Results of Bid Opening - NY FLAP DOT 63(1).pdf
PDF 77 KB Posted
- Attached to
- Roadway Improvements to NYS Route 63
- Solicitation number
- 693C73-23-B-000012
About this file
This document summarizes the results of a bid opening for roadway improvements to New York State Route 63. The solicitation was issued by the Eastern Federal Lands Highway Division of the Federal Highway Administration for project number NY FLAP DOT 63(1) with the identification number 693C73-23-B-000012. Two bids were received for the work divided into Schedule A and Schedule B components. Central Southern Construction Corp's bid was for $2,965,000 for Schedule A and $2,687,900 for Schedule B, totaling $5,652,900 for both. Keeler Construction Co., Inc. bid $1,823,195 for Schedule A and $3,028,830 for Schedule B, totaling $4,852,025 for both. The independent government estimate was $1,482,550 for Schedule A and $1,750,000 for Schedule B, totaling $3,232,550. Performance timelines are also provided based on award of Schedule A only, Schedule B only, or both combined.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
Roadway ImprovementS To NYS Route 63
PROJECT: NY FLAP DOT 63(1)
SOLICITATION NO. 693C73-23-B-000012
August 8, 2023 at 2:00 p.m. EDT
Ashburn, Virginia
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-23-B-000012
Project: NY FLAP DOT 63(1)
August 8, 2023, 2:00 p.m. EDT
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Central Southern Construction
Corp.
SCHEDULE A
$2,965,000.00
SCHEDULE B
$2,687,900.00
SCHEDULE A + OPTION 1 =
$5,652,900.00
Keeler Construction Co., Inc. SCHEDULE A
$1,823,195.00
SCHEDULE B
$3,028,830.00
SCHEDULE A + OPTION 1 =
$4,852,025.00
Engineer’s Estimate SCHEDULE A
$1,482,550.00
SCHEDULE B
$1,750,000.00
SCHEDULE A + OPTION 1 =
$3,232,550.00
If the Government awards the Contract as Schedules A + B, the performance period to complete all contract work will be
128 calendar days. If separate: Schedule A will be 76 calendar days; and Schedule B will be 100 calendar days.
File details come from the government source that posted it. Updated .