Appendix_V-PRHTAs Special Provisions.pdf

PDF 16 MB Posted

Attached to
BRIDGE REPLACEMENTS IN CANOVANAS - PR ER PRMNT RPR(1)
Solicitation number
693C73-24-R-000030
Issued by

About this file

This document appears to be Appendix V - PRHTA's Special Provisions, which are supplemental terms and conditions that apply to the BRIDGE REPLACEMENTS IN CANOVANAS project solicitation issued by the Federal Highway Administration (FHWA).

The key details are:

  • This is a two-phase design-build solicitation for the BRIDGE REPLACEMENTS IN CANOVANAS project, with Phase I being a Request for Qualifications (RFQ).
  • The solicitation number is 693C73-24-R-000030 and the project number is PR ST ER PRMNT RPR (1).
  • The FHWA, which is a civilian federal agency, is the awarding agency for this opportunity.
  • The document provides supplemental special provisions that apply to the project, covering topics such as construction requirements, materials, quality assurance, and environmental compliance. However, it does not outline the specific products, services, or pricing terms required.

View the file

Other files

File Type Posted
Shortlist - PR ST ER PRMNT RPR(1).pdf PDF
Amendment 0001 - PR ER PRMNT RPR(1).pdf PDF
Appendix_B-PR ST ER PRMNT RPR(1)_Final DSR_Redacted.pdf PDF
Appendix_W-PRHTAs Standard Drawings.pdf PDF
Appendix_P-PRHTAs Design Directive_107.pdf PDF
Appendix_AC-109.02 Request for Progress Payment Forms_RPR(1).xlsx XLSX spreadsheet
DRAFT RFP 693C73-24-R-000030.pdf PDF
Appendix_F-Bridge 653_Modular Bridge Shop Drawings.pdf PDF
Appendix_AA-Work Zone and Mobility Policy.pdf PDF
Appendix_A-PR-ST-ER-PRMNT-RPR(1)_Plans-30.pdf PDF
Appendix_Z-Puerto Rico Governor Executive Order_OE-2023-024.pdf PDF
Appendix_C-Bridge 606 Bridge Inspection Reports 02-01-2023.pdf PDF
Appendix_J-Bridge 653 Preliminary Bridge Hydraulics Memo.pdf PDF
Appendix_M-Utility Agreement PRHTA and PREPA.pdf PDF
Appendix_U-PRHTAs Material Testing Schedule.PDF PDF
Appendix_X-PRHTAs Standard Specifications.pdf PDF
Appendix_R-PRHTAs Design Directive_111.pdf PDF
Appendix_G-FHWA NEPA FONSI.pdf PDF
Appendix_AB-109.06 Price Proposal Forms_RPR(1).xlsx XLSX spreadsheet
Appendix_E-Bridge 606_Modular Bridge Shop Drawings.pdf PDF
Appendix_Q-DTOPs Manual de Senales de Transito (MST).pdf PDF
Appendix_H-Geotechnical Report.pdf PDF
Appendix_D-Bridge 653 Bridge Inspection Reports 08-05-2022.pdf PDF
Appendix_Y-PRHTAs Supplemental Specifications.pdf PDF
Appendix_O-Planning Board Regulation No13.pdf PDF
Appendix_I-Bridge 606 Preliminary Bridge Hydraulic Memo.pdf PDF
Appendix_S-PRHTAs Design Directive_114.pdf PDF
Appendix_L-Utility Agreement PRHTA and PRASA.pdf PDF
Appendix_N-Manual de Rotulacion para las Vias Publicas de Puerto Rico.pdf PDF
Appendix_T-PRHTAs Design Directive_410.pdf PDF
Appendix_K-USFWS Conservation Measures.pdf PDF
RFQ - PR ER PRMNT RPR(1).docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

October 10, 1995

SPECIAL PROVISION

REVISIONS TO ARTICLES 102.06, 104.02, 104.05 AND 108.07

OF THE GENERAL PROVISIONS

SP-GP/Page 1 of 3

Article 102.06 is revised to read as follows:

102.06 Pre Bid Meeting - The advertisement for bids will indicate if a pre-bid meeting is to be held and the time and place of such meeting.

Article 104.02 is revised to read as follows:

104.02 Alteration of Plans or Character of Proposed Work:

a. The Engineer reserves the right to make, in writing, at any time during the work, such changes in quantities and such alterations in the work as are necessary to satisfactorily complete the project. Such changes in quantities and alterations shall not invalidate the contract nor release the Surety, and the Contractor agrees to perform the work as altered.

b. If alterations or changes in quantities significantly change the character of the work under the contract, whether or not changed by any such different quantities or alterations, an adjustment, excluding loss of anticipated profits, will be made in the contract. The basis for the adjustment shall be agreed upon prior to the performance of the work. If a basis cannot be agreed upon, then an adjustment will be made either for or against the Contractor in such amount as the Engineer may determine to be fair and equitable.

c. If the alterations or changed in quantities do not significantly change the character of the work to be performed under the contract, the altered work will be paid for as provided elsewhere in the contract.

d. The term “significant change” shall be construed to apply only to the following circumstances:

(1) When the character of the work as altered differs materially in kind or nature form that involved or include in the original proposed construction or

(2) When a mayor item of work as defined below, is increased in the excess of 125 percent or decreased below 75 percent of the original contract quantity. Any allowance for an increase in quantity shall apply to that portion in excess of 125 percent of original contract item quantity, or in case of a decrease below 75 percent, to the actual amount of work performed.

SP-GP/Page 2 of 3

e. For the purpose of this article a major item is defined as any contract item for which the product of the proposed quantity and the unit contract price equals 15 percent or more of the total contract amount.

Article 104.05 is revised to read as follows:

104.05 Differing Site Conditions

a. During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before they are disturbed and before the affected work is performed.

b. Upon written notifications, the Engineer will investigate the conditions, and if he/she determines that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding loss of anticipated profits, will be made and the contract modified in writing accordingly. The Engineer will notify the Contractor of his/her determination whether or not an adjustment of the contract is warranted.

c. No contract adjustment which results in a benefit to the Contractor will be allowed unless the Contractor has provided the required written notice.

d. No contract adjustment will be allowed under this clause for any effects caused on unchanged work.

108.07 Suspension of Work

Subparagraphs (1), (2), (3) and (4) under paragraphs a. are revised to read as follows:

(1) If the performance of all or any portion of the work is suspended or delayed by the Engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and

SP-GP/Page 3 of 3 the Contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the Contractor shall submit to the

Engineer in writing a request for adjustment within seven (7) calendar days of receipt of the notice to resume work. The request shall set forth the reason and support for such adjustment.

(2) Upon receipt, the Engineer will evaluate the Contractor’s request. If the Engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the

Contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the Engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The Engineer will notify the

Contractor of his/her determination whether or not and adjustment of the contract is warranted.

(3) No contract adjustment will be allowed unless the Contractor has submitted the request within the time prescribed.

(4) No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided for or excluded under any other term or condition of this contract.

November 26, 2013

BUY AMERICA CLAUSE

SP-BAC/Page 1 of 2

1. All steel and iron items shall be manufactured and any required coating applied in the

United States. The coating materials are not subject to this clause, only the application of the coating. United States includes the 50 United States, Puerto Rico and any place subject to the jurisdiction thereof.

2. Products of steel include, but are not limited to, such products as structural steel, piles, guardrail, reinforcement steel, structural plate, steel supports for signs, luminaries and signals, steel products for utilities constructions and engines and electrical generators for traffic signal central power systems.

3. Products of iron include, but are not limited to, such products as iron frames, covers, grates, lather rungs and iron products for utilities constructions.

4. Application of coatings includes but is not limited to, such applications as epoxy, galvanization and paint.

5. Ore for the manufacture of steel or iron may be from outside the United States;

however, all other manufacturing processes of steel or iron shall be performed in the

United States.

6. The Contractor shall submit the following certificate attesting to the quality of the material provided and its origin or will cause such a certificate to be supplied by his subcontractors or suppliers. The certificate shall include as a minimum the following:

CERTIFICATE OF COMPLIANCE AND ORIGIN

FOR MANUFACTURED OR FABRICATED STEEL

OR IRON MATERIALS

WE HEREBY CERTIFY that (description of material)

Furnished to: (Name of Contractor or Subcontractor)

For use in: (Project name)

With Federal-aid Number: and PRHTA number:

In the quantity of (Quantity represented by this certificate)

Conforms to (List ASTM, AASHTO or other applicable specifications)

November 26, 2013

BUY AMERICA CLAUSE

SP-BAC/Page 2 of 2

Produced by: (Name of manufacturer) and manufactured at: (Location)

Identified by: (Label, seal or batch number) and shipped via: (Consignment or waybill) meets the requirements of the project plans, specifications and special provisions of the Puerto Rico Highway and Transportation Authority in all respects, processing, product testing, inspection control and origin.

Exceptions to the material requirements are as follows: (list all aspects in which the product does not complies with the contractual requirements. Attachment of manufacturer brochure is not acceptable and exceptions are to be listed independently in the certificate).

In addition, we certify that all steel and iron manufacturing processes and coating applications have been performed in the United States.

All records and documents pertinent to this certificate and not submitted herewith will be maintained available at (provide address at which records will be maintained) by the undersigned for a period of not less than five years from

(expected completion date of the project).

Signed by:

Title:

7. This document must be signed by a person having the legal authority for binding the

Contractor, Subcontractor or Supplier.

8. The document shall be submitted in triplicate prior to or at the time of delivery.

9. The Authority may sample and test materials covered by such certification at its discretion to ascertain the validity of certificates.

10. No materials will be incorporated into the project, nor direct or materials on hand payments made until the Contractor has submitted and the Authority approved the appropriate materials of origin and compliance.

January 13, 2010

PRICE ADJUSTMENT CLAUSE

HOT PLANT MIX BITUMINOUS PAVEMENT

SP-GP-PAC-HPM/Page 1 of 4

1.0 GENERAL - The current world situation is affecting the supplies and price of petroleum and may cause unpredictable fluctuation in the future costs of materials dependent on petroleum products. This clause will provide either an additional compensation to the

Contractor or a credit to the Authority, depending upon increases or decreases in the price of the petroleum.

2.0 ITEMS COVERED - This price adjustment clause will apply only to the following items:

2.1 Asphalt cement used in hot plant-mix bituminous pavement (Specifications 401 and 959).

2.2 Asphalt cut-backs and emulsions used for bituminous surface treatment

(Specification 409). The adjustment does not apply to bituminous materials used for prime and tack coats under Specifications 407 and 408 as these materials are not measured for direct payment but are included as a subsidiary obligation under other pay items.

3.0 GENERAL RULES

3.1 No price adjustment will be made until the average period for the covered item increases o decreases in excess of 5 percent of the base index price.

3.2 Price adjustment will be prospective only and will apply to covered items in contract work acceptably performed after the effective date of the adjusted item price.

3.3 Price adjustment for covered contract pay items will be computed monthly by the Authority after a price adjustment is triggered by a change of the average period price in excess of 5 percent over or under the base index price. The increased payment or deduction will be included in the next monthly payment certification covering work acceptably performed to which price adjustment is applicable.

3.4 Once a price adjustment for a covered item is triggered as indicated above, the monthly price adjustment computations and payment will be continued until the work to which it applies is completed.

SP-GP-PAC-HPM/Page 2 of 4

3.5 No upward adjustment in price will be made for items used in work performed during periods for which the Contractor is being charged liquidated damages. If liquidated damages are subsequently reduced by an approved extension of time then this price adjustment clause will be applicable to the work performed during the period covered by the authorized time extension.

4.0 BASE INDEX PRICES - The base index prices will be the prices on which price adjustment, either up or down, will be determined for the covered items in the contract. The base index price for each covered item as of the first working day of the month on which bids for this project are opened which will be determined as indicated below for the following item:

4.1 Asphalt cement, Cutbacks and Emulsions – The average of the lowest price, for each respective product per gallon, in effect as of the base index price date, tank load at the supplier’s plant established and posted by two or more major suppliers in Puerto

Rico.

5.0 AVERAGE PERIOD PRICE - The average period price will be the price to be used to compare with the base index price to compute any applicable up or down price adjustment.

5.1 The average period price will be determined by the Authority for each covered item as of the first working day for each month following the opening of bids using the same procedures for the determination of the base index price.

5.2 The average period price will be applicable to the quantities of covered work acceptably performed during the month for which it was determined. When there is no change in the average period price, the previously determined average price will apply until the end of the month prior to a new average price being determined.

6.0 PRICE ADJUSTMENT COMPUTATIONS - The quantity of material subject to price adjustment and the applicable adjustment will be determined as indicated below for the various items subject to price adjustment.

SP-GP-PAC-HPM/Page 3 of 4

6.1 Hot Plant Bituminous Pavement, Specifications 401 and 959

a. Additional compensation to the Contractor or credit to the Authority will be made for price variations in the asphalt cement and fuel oil (Bunker C or Diesel) used in preparing the mix.

b. The price adjustments for asphalt cement will be based on one of the following usage factors:

Mix Type

Mix Paid by the Ton

Gallons of Asphalt

Cement per Ton

S 12, SPS 13.98

S 38 14.12

B 1, B 34, B 12, SPB 11.68

B 38 14.26

L 1, L 34, L 12, SPL 11.96

L 38 14.24

Note: For mix designs developed as surface mixes (S) with nominal aggregate size (NMAS) of 1/2” (S 75 12 or S 50 12) which has been accepted in writing by the Authority and which are to be used (produced and placed) as a different type of mix (i.e. B 12 or L 12), the surface mixes (S) usage factor shall be considered for the adjustment clause purposes.

c. To determine the price adjustment to the contract unit price of the bituminous plant mix:

1. Compute the difference between the average period price for the month and the base index price for asphalt cement.

SP-GP-PAC-HPM/Page 4 of 4

2. Multiply the above differences by the respective usage factors given in paragraphs 6.1 b above and add the results to determine the total increase (or decrease) in unit price per ton for each type of mix.

3. Multiply the computed increase (or decrease) in unit price by the quantity of covered work to determine the additional compensation or credit due for each applicable contract item.

d. The price adjustment for fuel oil (Bunker C or diesel as applicable to the plant supplying the project) will be based on 2.4 gallons of fuel oil per ton of bituminous plant mix accepted in the project. When the bituminous pavement mix is paid by the square meter, use a 0.06 gallons of fuel per square meter per centimeter depth of accepted pavement, following the procedures stated on 6.1 c (1,2,3) above

6.2 Bituminous Surface Treatments, Specification 409

a. Additional compensation to the Contractor or credit to the Authority will be made for the price variation in the emulsified and cut-back asphalt’s used for surface treatments to be paid for by the gallon as a separate contract item.

b. The additional compensation or credit due will be computed by multiplying the difference between the average period price and the base index price for the bituminous material by the quantity used during the covered month.

7.0 ADDED PAY ITEMS - When new pay items which include materials covered by this price adjustment clause are added to this contract under an extra work order, the applicable base index prices will be determined by the Authority as of first working day of the month on which the extra work order is agreed upon and will be indicated in the extra work order.

8.0 DESIGN CHANGES - The Authority reserves the right to make changes in the design, reduce quantities or eliminate contract items affected by materials covered by this clause, under the terms provided in the General Provisions, when it considers such action to be in the public interest.

March 12, 2007

Revised: April 23, 2015

PRICE ADJUSTMENT CLAUSES

STEEL PRODUCTS

SP-GP-PAC-SP/Page 1 of 3

1.0 GENERAL - Due to increasing demand for steel products worldwide, the scarcity of raw materials, and manufacturing complications, the price of steel has increased dramatically since the year 2003. These changes make uncertain the prices to be quoted for several steel items used for highway construction. This clause provides for adjustments in the price of steel used for the items indicated below.

2.0 ITEMS COVERED - This price adjustment will apply only to the following items:

2.1 Reinforcing steels (Specification 601)

2.2 Steel Piles (Specification 615)

2.3 Guardrail beams and posts (Specification 606, 710)

3.1 No price adjustment will be made until the average period for the covered item increases or decreases in excess of 15 percent of the base index price.

3.2 Price adjustment will be prospective only and will apply to covered items in contract work acceptably performed after the effective date of the adjusted item price.

3.3 Price adjustment for covered contract pay items will be computed monthly by the Authority after a price adjustment is triggered by a change of the average period price in excess of 15 percent over or under the base index price. The increased payment or deduction will be included in the next monthly payment certification covering work monthly price adjustment computations and payment will be continued until the work to which it applies is completed.

3.5 No upward adjustment in price will be made for items used in work performed during periods for which the Contractor is being charged liquidated damages. If liquidated damages are subsequently reduced by an approved extension of time, then, SP-GP-PAC-SP/Page 2 of 3

4.0 BASE INDEX PRICES - The base index prices will be the prices on which price base index price for each covered item as of the first working day of the month on which bids for this project are opened will be determined using the costs provided by steel producers/suppliers in the United States, such as “Steel Services and Supplies, Inc. for reinforcing steel and “Skyline Steel LLC” for steel piles. In case the data are provided by more than one producer/supplie, then the average of the costs will be used.

5.0 PRICE ADJUSTMENT COMPUTATION - The quantity of material subject to price adjustment and the applicable adjustment will be determined as indicated below for the various items subject to price adjustment.

5.1 Reinforcing Steel

The procedure developed by the Authority on an interim basis in September

2004, known as “Metodología para el Ajuste en Precios del Acero de Refuerzo” will be used to determine any adjustments to be made in the price for this item.

The data shown in the original version of the procedure shall be updated by the

Authority to reflect data corresponding to each new individual project to be bid.

This procedure is hereby incorporated by reference into this Special Provision.

Copies of the document are available at the Office for Construction

Management of the Construction Area (“Oficina de Gerencia de

Construcción”). (Rev.: Apr-23-2015)

5.2 Steel Piles

The procedure developed by the Authority on an interim basis in November

2004, known as “Metodología para el Ajuste en los Precios para Pilotes de

Acero”, will be used to determine any adjustments to be made in the price for this item. The data shown in the original version of the procedure shall be updated by the Authority to reflect data corresponding to each new individual project to be bid. This procedure is hereby incorporated by reference into this

Special Provision. Copies of the document are available at the Office of

Estimates and Bids (Oficina de Estimados y Subastas).

SP-GP-PAC-SP/Page 3 of 3

5.3 Guard Rail Beams and Posts

The procedure developed by the Authority on a interim basis in July 2005, known as “Metodología para Ajuste en Precio de Barreras de Seguirdad (Guard

Rails)” will be used to determine any adjustments to be made in the price for this item. The data shown in the original version of the procedure shall be updated by the Authority to reflect data corresponding to each new individual project to be bid. This procedure is hereby incorporated by reference into this

Special Provision. Copies of the document are available at the Office of

Estimates and Bids (Oficina de Estimados y Subastas).

6.0 ADDED PAY ITEMS - When new pay items include materials covered by this price adjustment clause are added to this contract under an extra work order, the applicable base index prices will be determined by the Authority as of first working day of the month on which the extra work order is agreed upon and will be indicated in the extra work order.

7.0 DESIGN CHANGES - The Authority reserves the right to make changes in the design, HAULING OF MATERIALS

SP-GP-PAC-HM/Page 1 of 7

1.0 GENERAL - Hauling of materials from their sources (pits, quarries, natural deposits, etc.) to project site and to asphalt plants, and hauling of asphaltic mixes from the plants to the project site are important components of the cost of the different contract items included in highway projects. The rates for hauling these materials are established and controlled by the Public Service Commission (PSC).

The rates are revised periodically as market conditions change. This clause will provide either an additional compensation to the contractor or a credit to the Authority, depending upon increases or decreases in the rates established by the PSC.

A price adjustment clause for hauling was promulgated by Resolution No. 2004-21 dated April 23, 2004, on an interim basis. This Special Provision extends the applicability of the adjustment clause until otherwise revised, rescinded or declared null and void.

2.0 ITEMS COVERED - This price adjustment clause will apply only to the following items:

2.1 asphaltic concrete mixtures

2.2 coarse aggregate (crushed stone)

2.3 fill material for embankment (borrow) and sub-base material

3.1 No price adjustment will be made until the hauling rate for the covered item increases or decreases in excess of 15 percent of the base index price.

3.2 Price adjustment will be prospective only and will apply to covered items in contract work acceptably performed after the effective date of the adjusted item price.

3.3 Price adjustment for covered contract pay items will be computed monthly by the Authority after a price adjustment is triggered by a change of the hauling rates in excess of 15 percent over or under the base index price. The increased payment or deduction will be included in the next monthly payment certification covering work

SP-GP-PAC-HM/Page 2 of 7 monthly price adjustment computations and payment will be continued until the work to which it applies is completed.

3.5 No upward adjustment in price will be made for items used in work performed during periods for which the Contractor is being charged liquidated damages. If liquidated damages are subsequently reduced by an approved extension of time, then

4.0 BASE INDEX RATES - The base index rates will be the rates on which price base index rate for each covered item as of the first working day of the month on which bids for this project are opened will be determined as indicated below for the items in Article 2.0, above.

5.0 AVERAGE PERIOD (RATE) - The average period rate will be the rate to be used to compare with the base index rate to compute any applicable up or down price adjustment.

5.1 The average period rate will be determined by the Authority for each covered item as of the first working day for each month following the opening of bids using the same procedures for the determination of the base index rate.

5.2 The average period rate will be applicable to the quantities of covered work acceptably performed during the month for which it was determined. When there is no change in the average period rate, the previously determined average rate will apply until the end of the month prior to a new average rate being determined.

6.0 PRICE ADJUSTMENT COMPUTATIONS - The quantity of material subject to price adjustment and the applicable adjustment will be as indicated in Attachments I and II and the “Instructions for Computing Adjustments” attached to this Special Provision. The price adjustment (payment or credit) will be computed using the formula in Attachment II.

7.0 ADDED PAY ITEMS - When new pay items which include materials covered by this price adjustment clause are added to this contract under an extra work order, the applicable

SP-GP-PAC-HM/Page 3 of 7 base index prices will be determined by the authority as of first working day of the month on which the extra work order is agreed upon and will be indicated in the extra work order.

8.0 DESIGN CHANGES - The Authority reserves the right to make changes in the design, SP-GP-PAC-HM/Page 4 of 7

Instructions for Computing Adjustments

In addition to any conditions, restrictions, allowances included in Articles 1.0 to 8.0 above, the following will also apply:

1. Adjustments will only apply to projects advertised for bids after the effective date of this Special Provision.

2. Only the official rates approved by The Public Service Commission will apply.

3. Adjustment will only apply to asphaltic mixtures, store; sand, and fill material

(including sub-base material).

4. To determine any additional compensation for hauling aggregates from the source to asphalt plants a fixed distance of ten (10) kilometers will be used.

5. Hauling of asphalt will be measured based on the actual reasonable distance from the plant to the project site.

6. Hauling of borrow material and stone base course will be measure based on the actual reasonable road distance from the material source to the project site.

7. There will be no increase in payments for hauling rejected materials.

8. The following volumetric parameters are established for:

a. Borrow volume in excess of ten thousand (10,000) cubic meters.

b. Crushed stone for base course-in excess of two thousand (2,000) cubic meters.

9. Adjustments will only apply to materials hauled by truckers with valid permits issued by the PSC. Contractor – owned trucks are not eligible for pay adjustments. Hauling of material excavated from within the right of way and within project limits is not eligible for pay adjustment, no matter where the material is deposited or the type of truck used for hauling (contractor owned, leased, private truckers, etc).

SP-GP-PAC-HM/Page 5 of 7

10. The contractor and his subcontractors shall submit evidence of payment to truckers clearly detailing hauling costs.

11. The contractor and his subcontractors will authorize the Authority to conduct audits of payments claimed for hauling.

12. Computation of payment will be based on PSC tables shown in Attachment I and using formulae shown in Attachment II.

SP-GP-PAC-HM/Page 6 of 7

ATACHMENT I

Rates for Aggregates: Asphalt, stone, sand and fill material.

Note: Asphalt is computed based on short-ton stone, sand, and fill material is computed based on cubic meters.

Distance in

Kilometers

Asphalt

Tariff

Aggregate and

Sand

Tariff

Fill

Tariff

1 $2.28 $1.98 $1.58

2 $2.46 $2.29 $1.77

3 $2.67 $2.48 $1.96

4 $2.89 $2.67 $2.13

5 $3.06 $2.86 $2.28

6 $3.27 $3.08 $2.45

7 $3.40 $3.25 $2.65

8 $3.60 $3.43 $2.85

9 $3.78 $3.62 $3.06

10 $3.97 $3.77 $3.28

11 $4.18 $3.97 $3.47

12 $4.40 $4.18 $3.67

13 $4.61 $4.40 $3.77

14 $4.82 $4.61 $3.94

15 $5.03 $4.82 $4.08

16 $5.25 $5.17 $4.27

17 $5.46 $5.25 $4.41

18 $5.67 $5.46 $4.55

19 $5.87 $5.67 $4.75

20 $6.09 $5.87 $5.17

$0.19 per additional Km.

$0.19 per additional Km.

$0.35 per additional Km.

SP-GP-PAC-HM/Page 7 of 7

ATTACHMENT II

A. Computation of additional payment or credit

a. Percent increase or decrease in rate (P∆)

APP – BIP = P∆

BIP

This percentage (P∆) must be numerically larger than 0.15 to be able to apply adjustment (payment or credit)

b. Adjustment Factor (F)

F = P∆ - 0.15

B. Computation of adjustment – asphaltic mixes

a. Hauling from material source to the batching plant – Based on a fixed distance of 10 Km. using the column for stone and sand (piedra y arena) in Attachment I.

b. Hauling from plant to project site

i. CA = F x CTM x 1.25 for Borrow class “A” and “B”, sub-base material in excess of 10,000 C.M.

ii. CA = F x CTM x 1.25 Base course material in excess of 2,000 C.M.

iii. CA = F x CTM for asphaltic mixes

Legend:

CA = Clause Adjustment APP = Average Period Price (rate) BIP = Base Index Price (rate) CTM = Total quantity of material deposited during the month

August 2, 2013

REVISIONS TO ARTICLE 105.04 OF THE GENERAL PROVISIONS

SP-GP105.04/Page 1 of 1

105.04 Coordination of Plans, Specifications, Supplemental Specifications, Special Provisions and Other Contract Documents

Revised paragraph “a.” to read as follows:

a. These specifications, the supplemental specifications, special provisions, instructions to bidders, project plans (or works to be performed section in the contract book), standard drawings, technical specifications and all contract documents affecting the work, duly issued to the Contractor, are essential parts of the contract and a requirement occurring in one is as binding as if occurring in all. They are intended to be complementary and to describe and provide for a complete work. In case of discrepancy, numerical dimensions will prevail over scaled dimensions and the following contract documents will prevail in the order shown:

(1) Special Provisions

(2) Instructions to Bidders

(3) Plans (or works to be performed section of the contract book)

(4) Standard Drawings

(5) Supplemental Specifications

(6) Standard Specifications (including the General Provisions)

(7) Technical Specifications

(8) Transportation Management Plan (TMP)

July 30, 2009

REVISIONS TO ARTICLE 106.05 OF THE GENERAL PROVISIONS

SP-GP106.05/Page 1 of 1

106.05 Contractor’s Quality Control

Add the following paragraph:

d. The Contractor shall submit for approval and implement a Quality Control

Plan according to Special Provision 665 – Contractor Quality Control Plan (CQCP)

Requirements for Hot Plant Mix Asphalt (HPMA) and specific instructions to bidders included when said special provision and instructions are included in the contract.

The CQCP will be paid according to Special Provision 665.

July 17, 2012

SPECIFICATION 210 - SOIL EROSION AND WATER POLLUTION CONTROL

SP-210/Page 1 of 2

210-1 DESCRIPTION

Revise Article 210-1.01 to read as follows:

210-1.01 Scope - This work shall consist of providing temporary soil erosion and water pollution control measures as shown on the plans or as ordered by the Engineer. The control measure may include berms, dikes, check dams, silt fences, sediment basins, fiber mats, mulches, grasses, slope drains, temporary waterways, construction exists, turbidity barriers and other erosion control devices or methods.

210-2 MATERIALS

Add the following articles:

210-2.08 Construction Exits - Construction exits shall be constructed on a prepared subgrade and shall consist of geotextiles (filter fabrics) and aggregate base course as per

Specification 304.

210-2.09 Turbidity Barriers - Turbidity barriers shall be fabricated and installed at locations indicated on the drawings. Materials will be as indicated on drawings.

210-4 METHOD OF MEASUREMENT

Add the following articles:

210-4.09 Construction exits will be measured by the number of construction exits constructed and accepted by the Engineer.

210-4.10 Turbidity barriers will be measured by the linear meter fabricated, installed and accepted by the Engineer. Anchorage of turbidity barriers to concrete channel is considered a subsidiary obligation of the pay item.

July 17, 2012

SPECIFICATION 210 - SOIL EROSION AND WATER POLLUTION CONTROL

SP-210/Page 2 of 2

210-5 BASIS OF PAYMENT

210-5.05 Payment will be made under:

Pay Item Pay Unit

Construction Exits...................................................................................... Each

Turbidity Barrier ........................................................................................ Linear Meter

Revised: October 20, 2003

REVISIONS TO STANDARD SPECIFICATION 615 –

PILING

SP-615/Page 1 of 1

615-3.1 CONSTRUCTION REQUIREMENTS

Add the following paragraph to Article 615-3.12:

The Contractor shall replace and/or repair damaged sensors, cables, PDA-PAK and any other accessory required to perform PDA up to an amount of four thousand dollars ($4,000), as a subsidiary obligation to piles pay items included in the proposal schedule. When the cost of repairs of the equipment is over four thousand dollars ($4,000), the amount in excess will be paid for on a force account basis.

September 8, 2014

REVISION TO STANDARD SPECIFICATION 621 –

MARKERS AND DELINEATORS

SP-621/Page 1 of 7

621-1 DESCRIPTION

621-1.01 Scope

Add the following to Article 621-1.01

e. This work shall also include furnishing and installation of Flexible Delineators consisting of posts, retro-reflective sheeting and anchoring devices at the locations shown on the plans or contract documents. Flexible delineators are traffic delineators surface or ground mounted and designed to withstand multiple impacts

f. This work shall also include furnishing and installation of traffic delineators mounted on guardrail, concrete barriers, bridge parapets and retaining walls. These delineators consist of reflector panels, retro-reflective sheeting and anchoring devices at the locations shown on the standard drawings, project plans or contract documents.

621-2 MATERIALS

Add Articles 620-2.03 and 620-2.04

621-2.03 Flexible Delineators

a. Flexible delineators shall have a post consisting of a flexible, durable, UV resistant and non- discoloring material for maximum visibility and increased impact resistance. Posts shall be yellow or white for permanent installations and orange for

Maintenance and Protection of Traffic applications. The post shall be a minimum 3 inches wide at the base and at least 48 inches high. The delineator post shall provide an area suitable for the application of retro-reflective sheeting. The flexible delineator posts shall be compatible with an anchor which will hold the post in vertical position by a locking or bolting mechanism. The mechanism shall be such that when a post is no longer serviceable, it can be removed and a new post can be inserted to the anchor and locked or bolted into place.

b. Tubular posts shall be acceptable for this specification. The posts may have round, semi-round, oval, cloverleaf and other shapes to increase the strength and rebounding properties of the post. Flat delineator posts shall not be acceptable for this specification. Tubular posts shall have a minimum width profile viewable from the traffic direction of 3 inches through its entire length. If the shapes of the delineator post

SP-621/Page 2 of 7 changes, the upper end shall be at least 12 inches long. If the flexible delineator posts are exposed to bidirectional traffic, tubular posts shall be equally viewable from all directions and designed to receive multiple heavy impacts from all directions.

c. Drivable and surface mount anchors shall be acceptable for this specification.

A drivable, reusable metal anchor shall be used for roadside installations. The drivable anchor shall have a locking mechanism to which a post can be attached and held in place. A surface mount designed by the manufacturer to be held in place with anchor bolts and a locking device to secure the post shall be used for installations on the road surface. A surface mount shall be rounded on its edges and lightweight to avoid dangerous debris after a heavy impact to the anchor. Surface mounts with anchoring not designed and tested by the manufacturer shall not be acceptable under this specification.

d. Tubular flexible delineators shall comply with the crashworthiness requirements of a Category 1 Traffic Control Device, with evidence of independent testing following the recommendations and guidelines of NCHRP Report 350 Test

Level 3 procedures. In addition, flexible delineators shall have specifications, which conform to the most current edition of the Manual on Uniform Traffic Control Devices

(MUTCD), as adopted by PRHTA.

e. The flexible delineator posts shall be capable of withstanding at least fifty (50) impacts before replacement. If the flexible delineator posts are exposed to bidirectional traffic, they shall be designed to receive impacts from all traffic directions. The testing criteria for these posts shall be in accordance with the AASHTO’s National

Transportation Product Evaluation Program (NTPEP) Field Performance and

Laboratory Evaluation of Selected Flexible Delineators impact testing report. Flexible delineator posts shall be acceptable for this specification if a minimum of 6 of 8 posts tested have not failed. The following conditions will be considered a failure:

1. The flexible delineator post has torn loose or pulled out of the ground.

2. The flexible delineator post has lost more than 10 percent of the post’s exposed length.

3. The flexible delineator post is at an angle greater than 10 degrees from a vertical position.

SP-621/Page 3 of 7

4. The flexible delineator post has less than 50 percent of the retro-reflective sheeting remaining.

5. The surface mount or drivable anchor has torn loose or pulled out of the ground.

f. The NCHRP350 crashworthiness and NTPEP impact testing requirements shall be re-tested when the materials composition has changed, or when the original design has changed.

g. The furnished materials are subject to field inspection by the Engineer as provided in article 621-3.03 of Standard Specification 621 – MARKERS AND

DELINEATORS. The Authority reserves the right to reject materials that do not comply with this specification.

h. The colors of the flexible delineator posts for permanent installations shall be limited to white and yellow, matching the pavement marking colors. When flexible delineators are used as object markers, the posts shall be yellow regardless of the pavement marking color. Orange flexible delineator posts shall be used for work zone applications only.

i. The upper end of the flexible delineator post shall include factory installed retro-reflective bands. The horizontal bands shall be a minimum of 3 inches high and cover the entire post, viewable from all directions. The colors for each retro-reflective band shall comply with ASTM D4956. For yellow delineators used as object markers, the band pattern shall consist of three horizontal stripes, alternating two white bands with one yellow band between the two white bands. A fluorescent orange band shall be used in the place of the yellow band when an orange delineator post is used. For white or yellow delineators not used as object markers, the band pattern shall consist of two white or yellow horizontal stripes, matching the color of the delineator posts. Retro-reflective bands not installed at the factory shall not be acceptable under this

j. Each of the bands shall consist of factory installed flexible retro-reflective sheeting. Yellow and white retro-reflective prismatic sheeting material shall comply or exceed the requirements of ASTM D4956 Type IV. Fluorescent orange retro-reflective prismatic sheeting material shall comply or exceed the requirements of ASTM D4956

Type IV or their equivalent requirements for work zone applications, as determined by the Authority. The retro-reflective flexible prismatic sheeting shall be installed by the

SP-621/Page 4 of 7 manufacturer and shall comply with the performance requirements of this specification.

The design and placement of the bands shall follow this specification and the most current MUTCD requirements.

k. Prior to their use, the Contractor shall submit the Engineer a certificate of compliance in a form meeting the requirements of section 106.06 of the General

Provisions. This certificate shall be submitted before furnishing any materials. The certificate of compliance shall be accompanied by the following:

1. Flexible Delineator product catalog, manuals and specification.

2. A copy of the Federal Highway Administration (FHWA) acceptance letter or a letter of self-certification that complies with FHWA crashworthiness requirements.

3. NTPEP impact testing results and applicable certification.

4. Retro-reflective band sheeting ASTM specifications.

l. The Authority reserves the right to prohibit the use of a flexible delineator product in any project if the Contractor does not comply with the requirements of this specification or if the flexible delineator does not exhibit appropriate behavior or performance in the field, as determined by the Authority. The removal and replacement of any flexible delineator in non-compliance with all of the above shall be the

Contractor’s responsibility and at no cost to the Authority.

621-2.04 Guardrail or Concrete Barrier Mounted Traffic Delineators

a. Guardrail or Concrete Barrier Traffic Delineators shall consist of reflector panels with retroreflective sheeting mounted to guardrail or concrete barrier, built to the design and of the materials indicated in this specification and as shown on the plans or the standard drawings.

b. The reflector panel materials for traffic delineator guardrail or concrete barrier mounted shall be fabricated of steel, following the requirements of straight guardrail reflector panel as per standard drawings.

c. The Contractor may use high strength plastic for the reflector panels, following the requirements of straight guardrail reflector panel as per standard drawings.

SP-621/Page 5 of 7

The plastic panel shall be UV resistant, durable and with high impact resistance, conforming to the parameters indicated in the standard drawings. The

Contractor shall submit product technical data for Engineer evaluation and approval.

d. The concrete barrier traffic delineator shall have a retroreflective sheeting of 5 inches by 5 inches.

e. The guardrail traffic delineator shall have a retroreflective sheeting of 6 inches by 4 inches, following the design of the straight guardrail reflector panel shown in the standard drawings.

f. Reflective sheeting for traffic delineators shall conform to the requirements of

ASTM D4956 for a Type IV material. The adhesive backing for these markers shall be class 1 or class 2.

g. The color of the retroflective sheeting shall conform to the color of the adjacent pavement markings.

h. If the guardrail or concrete barrier is on a median or any location where it requires sheeting on both sides, the corresponding retroflective sheeting shall be installed on both sides of the plate as a subsidiary obligation of the contractor under the corresponding traffic delineator pay item.

621-3 CONSTRUCTION REQUIREMENTS

Add Articles 621-3.04 to 621-3.11

621-3.04 When orange flexible delineators are used for work zone applications or according to maintenance and protection of traffic plans (MPTP), the contractor shall remove them whenever the work zone application or the MPTP changes and when the road works are finished. Removal and disposal of orange flexible delineator posts shall be a subsidiary obligation of the Contractor under the pay items listed below.

621-3.05 Installation of each flexible delineator shall be accomplished in accordance with the recommendations of the manufacturer of said delineator and the construction plans.

Anchoring bolts for surface mounts shall be as indicated by the manufacturer and installed using the manufacturer’s recommendations. Drivable anchors shall be installed according to

SP-621/Page 6 of 7 the manufacturer’s recommendations. Drivable anchors that cannot be driven into the ground to the manufacturer’s recommended depth shall be relocated to a more suitable location in consultation with the Engineer. This relocation shall be performed by the Contractor without additional compensation.

621-3.06 Any unit or element of the flexible delineator which becomes damaged during installation or construction operations after placement shall be replaced by the Contractor without additional compensation.

621-3.07 The removal of any obstruction, including flexible delineator bases, shall be performed previous to the installation of the flexible delineators. Removal of obstructions from previous flexible delineator installations shall be considered a subsidiary obligation of the

Contractor under this specification.

621-3.08 The installation of guardrail or concrete barrier traffic delineators shall conform to this specification, standard drawings, plans and contract documents, as directed by Engineer.

Attach the delineator panel to concrete barrier (including bridge parapet) with a suitable corrosion resistant fastener for concrete conforming to the manufacturer’s recommendations and approved by the Engineer. Attach the delineator panel to guardrail using two holes to install self drilling – self tapping screws as indicated in the standard drawings for the straight guardrail reflector panel.

621-3.09 The installation of traffic delineators for existing guardrail shall use suitable fasteners conforming to this specification and standard drawings. The use of adhesive shall not be acceptable for installation of traffic delineators on existing guardrail.

621-3.10 Reflector panels shall be perpendicular to the barrier horizontal axis, visible to traffic and attach in at least two points to guardrail or concrete barrier.

621-3.11 The traffic delineators shall be installed carefully after completing installation of guardrail, painting of concrete barriers and other works that may cause damage, require cleaning or obstruct visibility. The Contractor shall replace, at no additional cost to the

Authority, any component damaged during the installation or as a result of not complying with this specification, plans or standard drawings.

SP-621/Page 7 of 7

621-4 METHOD OF MEASUREMENT

Add Articles 621-4.03 to 621-4.05

621-4.03 Tubular flexible delineators, of the specified color will be measured by the number of units installed in place and accepted. Site preparation for the installation of posts and anchoring devices, removal of structures and obstructions, removal and disposal of existing posts, markers, or delineators, and any other requirements established on this specification, plans and contract documents, which is not paid under a separate pay item, shall be considered as a subsidiary obligation of the Contractor with their cost included in the contract prices for the flexible delineator pay items listed below.

621-4.04 The guardrail or concrete barrier mounted traffic delineators installed on existing guardrail, concrete barriers bridge parapets or retaining walls will be measured by the number of units installed in place and accepted. Site preparation for the installation of reflective panels, retroreflective sheeting, anchoring devices, and any other requirements established on this specification, plans and contract documents, which is not paid under a separate pay item, shall be considered as a subsidiary obligation of the Contractor with their cost included in the contract prices for the guardrail or concrete barrier traffic delineator pay items listed below.

621-4.05 Retroreflective markers (traffic delineators) installed as part of new guardrail or concrete barrier works will not be measured for payment but shall be a subsidiary obligation of the Contractor under the corresponding guardrail or concrete barrier pay item.

621-5 BASIS OF PAYMENT

621-5.02 Payment will be made under:

Add the following pay item:

Tubular Flexible Delineator, White, Yellow or Orange .......................... Each

Traffic Delineator Metal Barrier Mounted ............................................... Each

Traffic Delineator Concrete Barrier Mounted .......................................... Each

Revised April 25, 2017

REVISIONS TO STANDARD SPECIFICATION 626 –

PLANTING

SP-626/Page 1 of 5

626-1 DESCRIPTION

626-1.01 Scope

This section is revised as follows:

a. This work shall consist of furnishing and planting or removal and transplanting of trees and palms, pruning o existing trees, shrubs, vines and other ground cover plants in accordance with these specification and the details and locations shown on the plans or established by the Engineer.

b. This work shall consist of furnishing and planting the Vetiver grass

(Chrysopogon Zizanioides) for the application of soil and slope stabilization methods, soil erosion control measures or landscaping. This work shall be in accordance with these specification and details and locations shown on the plans or established by the

Engineer. The work also may include the application of a temporary erosion control blanket for the purpose of the Vetiver grass establishment and protection.

626-2 MATERIALS

626-2.01 Materials for this work shall meet the requirements of the following articles of

Specification 713 - Roadside Improvement Materials.

Add the following material:

Temporary Erosion Control Blanket .................................... 712-7

626-2.03 Source of Plants

a. All plant materials should originate in Puerto Rico from locally available seed and cutting sources (including Vieques, Culebra and Isla de Mona). Exceptions to this requirement need to the approved by the Puerto Rico Highway and Transportation

Authority (PRHTA) or Department of Natural Environmental Resources (DNER).

SP-626/Page 2 of 5

b. All plant material to be imported shall comply with importation dispositions of the US Department of Agriculture and the Department of Agriculture of the

Commonwealth of Puerto Rico.

c. The origin of the Vetiver (Chrysopogon Zizanioides) must be certified by the supplier as being of the "Sierra" variety, adapted to Puerto Rico and which is a native variety in the South of India, guaranteed non-fertile, and coming from a producer certified by The Vetiver Network International (TVNI). The plants must be free of insects or disease, and must be developed in a substrate (growing mix) that does not contain natural soil, sand, or contaminants. The plants are planted in seedlings

(plugs) of a diameter of 2.0 to 2.5 inches (0.050 to 0.063 meter) at the top and 4.75 to

5.0 inches (0.121 to 0.127 meter) in depth. The seedlings will have a minimal development of two active stems cut of 10 to 12 inches (0.254 to 0.304 meter) high and not less than 4 inches (0.102 meter) long thick root system.

626-3 CONSTRUTION REQUIREMENTS

626-3.05 Excavation for Plant…

This is the start of the file's text. The full file is on GovTribe.