Amendment 0001 - WV NP NERI 107(2).pdf

PDF 601 KB Posted

Attached to
New River Gorge National Park & Preserve
Solicitation number
693C73-24-R-000010
Issued by

About this file

This request for proposal (RFP) solicits proposals for a construction project located at the New River Gorge National Park and Preserve in West Virginia. The project consists of granular backfill, mechanically stabilized earth (MSE) wall construction, deep geotechnical patches, pipe culverts, inlets, manholes, curb and gutter, asphalt paved waterway, and guardrail replacement. The work will be split into multiple schedules and contract options with a total cost expected between $5 million and $10 million. Certified small businesses will be invited to submit technical and price proposals by January 23, 2024 following the instructions in the RFP. Offerors must demonstrate experience constructing MSE walls and working within a short construction season. The contract will be awarded to the responsive, responsible bidder with the lowest total price who meets the technical requirements.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

693C7324R000010 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ASHBURN VA 20147

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

ASHBURN VA 20147

ATTN:ACQUISITIONS

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

See Block 1401/02/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

12/22/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project WV NP NERI 107(2)

The purpose of this Amendment is to:

1) Revise the Solicitation Proposal Schedule Instructions (B Pages) to

a) Change Technical Proposal Evaluation Factors, item (a) (ii) and (b)(ii) on page 2 of the Proposal Schedule Instructions to reflect the correct amount of experience required in MSE wall construction.

The Proposals due date of January 23, 2024, at 2:00 p.m. EST remains unchanged.

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment No. 0001

Info Page 1 of 1

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Amendment No. 0001 Project WV NP NERI 107(2)

New River Gorge National Park and Preserve Solicitation No. 693C73-24-R-000010

The purpose of this Amendment is to:

1) Revise the Solicitation Proposal Schedule Instructions (B Pages) to

a) Change Technical Proposal Evaluation Factors, item (a) (ii) and (b)(ii) on page 2 of the Proposal Schedule Instructions to reflect the correct amount of experience required in MSE wall construction.

The Proposals due date of January 23, 2024, at 2:00 p.m. EST remains unchanged.

PROPOSAL INSTRUCTIONS

PROJECT: WV NP NERI 107(2)

OFFERORS PLEASE NOTE: Before preparing the proposal, carefully read the Instructions to

Offerors. While preparing the proposal, comply with the following:

The Government will award the project to the lowest priced/technically acceptable responsible Offeror. The Contracting Officer intends to evaluate all proposals from all eligible Contractor firms/teams (Offerors) for technical acceptability. After all of the technical proposals have been evaluated, the Offerors that are found technically acceptable will be ranked according to the price and the lowest Offeror will be awarded the contract.

EVALUATION OF PROPOSAL DOCUMENTS

STEP 1 - TECHNICAL ACCEPTABILITY – Experience in MSE wall construction

TECHNICAL ACCEPTABILITY EVALUATION DESCRIPTION

Competing technical proposals will be evaluated against the solicitation requirements; they are not compared with each other. Each of the technical evaluation factors described below will be rated on a pass/fail basis and must receive a passing score for an Offeror's proposal to receive further consideration. Failure to receive a passing score for any technical evaluation factor will result in rejection of an Offeror's proposal notwithstanding passing scores for other technical evaluation factors. Technical acceptability will be determined by evaluating each responsive proposal and comparing the results of that evaluation against the technical requirements specified in the solicitation. Proposals which satisfy the technical requirements of the solicitation, in light of the evaluation criteria, will be determined technically acceptable.

Offerors will be evaluated on the Offeror’s past performance and experience in construction of MSE walls.

TECHNICAL PROPOSAL EVALUATION FACTORS

The Offerors need to submit the following qualifications and information, and label it as the Technical Proposal. Offerors must include names, titles, phone numbers, and email address for all references submitted.

(a) Key Personnel. The Offerors need to submit resumes of key personnel proposed for this contract. The Government will review and evaluate each Offeror's proposed key personnel, including technical similarities between the Offeror's experience and the work described in this solicitation, of the Offeror’s proposed key personnel. Include names, titles, phone numbers, and email addresses for all references submitted. Submit documentation for all key construction personnel to be involved in the construction of the project: The Offerors will be required to submit the following:

Amendment 0001

(i) Superintendent: The Offerors need to show that the Contractor’s Superintendent has a minimum of five years of Mechanically Stabilized Earth (MSE) wall construction experience.

(ii) Foreman: The Offerors need to show that the Contractor/subcontractor’s MSE Wall Foreman has a minimum of five (5) years of MSE wall construction experience in the last 10 years since the solicitation date of this contract.

(b) Construction Capability and Resources. The Government will review and evaluate the information about each Offerors' past performance in the design and construction of MSE wall construction projects based on the Offeror's record and reputation for satisfactorily completing projects similar in size and scope. The Offerors will be required to submit the following:

(i)Organizational structure, identifying major participants and describing their roles in the project. Identify how the Contractor/subcontractor was involved with construction engineering support and the MSE wall construction.

(ii) Documentation that shows direct experience of the Offeror, and/or experience of subcontractors that the Offeror proposes to utilize in the execution of this project.

Submit documentation that shows direct experience of the Contractor/subcontractor in constructing MSE walls by providing at least three (3), but no more than five (5) MSE wall construction projects completed in the past ten (10) years similar in scope and size to the Cunard River Access Road project. Offerors are to include the experience of the entire prime and subcontracting team that will perform the work on this project.

(iii) For each project included under (b)(ii), offeror required to provide owner contact information, including name, title, company, phone number, email address, and provide initial and final construction cost, reasons for cost changes, and initial and final durations, including reasons for schedule changes.

(c) Technical Approach to Construction.

(i) Approach to wall construction. The Offerors need to describe the construction of the MSE wall project, including excavation and installation. In addition, offeror must describe how Occupational Safety and Health Administration (OSHA) requirements will be implemented on the project. Also, describe how the contractor plans to remove the existing earth retaining structure and how it will connect the existing (to remain) retaining structure with the new MSE wall.

(ii) Construction staging. The Offerors required to describe how they will stage construction to stay within the limits shown in the plans.

(iii) Approach to maintaining temporary traffic control. The Offerors must describe how they will maintain construction signing. Describe how you will provide emergency access to Government personnel, if possible.

(iv) Environmental considerations and compliance during construction. The Offerors must describe how work will comply with the environmental documents for this project.

(d) Project and Management Plan. The Offerors required to provide the following:

(i) Proposed Quality Assurance and Quality Control plans for construction in order to deliver a quality construction project on-time and within budget (see Sections 153 and 155).

(ii) Approach to coordinating with the EFLHD, NPS, entities such as Fire & Rescue, Police and local jurisdictions; and approach to public safety and public awareness.

(iii) Approach to meeting the tight contract construction schedule.

Technical Proposals shall not exceed 10 single sided pages of 8.5” x 11” size using Times New Roman font with a size of 12-point. All pages must be numbered. Only pages numbered 1 through 10 will be considered during the evaluation process. Additional pages consisting of photos, brochures, resumes, or other pre-printed material may be submitted as long as the exact item to be incorporated is identified. This material may not exceed an additional 10 pages. Gantt charts, site maps, or charts can be submitted on single sided sheets up to 11” x 17”. If tabs are used and contain project-specific information, they will be counted as pages.

STEP 2 - LOWEST PRICE - Cost to Perform the Proposed Work

LOWEST PRICE EVALUATION DESCRIPTION

Only Cost Proposals from Offerors that passed the technical acceptability phase will be evaluated.

Cost Proposals from Offerors that did not pass the technical acceptability phase will be returned unopened. All acceptable Cost Proposals will be reviewed and evaluated for completeness and reasonableness.

COMPLETING THE PROPOSAL SCHEDULE

Complete the Proposal Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places, for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit Bid Price and Amount Bid for the pay item. Determine the Proposal Total for each specific individual Schedule of Work by adding the amounts of the listed items and show it in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.

To be eligible for award, offerors must submit prices for each pay item.

Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.

Fill in the Proposal Total(s) for each individual Schedule of Work as directed on the Proposal Summary page. Fill in the Evaluation Total Price of Project in the space provided on the Proposal Summary page.

The amount in Block 17 of the SF 1442 should be completed as follows:

Schedule A - $ .

Schedule B - $ .

Schedule C - $ .

SCHEDULES OF WORK

The Proposal Schedule is comprised of the following separate schedules and options of work:

Schedule A (Base Contract) - Pages B-1 thru B-3 Schedule B (Government Option 1) - Pages B-4 thru B-6 Schedule C (Government Option 1) - Pages B-7 thru B-9

The Government will award the project as a Base Contract (Schedule A) with the option to award Schedule B and Schedule C (Government Options 1 and 2); see FAR Clauses 52.217-4 and 52.217-5.

The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price, by proper utilization of programmed funds and upon receipt of any additional funds required to award the contract. If complete funding is in place at the time of award of Schedule A (Base Contract), the Government may award Schedules B and C (Government Options 1 and 2) at that time. If additional funding is required for the award of Schedules B and C (Government Options 1 and 2), and is received after the award of Schedule A (Base Contract), the Government has the right to exercise Schedules B and C (Government Options 1 and 2) at the unit prices bid according to the following schedule:

Schedule B (Government Option 1): No later than June 30, 2024.

Schedule C (Government Option 2): No later than June 30, 2024.

COMPLETION OF WORK

If the Government awards the contract as Schedules A + B + C, all construction activities at the project site must be completed by no later than April 15, 2025.

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 96 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 30 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 25 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.

In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and Special Contract Requirements (SCR’s). Specific work limitations may be (but are not limited to): National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection

104.03 of the FP and SCR’s).

Offerors are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-15) may result in the start of construction activities no be no earlier than March 2024. See Subsection 108.01 of the SCRs for additional details.

BASIS FOR AWARD

The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation Total Price of Project, which is defined as:

Schedule A (Base Contract) Bid Total + Schedule B (Government Option 1) Bid Total + Schedule C (Government Option 2) Bid Total.

U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0001
Proposal Instructions_Amendment 0001.pdf
PROPOSAL INSTRUCTIONS
EVALUATION OF PROPOSAL DOCUMENTS
COMPLETING THE PROPOSAL SCHEDULE
To be eligible for award, offerors must submit prices for each pay item.
SCHEDULES OF WORK
COMPLETION OF WORK
B pages Sch A + B(Opt 1) - (RFP competitive negotiation)_Not Bidding CalDays_DRAFT.pdf
PROPOSAL INSTRUCTIONS
EVALUATION OF PROPOSAL DOCUMENTS
COMPLETING THE PROPOSAL SCHEDULE
To be eligible for award, offerors must submit prices for each pay item.
SCHEDULES OF WORK
COMPLETION OF WORK
B pages Sch A + B(Opt 1) - (RFP competitive negotiation)_Not Bidding CalDays_DRAFT.pdf
PROPOSAL INSTRUCTIONS
EVALUATION OF PROPOSAL DOCUMENTS
COMPLETING THE PROPOSAL SCHEDULE
To be eligible for award, offerors must submit prices for each pay item.
SCHEDULES OF WORK
COMPLETION OF WORK
B pages Sch A + B(Opt 1) - (RFP competitive negotiation)_Revised.pdf
PROPOSAL INSTRUCTIONS
EVALUATION OF PROPOSAL DOCUMENTS
COMPLETING THE PROPOSAL SCHEDULE
To be eligible for award, offerors must submit prices for each pay item.
SCHEDULES OF WORK
COMPLETION OF WORK