Results of Bid Opening - NP CHOH 206(1) 913(1) ETC.pdf
PDF 83 KB Posted
- Solicitation number
- 693C73-23-B-000006
About this file
This document summarizes a bid opening for a federal construction contract. The bid opening was held on February 28, 2023 by the Federal Highway Administration Eastern Federal Lands Highway Division for Solicitation Number 693C73-23-B-000006. The project involves replacement of five bridges, construction of a new pedestrian bridge, and repairs to a box culvert along the Chesapeake and Ohio Canal National Historical Park. The bids ranged from $2,989,515 to $4,620,065 for Schedule A work and $685,500 to $1,777,900 for Schedule B work. The engineer's estimate was $3,020,000 for Schedule A and $1,037,000 for Schedule B. The performance period for all work is estimated at 245 calendar days, with Schedule A taking 235 days and Schedule B taking 105 days. The solicitation involves construction services along the Chesapeake and Ohio Canal National Historical Park and is open only to certified small businesses.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
Chesapeake and Ohio Canal National Historical Park
PROJECT: NP CHOH 206(1) 913(1) ETC
SOLICITATION NO. 693C73-23-B-000006
February 28, 2023 at 2:00 p.m. EST
Ashburn, Virginia
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-23-B-000006
Project: NP CHOH 206(1) 913(1) ETC
February 28, 2023, 2:00 p.m. EST
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Central Southern Construction
Corp.
SCHEDULE A
$4,345,518.00
SCHEDULE B
$966,205.00
SCHEDULE A + OPTION 1 =
$5,311,723.00
HMF Paving Contractors, Inc. SCHEDULE A
$4,620,065.00
SCHEDULE B
$1,777,900.00
SCHEDULE A + OPTION 1 =
$6,397,965.00
Kovilic Construction Company, Inc.
SCHEDULE A
$4,247,800.00
SCHEDULE B
$685,500.00
SCHEDULE A + OPTION 1 =
$4,933,300.00
If the Government awards the Contract as Schedules A + B, the performance period to complete all contract work will be
245 calendar days. If separate: Schedule A will be 235 calendar days; and Schedule B will be 105 calendar days.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-23-B-000006
Project: NP CHOH 206(1) 913(1) ETC
February 28, 2023, 2:00 p.m. EST
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Scrimgeour’s Farm All, LLC SCHEDULE A
$2,989,515.00
SCHEDULE B
$996,240.00
SCHEDULE A + OPTION 1 =
$3,985,755.00
Engineer’s Estimate SCHEDULE A
$3,020,000.00
SCHEDULE B
$1,037,000.00
SCHEDULE A + OPTION 1 =
$4,057,000.00
If the Government awards the Contract as Schedules A + B, the performance period to complete all contract work will be
245 calendar days. If separate: Schedule A will be 235 calendar days; and Schedule B will be 105 calendar days.
File details come from the government source that posted it. Updated .