivery truck plus the equipment. Alternately, enter and exit via Howe Lane using a grassy area (for a three-point turnaround) immediately east of the chain-link fence site closure.

For Sites 7, 8 and 9, due to the lengths of the some of the heaviest trucks delivering the equipment, there may not be enough space to turn it around within the construction limits (from either access) so the vehicles may have to enter from one side and exit through the site. After demolishing Union

Avenue within construction limits, making it passable for construction traffic, the Contractor may use Howe Lane to deliver the heaviest and largest equipment and exit via Given Hill Road (Cairo

Museum).

Due to the length of the delivery truck and equipment load, the entire 80,000-plus pounds should not be on the Union Avenue bridges at the same time, minimize crossing the bridges as much as possible with this equipment weight throughout the duration of the project.

See Subsection 202.03 for the hauling route when salvaging imported fill and rock materials from

Site 5 temporary access road at the end of the project.

Info Page 2 of 4

Hauling will be permitted on only the above-mentioned park roads. Do not use any other park roads for hauling.

Minimize hauling over completed pavement.

When hauling on National Park Service (NPS) roads, do not exceed the load restrictions shown in

Table 104-1, except as approved by the CO. Submit proposed maximum loads including justification for CO’s approval.

Do not exceed the Inventory Rating loads specified in the bridge inspection reports for NPS owned bridges. If the Inventory Rating loads are planned to be exceeded, submit a non-destructive field load test proposal for review and approval. Provide a description of instrumentation and testing procedures in the load test proposal. After completion of field load test, submit a full rating report that includes a summary of results, outline of instrumentation and testing procedures, observations, load ratings, and conclusions and recommendations, for review and approval prior to hauling on the bridges.

Responses To Bidder Questions

a. Question: We recently tried to access the site to take pictures but were unable to due to fallen trees blocking the roadway. Who is responsible for clearing these trees?

Response: If the bidder is referring to the entrance to Site 7 at Union Avenue, these trees need to be removed from the site by the Contractor.

b. Question: Does the Federal Highway Administration have any pictures of the site prior to the roads being blocked by the fallen trees?

Response: If the bidder is referring to Union Avenue Sites 7, 8 and 9 (Thayer’s Approach), please see the geotechnical report posted as part of the solicitation, pages 425-431, 467-493, and 531-

533. For Site 5 at Grant Avenue photos, please see other pages within this report.

c. Question: Referring to the Specs, J pages section 255 & for Mechanically stabilized Earth wall, Welded wire face = 350 SF (320 SF per summary sheet C03), can we know how the SF is derived?

Response: See Standard Specifications for the Construction of Roads and Bridges on Federal

Highway Projects (FP-14) included as part of advertisement documents. The second paragraph of

Subsection 257.07 says the following: “When measuring MSE walls by the square foot, measure the front face of wall excluding footings and leveling courses.”

d. Question: Can the reclamation yard be used for exporting excess material from site 7, 8 and 9?

Per section 203, is it used to salvage borrow and aggregate for site 5 construction access road?

Response: No, the excavated material from these sites needs to be removed from the project and is not expected to be useful to the government. In accordance with the FP-14, Subsection

203.05(a), the material needs to be removed from site.

Info Page 3 of 4

e. Question: For access to sites 7,8, and 9 for the installation of RAP's. It was the consensus from the site visit access would be from the USS Cairo Gunboat Museum entrance. Is the road from the Cairo entrance to the sites subject to load restrictions stated in the specifications? The machinery to install the type of RAPs specified for the project (Liebherr 125) weighs approximately 80,000 (pounds) and must be transported as shown in the attached picture, which exceeds the load restriction and may not be able to make the sharp turns on the access road.

Response: The park has agreed to allow the Contractor to use Given Hill Road (Cairo Museum) for the entering and exiting of their heaviest and largest equipment only as needed. This equipment can also enter and exit via Howe Lane using a grassy area (for a three-point turnaround) immediately east of the chain-link fence site closure. The requests to exceed the load limits under

Subsection 104.05 of the Special Contract Requirements (SCRs) (J-pages), included as part of the solicitation, will need to be submitted to the CO and will be approved on a case-by-case basis.

All other construction traffic will use Howe Lane for the duration of the project. For hauling to

Grant’s Avenue Site 5, entering and exiting will still be allowed only via Howe Lane. The intent is for the Contractor to demolish Union Avenue within construction limits, making it passable for construction traffic, then use Howe Lane to deliver their heaviest and largest equipment and exit via Given Hill Road (Cairo Museum). After measuring from both accesses to the construction sites

(Sites 7, 8, and 9), entering from Howe Lane is a shorter route.

Due to the length of the truck delivering the equipment the bidder mentioned (pictured or equivalent) there may not be enough space to turn it around within the construction limits (from either access) so the Contractor will have to enter from one side and exit through the site. Given

Hill Road is an unmaintained, steep gravel road, thus probably not allowing the Contractor to access the site with the weight of the delivery truck plus the equipment, even if it is allowed.

Due to the length of the delivery truck and equipment load, the entire 80,000-plus pounds should not be on the bridges at the same time, minimize crossing the bridges as much as possible with this equipment weight throughout the duration of the project. In addition, the Contractor will have to analyze the proposed loads for Thayer’s Approach bridges 1 and 2 according to Subsection

104.05 of the SCRs (J-pages), included as part of the solicitation (the currently allowed maximum loads are in bridge inspection reports provided under Amendment 1).

The SCRs have been revised based on this additional information as part of this Amendment.

f. Question: Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

Response: The Superintendent and the QC Manager cannot be the same individual according to the SCRs (J-pages) Subsection 153.02 (see page J-7). The SSHO can be a dual role for either the

Superintendent or QC Manager, but a safety conscious Contractor will have a robust safety plan with a singular individual overseeing this role.

g. Question: Are there any phasing requirements?

Response: No. The Contractor is allowed to work at both Site 5 and Sites 7, 8, and 9 concurrently.

Info Page 4 of 4

h. Question: Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

Response: The Notice To Proceed (NTP) date will be discussed following the award between the

CO and the Contractor and will be agreed to based on the information that the latter shares including justifying any delays to the NTP.

i. Question: Please provide bidding quantities for deteriorated underlayment base course (paving).

Response: The bidding quantities are provided as part of the solicitation (B pages). For additional description and detail on where each pay item applies, see B sheets of the plans. For further quantity breakdown by site, please see sheet C03 of the plans.

File details come from the government source that posted it. Updated .