Amendment 0004 - NP-BLRI 2D17.pdf
PDF 8 MB Posted
- Attached to
- Blue Ridge Parkway Federal contract opportunity
- Solicitation number
- 693C73-22-R-000008
About this file
This document provides details on a federal contract opportunity for the replacement of the Laurel Fork Bridge on the Blue Ridge Parkway in North Carolina. The solicitation seeks proposals for a project that includes precast segmental concrete work, structural concrete, post-tensioning systems, drilled shafts, temporary bridges, mechanically stabilized earth walls, bridge removal and other work. Offerors must demonstrate experience with precast post-tensioned concrete box girder segmental bridges, drill shafts, stone masonry and project management. The contract value is estimated to be over $10 million. The proposal due date is specified in the solicitation. The low price technically acceptable source selection process will evaluate technical proposals and price proposals submitted separately. The contract is expected to be awarded upon receipt of necessary permits.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0006 - NP-BLRI 2D17.pdf | ||
| Amendment 0005 - NP-BLRI 2D17.pdf | ||
| Amendment 0003 - NP-BLRI 2D17.pdf | ||
| Amendment 0002 - NP-BLRI 2D17.pdf | ||
| Amendment 0001 - NP-BLRI 2D17.pdf | ||
| ADV_Subcontracting Plan - NP-BLRI 2D17.doc | DOC document | |
| ADV_Offerors Qualifications Form.doc | DOC document | |
| Laurel Fork Bridge -As Built Plans.pdf | ||
| NPS BLRI 2D17 2A16 FONSI.pdf | ||
| Plans - NP-BLRI 2D17.pdf | ||
| NP BLRI 2D17 Final Geotech Report.pdf | ||
| RFP Solicitation - NP-BLRI 2D17.pdf | ||
| FP14_Eng.pdf | ||
| VETS-4212 Form.pdf | ||
| 5140-159P-2021 insp rep_Redacted.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
693C7322R000008 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ASHBURN VA 20147
ATTN: CONSTRUCTION
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
ASHBURN VA 20147
ATTN: ACQUISITIONS
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
See Block 1412/09/20210004
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
10/21/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project NP-BLRI 2D17
The purpose of this Amendment is to:
1) Revise plan sheets to address permitting agency's concerns.
2) Revise B-Pages to change quantities for two (2) pay items.
3) Revise RFP Statement to make required changes.
4) Revise B-Pages Proposal Instructions to make required changes.
5) Respond to bidder questions.
6) The proposal due date remains January 18, 2022, at 2:00 pm EST.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment 0004
Info Page 1 of 2
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0004
Project NP-BLRI 2D17
Laurel Fork Bridge Replacement
Solicitation: 693C73-22-R-000008
The purpose of this Amendment is to:
1) Revise plan sheets to address permitting agency’s concerns.
2) Revise B-Pages to change quantities for two (2) pay items.
3) Revise RFP Statement to make required changes.
4) Revise B-Pages Proposal Instructions to make required changes.
5) Respond to bidder questions.
6) The proposal due date remains January 18, 2022, at 2:00 pm EST.
Request for Proposal Changes
1) Replace plan sheets A03, C01 through C04, C10, D03, M01 and M07 through M11.
2) Replace B-Pages (B-1 through B-7) pages.
3) Delete first sentence of the first paragraph on page 3 of the RFP Statement and substitute the following:
Submit two (2) unbound paper copies and one (1) CD-ROM (or a USB stick) copy of the
Price Proposal.
4) Delete Subsection 1.B.(b)(2) of the B-Pages Proposal Instructions (Page 3) and substitute the following:
(2) Documentation that shows direct experience of the Offeror, and/or experience of subcontractors that the Offeror proposes to utilize in the execution of this project. Submit documentation that shows direct experience of the Contractor/subcontractor in constructing precast concrete box girder segmental bridges by providing at least one (1), but no more than three (3) precast concrete box girder segmental bridge example projects completed in the past eleven (11) years similar in scope and size to the Laurel Fork Bridge project. Offerors are to include the experience of the entire prime and subcontracting team that will perform the work on this project.
Info Page 2 of 2
5) Respond to bidder questions:
Question: Page J-47 states a Maximum foot-print of 105’ X 30‘for the Optional Temporary
Bridge and 85’X 30‘Maximum foot-print on the temporary bridge for the South Staging area.
To achieve a 30’ open roadway, can our temporary bridge substructure be wider, if out of the
Buffer Zone?
Response: We don’t recommend modifying the widths of the temporary bridges even if their ends are outside of the buffer zone. The bridges are over the buffer zone, so any additional widths will be considered a disturbance. We have applied for permits with the plans as currently shown. The plans would need to be updated to show the footprint of the bridge, and the associated impacts to the trout buffer, and possibly additional wetland impacts would need to be calculated and included in the permits. If the contractor proposes changes that will result in additional disturbance, the contractor will be responsible for updating the environmental permits obtained by the government. The contractor would not get additional time for delays due to permitting.
Question: Page 3 of the Bid Schedule Instruction, Item 1.B.b.(2) states:
(2) Documentation that shows direct experience of the Offeror, and/or experience of subcontractors that the Offeror proposes to utilize in the execution of this project. Submit documentation that shows direct experience of the Contractor/subcontractor in constructing precast concrete box girder segmental bridges by providing at least one (1), but no more than three (3) precast concrete box girder segmental bridge example projects completed in the past five (5) years similar in scope and size to the Laurel Fork Bridge project. Can the window for example projects be expanded to include the Foothills Parkway Project PRA FOOT 8E17 Bridge
2 project Bridge from 2011? The referenced project is similar in scope and construction to the current project. The Blue Ridge Parkway over IH-26 is currently under construction, would this project currently under construction be considered for satisfying this specification requirement?
Response: Under an upcoming amendment (Amendment 004), the performance window will be expanded to count all projects that have been completed within the last 11 years, so the Foothills
Parkway Project PRA FOOT 8E17 Bridge 2 project Bridge from 2011 will be acceptable for inclusion. Since the Blue Ridge Parkway over I-26 is currently under construction, this project will not be considered an acceptable example project as the post-tensioning has not been completed while the above requirement clearly states that the projects have to be “completed”.
Question: Under Submittals on page 2 of the Request for Proposal it states:
Submit two (2) unbound paper copies and one (1) CD-ROM copy of the Price Proposal. Submit the Price Proposal separately from the Technical Proposal in a sealed envelope and clearly labeled as the “Price Proposal.” Will either a CD-ROM or USB memory stick be acceptable?
Response: A USB memory stick will be acceptable. This change will be added to the upcoming amendment (Amendment 004).
B - 1
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
A0060 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0080 15702-5000 SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM (BYPASS
PUMPING)
ALL LPSM $___LPSM_____ $____________
0004 A0100 15705-0100 SOIL EROSION CONTROL, SILT FENCE
3,150 LNFT $____________ $____________
A0120 15705-0300 SOIL EROSION CONTROL, SLOPE DRAINS
320 LNFT $____________ $____________
A0140 15705-0500 SOIL EROSION CONTROL, TEMPORARY CULVERT PIPE (18-INCH
EQUIVALENT DIAMETER ARCH)
165 LNFT $____________ $____________
A0160 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
140 LNFT $____________ $____________
A0180 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION
2 EACH $____________ $____________
A0200 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT
1 EACH $____________ $____________
A0220 15706-2200 SOIL EROSION CONTROL, FILTER BAG
1 EACH $____________ $____________
A0240 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
A0260 20101-0000 CLEARING AND GRUBBING
3.1 ACRE $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP-BLRI 2D17
Project Name:Blue Ridge Parkway Laurel Fork Bridge Replacement
B - 2
A0280 20301-1400 REMOVAL OF INLET
1 EACH $____________ $____________
A0300 20302-0800 REMOVAL OF FENCE, BARBED WIRE
170 LNFT $____________ $____________
A0320 20302-2100 REMOVAL OF PIPE CULVERT
35 LNFT $____________ $____________
A0340 20303-1500 REMOVAL OF PAVED WATERWAY, STONE
110 SQYD $____________ $____________
A0360 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
1,470 SQYD $____________ $____________
A0380 20304-2000 REMOVAL OF BRIDGE
ALL LPSM $___LPSM_____ $____________
A0400 20401-0000 ROADWAY EXCAVATION
300 CUYD $____________ $____________
A0420 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
1,840 SQYD $____________ $____________
A0440 20801-0000 STRUCTURE EXCAVATION
1,700 CUYD $____________ $____________
A0460 25102-0200 PLACED RIPRAP, METHOD A, CLASS 2
12 TON $____________ $____________
A0480 25102-0300 PLACED RIPRAP, METHOD A, CLASS 3
62 TON $____________ $____________
A0500 25501-0000 MECHANICALLY STABILIZED EARTH WALL (MODULAR BLOCK WITH
STONE MASONRY FACING)
3,220 SQFT $____________ $____________
A0520 25701-0200 CONTRACTOR FURNISHED MECHANICALLY STABILIZED EARTH WALL
DESIGN (MODULAR BLOCK WITH STONE MASONRY FACING)
ALL LPSM $___LPSM_____ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP-BLRI 2D17
B - 3
A0540 30101-4000 AGGREGATE BASE GRADING C OR D
1,750 TON $____________ $____________
A0560 31302-0000 AGGREGATE-TOPSOIL COURSE (VARIABLE DEPTH)
2,900 SQYD $____________ $____________
A0580 31302-0400 AGGREGATE-TOPSOIL COURSE, 4-INCH DEPTH
410 SQYD $____________ $____________
A0600 40101-0100 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL , PG 64-22, TYPE IV
PAVEMENT ROUGHNESS
460 TON $____________ $____________
A0620 40101-0900 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/4-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL , PG 64-22
205 TON $____________ $____________
A0640 41202-0000 TACK COAT
310 GAL $____________ $____________
A0660 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1
490 SQYD $____________ $____________
A0680 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE) (ABUTMENT BACKWALLS,
WINGWALLS)
195 CUYD $____________ $____________
A0700 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE) (PIER CAPS, BRACES)
230 CUYD $____________ $____________
A0720 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE) (PIER FOOTINGS)
410 CUYD $____________ $____________
A0740 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE) (ABUTMENT STEMS)
240 CUYD $____________ $____________
A0760 55202-2000 STRUCTURAL CONCRETE, CLASS D (AE), FOR APPROACH SLABS, TYPE 2
135 SQYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP-BLRI 2D17
B - 4
A0780 55235-0000 EXPANSION JOINTS (WINGWALL/MSE WALL)
97 LNFT $____________ $____________
A0800 55235-0000 EXPANSION JOINTS (MODULAR)
59 LNFT $____________ $____________
A0820 55401-1000 REINFORCING STEEL
158,000 LB $____________ $____________
A0840 55601-0500 BRIDGE RAILING, CONCRETE
1,090 LNFT $____________ $____________
A0860 55901-0000 MEMBRANE WATERPROOFING
1,580 SQYD $____________ $____________
A0880 56401-4000 BEARING DEVICE, DISK
8 EACH $____________ $____________
A0900 56501-0600 DRILLED SHAFT, 48-INCH DIAMETER (ROCK SOCKET)
170 LNFT $____________ $____________
A0920 56501-0600 DRILLED SHAFT, 48-INCH DIAMETER
63 LNFT $____________ $____________
A0940 56501-0900 DRILLED SHAFT, 72-INCH DIAMETER
120 LNFT $____________ $____________
A0960 56501-0900 DRILLED SHAFT, 72-INCH DIAMETER (ROCK SOCKET)
45 LNFT $____________ $____________
A0980 57502-0000 TEMPORARY BRIDGE (105 FEET BY 30 FEET)
ALL LPSM $___LPSM_____ $____________
A1000 57502-0000 TEMPORARY BRIDGE (85 FEET BY 30 FEET, OPTIONAL)
ALL LPSM $___LPSM_____ $____________
A1020 58601-0000 PRECAST SEGMENTAL CONCRETE (SUPERSTRUCTURE CASTING AND
TRANSPORT)
1,530 CUYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP-BLRI 2D17
B - 5
A1040 58601-0000 PRECAST SEGMENTAL CONCRETE (PIER CASTING, TRANSPORT, AND
ERECTION)
325 CUYD $____________ $____________
A1060 58602-0000 PRECAST SEGMENTAL CONCRETE (SUPERSTRUCTURE ERECTION)
ALL LPSM $___LPSM_____ $____________
A1080 58701-0000 POST-TENSIONING SYSTEM (PIERS)
ALL LPSM $___LPSM_____ $____________
A1100 58701-0000 POST-TENSIONING SYSTEM (SUPERSTRUCTURE)
ALL LPSM $___LPSM_____ $____________
A1120 60201-0600 18-INCH PIPE CULVERT (CONCRETE)
8 LNFT $____________ $____________
A1140 60201-1000 36-INCH PIPE CULVERT
26 LNFT $____________ $____________
A1160 60403-0900 INLET, FLH TYPE 4B
1 EACH $____________ $____________
A1180 60801-0300 PAVED WATERWAY, TYPE 3
155 SQYD $____________ $____________
A1200 61701-4000 GUARDRAIL SYSTEM SBTB
20 LNFT $____________ $____________
A1220 61702-0100 TERMINAL SECTION, TYPE SBT-BAT
2 EACH $____________ $____________
A1240 61707-2000 STRUCTURE TRANSITION RAILING, SBT SYSTEM
48 LNFT $____________ $____________
A1260 61901-1600 FENCE, CHAIN LINK, 48-INCH HEIGHT
65 LNFT $____________ $____________
A1280 61901-2100 FENCE, CHAIN LINK, 96-INCH HEIGHT
130 LNFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP-BLRI 2D17
B - 6
A1300 61902-0500 GATE, WOOD, 16 FEET WIDTH
1 EACH $____________ $____________
A1320 61902-3800 GATE, CHAIN LINK, 22 FEET WIDTH
2 EACH $____________ $____________
A1340 62002-0000 STONE MASONRY (ABUTMENT)
290 SQYD $____________ $____________
A1360 62010-1000 STONE MASONRY GUARDWALL
134 LNFT $____________ $____________
A1380 62010-7000 STONE MASONRY PARAPET (APPROACH SLAB PARAPET)
86 LNFT $____________ $____________
A1400 62011-0700 STONE MASONRY HEADWALL FOR 36-INCH PIPE CULVERT
2 EACH $____________ $____________
A1420 62402-0200 FURNISHING AND PLACING TOPSOIL, 3-INCH DEPTH
3.1 ACRE $____________ $____________
A1440 62501-0000 TURF ESTABLISHMENT
3.1 ACRE $____________ $____________
A1460 62902-0800 ROLLED EROSION CONTROL PRODUCT, TYPE 2.D
3.1 ACRE $____________ $____________
A1480 63316-1000 REMOVE AND RESET SIGN (AND MILE MARKER)
2 EACH $____________ $____________
A1500 63401-2300 PAVEMENT MARKINGS, TYPE L, SOLID
2,850 LNFT $____________ $____________
A1520 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
24 EACH $____________ $____________
A1540 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
2 EACH $____________ $____________
A1560 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
70 LNFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP-BLRI 2D17
B - 7
0004 A1580 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
1,800 LNFT $____________ $____________
A1600 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
1,100 SQFT $____________ $____________
A1620 63701-0000 FIELD OFFICE
1 EACH $____________ $____________
A1640 65001-1000 CONSTRUCT AND MAINTAIN DIVERSION (TEMPORARY ACCESS ROADS)
ALL LPSM $___LPSM_____ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP-BLRI 2D17
N
AREA PATTERN
Paved waterway, type 3
VariesVar.
Aggregate surface
Cubic yardcuyd
Ordinary high water markOHWM
Buffer zone
Steel-backed timber guardrailSBT
AmendmentAMD
PROJECT SPECIFIC SYMBOLS AND ABBREVIATIONS:
AMD #4 - Added new abbreviation
NO. DATE BY REVISIONS
12/08/21
Siou
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION BLUE RIDGE PARKWAY
SYMBOLS AND ABBREVIATIONS
AMENDMENT #4 1
NOTE:
Fiber Roll or Wattle
North Arrow
Fence
Gate with Fence
Cattleguard
Guardrail
Retaining Wall
Concrete Barrier
Slope Stake Limits
Delineators
Signs (single, double post; portable)
Transition
Toe of Fill
Top of Cut
Pipe Culvert (arrow shows flow)
Pipe Culvert with End Section
Pipe Culvert with Headwall
Underdrain
Pipe Culvert with Drop Inlet
Box Culvert
Underground Utilities
Overhead/Above Ground Utilities
STEAM = steam, T = telephone, TV = CATV, W = water
P = power, SA = sanitary sewer, SD = storm drain, SS = storm sewer, FM = force main, FO = fiber optic, G = gas, IRR = irrigation, O = oil, Light, Support w/Anchor)
Poles (Power, Telephone, Joint Use, Miscellaneous Utility Features
UP = transformer or junction box, WF = water fountain
EM = electric meter, T = telephone pedestal, TV = CATV pedestal, Building
Right-of-Way Line with Monument
Permanent Easement
Construction Easement
Riprap
EXISTING PROPOSED
DI
Pavement Removal / Roadway Obliteration
Full Depth Pavement
Sidewalk Asphalt/Concrete
Mill and Overlay
Overlay
Silt Fence
Diversion Berm
Drainage Divide
Check Dam
Limits of Disturbance
Sheet 2 of 2
:2
A
M
D e c e m b e r
S
H E
E T f h f l1 f il e s e r v e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d \P r o j_
D e v \C
A D
D \O p e n R o a d
\A m e n d m e n t
\A
A
B
L R
I D s y m
A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 A03
NPS Drwg. No. 601/152750 NPS PMIS No. 186570
Sheet 1 of 2
AMD #4 - Revised quantity
12/06/21
U.S. DEPARTMENT OF TRANSPORTATION
TABULATION OF QUANTITIES
BLUE RIDGE PARKWAY
1AMENDMENT #4
:2 e c e m b e r
C
C f h f l1 f il e s e r v e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d
\P r o j_ D e v
\C A
D D
\O p e n
R o a d
\A m e n d m e n t
\C
B
L R
I
D ta b
A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 C01
Sheet 2 of 2
12/06/21
TABULATION OF QUANTITIES
1AMENDMENT #4
:2 e c e m b e r
C
C f h f l1 f il e s e r v e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d
\P r o j_ D e v
\C A
D D
\O p e n
R o a d
\A m e n d m e n t
\C
B
L R
I
D ta b
A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 C02
Sheet 1 of 8
AMD #4 - Added quantity
11/26/21
SUMMARIES AND SCHEDULES
21AMENDMENT #4
:3 e c e m b e r
C
C f h f l1 f il e s e r v e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d
\P r o j_ D e v
\C A
D D
\O p e n
R o a d
\A m e n d m e n t
\C
B
L R
I
D s u m s c h
A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 C03
Sheet 2 of 8
1AMENDMENT #4
:3 e c e m b e r
C
C f h f l1 f il e s e r v e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d
\P r o j_ D e v
\C A
D D
\O p e n
R o a d
\A m e n d m e n t
\C
B
L R
I
D s u m s c h
A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 C04
Sheet 8 of 8
AMD #4 - Deleted quantity
21AMENDMENT #4
:5 e c e m b e r
C
C f h f l1 f il e s e r v e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d
\P r o j_ D e v
\C A
D D
\O p e n
R o a d
\A m e n d m e n t
\C
B
L R
I
D s u m s c h
A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 C10
18" CMP Buried
RCA
INV 2884.1'
Acr eag e 0 .75 Lot n/a
DB/P
age
8/1 Pla t/Pa ge 4/3
74A
Owner : W
ILHELM,
DALE F
& K
ATHY B
Par cel
ID 1
4 0
Acreage 1 Lot n/a DB/Page 338/1134 Plat/Page 4/374A
Owner: WILHELM, DALE F & KATHY B
Parcel ID 14437024 002
Pav ed
Wate r W ay
0 2
0 2900
OHWM 2841.95'
OHWM 2835.12'
OHWM 2835.61'
OHWM 2856.86'
OHWM 2853.92'
0 2
1"
PVC (
Unk no wn U tl)
1.5 " P
VC (
Unk no wn U tl)
IN
V
.2 1'
IN
V
.8 7'
CMP
"x
.1 4'
C
M P
IN
V
.4
IN
V
.3
P
V C
IN
V
.3
IN
V
.3
RCA
18" CMP BuriedINV 2884.1'
C
M P
IN
V
.5
IN
V
.7
0 2900
R C
P x .2
I N
V
.2
Pav ed
Wate r W ay
C o v e re d
.5 'P
C
R C
P x .1
I N
V
.3
'29
I N
V
.4
I N
V
.3
N
SR 1613 that connects to Route 18 (Sparta Road).
access road (Agricultural access), use the east end of
For access to and from the temporary construction7.
contours as directed by the CO.
wide, and regrade the area to the preconstruction the temporary construction access road, the 30-foot
When construction activities are complete, remove6.
aggregate base as directed by the CO.
10-foot wide road with a minimum of 4-inch depth access road (Agricultural access), and restore to a
2 feet on each side of the 14-foot temporary construction
When construction activities are complete, remove5.
construction. See M sheets for more information.
Maintain Agricultural access at all times during4.
according to Section 575 at the Contractor's option.
Construct 85 ft (length) x 30 ft (width) temporary bridge3.
according to Section 575.
Construct 105 ft (length) x 30 ft (width) temporary bridge2.
and M sheets for more information.
See temporary construction access Typical Sections1.
riprap, class 3, at outlet side.
stone masonry headwalls. Place 14 tons of
Install 36" x 26' of pipe culvert and 2
Remove 22' of existing pipe culvert.
See Note 4
Notes:
Existing highway easement
Existing NPS boundary varies, area= 12,010 sqft. See Note 6.
construction access road, 30-ft width and
50+40.0 - 52+77.3, construct temporary
14-ft width, area= 1,937 sqft. See Note 5.
construction access road (agricultural access), 10+00.0 - 11+38.4, construct temporary varies, area= 11,079 sqft. See Note 6.
construction access road, 30-ft width and
53+82.3 - 58+29.5, construct temporary road, 30-ft width, area= 4,865 sqft. See Note 6.
Construct temporary construction access
Staging Area 2
Blue Ridge Parkway
14-ft width, area= 9,101 sqft. See Note 5.
construction access road (agricultural access), 11+68.8 - 18+00.5, construct temporary
See Note 2 elliptical pipe culvert equivalent diameter arch or
Install temporary 18" x 134'
See Note 3
S ta g in g A re a
Trail. Do not disturb trail.
Existing Mountain Sea
Do not disturb existing steps.
Existing trail steps to remain.
Install gate, 16-ft wide construction exit
Construct stabilized barbed wire
Remove 170' of existing fence, Do not disturb fence.
Existing fence to remain.
La ur el F or k C re ek
Wetlands (typ)
To SR 18
See Note 6
Unnamed Creek
Unnam ed Creek of existing stone paved waterway.
118+33 to 119+40 LT, remove 107'
SCALE IN FEET
0 50 100
AMD #4 - Added buffer zone patterns
AMD #4 - Added Unnamed Creek label
AMD #4 - Revised access road area
AMD #4 - Deleted callout
11/29/21
U.S. DEPARTMENT OF TRANSPORTATION
ACCESS ROADS
TEMPORARY CONSTRUCTION
.0
P
C
.5
C
C
C
C
.0
P O
B
.1
P O
E
6 1 7 1 8 1
11+02.17 PC
11+ 19.
PT
11+88.11 PC
PT
14+ 38.39
PC
15+06.42
PT
15+85.40
PC
16+15.34 PT
16+66.48 PC
17+13.3
PT
10+57.46 PT
11+ 27.
PC
11+47.28 PT
13+ 72.27
.0
PO
B
18+11.7
POE
.6
51+89.96 PT
.8
.2
.0
PO
B
.7
P
E
:3 e c e m b e r
D f h f l1 f il e s e r v e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d
\P r o j_ D e v
\C A
D D
\O p e n
R o a d
\A m e n d m e n t
\D
B
L R
I
D
C o n s t_
A c c e s s
A M
D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 D03
NPS Drwg. No. 601/152750 NPS PMIS No. 186570
So uth La ure l F ork Rd (S
R 1
3)
1AMENDMENT #4 3
2 4
Stabilize all areas that are disturbed due to the removal of sediment control devices-
Remove silt fence after all upslope areas are stabilized and vegetation is well established.-
Inspect, clean, and repair all culvert outlet protection, riprap basins, and stabilized riprap slopes-vegetation has not established
Where necessary, replace eroded topsoil and re-apply permanent turf establishment to disturbed areas where-permanently stabilize disturbed areas:
After the completion of roadway construction and culvert replacement, do the following as directed by the CO to or 1-202-267-2675.
Report spills large enough to discharge to surface water to the National Response Center (NRC) at 1-800-424-8802-waste materials into the on-site dumpsters. Dispose of material according to Federal, State, and local regulations.
appropriate and clearly marked containers away from other non-waste materials. Do not dispose of hazardous conduct these activities in a covered area to avoid contact with storm water. Store all hazardous waste materials in could generate spills, leaks, and hazardous wastes like motor oil, diesel, gasoline, and battery fluid. If feasible, Hazardous waste will not be generated from normal construction activities. Equipment fueling and maintenance-
Collect and store all waste in dumpsters, or in metal or plastic drums as appropriate.
Solid waste resulting from the construction will consist of construction debris, garbage, and empty containers.-
Provide watering for dust control within the construction limits, on active haul roads, and in pits and staging areas.-
Cover stockpiled soil with plastic or surround it with silt fence.
Stockpile topsoil stripped from the construction area in an area that will not interfere with construction phases.-
In general, preserve existing vegetation, trees, and shrubs.-of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials.
Inspect and maintain regularly all mechanized equipment used in or near surface waters to prevent contamination-
Direct storm water to vegetated buffer areas and do not discharge directly into surface waters.-measures.
Do not allow any construction equipment to operate on or access the down-slope side of the perimeter control-
Do not allow construction vehicles to track sediment outside the project limits.-
Do not drive construction equipment across flowing waterways.-type, size, or location of any control or practice without prior approval from the CO.
Install all erosion and sediment control measures as directed by the Contracting Officer (CO). Do not modify the-
Employ temporary stabilization practices in incremental stages as construction proceeds.-control.
control measures with roadway activities to assure economical, effective, and continuous erosion and sediment erosion, particularly at the toe of fills. Coordinate the installation, use, and removal of erosion and sediment
Install fiber roll per Detail 157-04 in all areas of ground disturbance where sheet flow may cause-in conjunction with the construction of this project. These include:
Temporary Best Management Practices (BMP) to reduce erosion as a result of project work will be implemented the erosion and sediment controls.
Requirements. The attached Erosion and Sediment Control Plan, M04 provides details regarding the installation of
Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14 and in the Special Contract
Erosion Control and Turf Establishment measures listed in this narrative are defined and outlined in the Standard
EROSION AND SEDIMENT CONTROLS
0.85. The Runoff Coefficient after construction will be 0.85. See Sheet M05 and M06 for the Soil Maps.
the reconstructed stone masonry guardwall and paved waterway. The Runoff Coefficient prior to construction is
Blue Ridge Parkway is a paved roadway. Approximately 0.004 acres of new impervious surface will be created by
3.9 acres.
reconstruction, and temporary access road construction. The total disturbed area for the project is approximately
Soil disturbing activities will mainly include clearing and grubbing for bridge replacement, roadway approach
SUMMARY
The receiving water is Laurel Fork Creek. The project is located in Ashe County, North Carolina.
micellaneous works.
aggregate base, asphalt paving, stone masonry guardwall, steel-backed timber guardrail, drainage, and other
This work includes Laurel Fork Bridge replacement, Mechanically Stabilized Earth wall construction, grading, This project consists of the reconstruction of a 0.1-mile segment of Blue Ridge Parkway over Laurel Fork Creek.
PROJECT DESCRIPTION
project.
Provide the CO with copies of the inspection and maintenance records every month, and at the completion of the of inspection and repairs.
If visible sedimentation is found off-site, take immediate measures to clean up the site. Maintain written records damaged shields to prevent debris from entering waterways.
Debris shields - Inspect, check, and remove accumulations daily from the debris shields. Repair or replace any needed after the rainfall, or as directed by the CO.
Slope drain (plastic lined waterway) - check the slope drain daily for punctures, breaks, or other damage. Repair as capacity.
for capacity. Immediately cease pumping and replace damaged filter bag, or bag that have reached their rated Filter bag - check the filter bag daily during the dewatering operations for punctures, tears, or other damage, and staples and stakes to make sure they are secured in the ground.
and erosion beneath the matting. Replacement of matting may be necessary if damaged by equipment. Check and then up the side slopes. Inspect matting after every significant rainfall (0.5 inch or greater) even for damage slope. Do not stretch matting. For culvert inlets and ditches, install matting along the bottom of the ditches first Rolled erosion control product - Unroll and lay matting out down slope face (in direction of flow). Anchor at top of or damaged. Repair or replace split, torn, unraveled, or slumping fiber rolls.
Check dam (fiber roll) - inspect to ensure that the check dams remain firmly anchored in place and are not crushed
Repair as needed after the rainfall, or as directed by the CO.
iber roll inlet protection - check the inlet protection daily for punctures, breaks, or other damage, and capacity.
Silt fence-duration) In general check all erosion and sediment control measure daily, after every significant (0.5 inch in 24-hour
Section 157, details shown in the plans, and the individual permitting requirements.
Unless stated otherwise, construct and maintain all vegetated and structural erosion control practices according to
MAINTENANCE AND INSPECTION PROCEDURES
vegetation was not established. Inspect, clean and repair inlet protection, riprap basins and stabilized channels.
Where necessary, replace eroded topsoil and re-applay permanent turf establishment ot disturbed areas where
Remove all other perimeter controls when directed by the CO.- Remove silt fence only after all upslope areas are stabilized and vegetation is well established.-where vegetation has not established.
Where necessary, replace eroded topsoil and re-apply permanent turf establishment to disturbed areas- Finish grading, place riprap, and apply permanent turf establishment to any remaining disturbed areas.-
After completion of roadway construction do the following as directed by the CO:
PHASE III- Final Construction / Stabilization
Apply temporary turf establishment to stockpiles remaining in place longer than 14 days, or when directed by the CO.
Provide silt fence around all stockpiled excavated roadway material.
Do not allow ponded water to encroach into the travel lanes.
At the end of each day’s grading operations, shape earthwork to minimize and control erosion from storm runoff.
according to Section 625. These areas may include the existing piers.
As soon as practical, but not to exceed 7 calendar days, apply permanent turf establishment to the finished slopes or as directed by the CO. These areas may include the disturbed areas along the construction access roads.
Apply temporary turf establishment in completed disturbed areas that will remain exposed for over 7 calendar days, problems.
The CO may direct the installation of certain controls in order to forestall or mitigate potential or existing erosion approval before installing any control not specified in the SWPPP/ECN.
diversion berm bypass pumping, and filter bag for dewatering at the pipe culvert installation. Obtain the CO’s and Sediment Control Plans, sheets M07-M10. Install check dams (fiber roll) in ditches along the roadway, temporary Apply intermediate controls during rough grading operations. Install silt fence in areas called out on the Erosion
PHASE II: Intermediate Controls
Install the debris shields before the bridge removal operation according to Section 203.
(fiber roll), slope drains (plastic lined waterway), and other approved measures outside the construction limits.
ensure that disturbed sediment does not leave the project site. Perimeter controls include silt fence, check dams Prior to any clearing, grubbing, excavation, and bridge demolition and removal, construct perimeter controls to
PHASE I: Establish Perimeter Controls
EROSION & SEDIMENT CONTROL CONSTRUCTION SEQUENCE
Requirements for the fertilizing, seeding, and mulching requirements.
See Permanent Revegetation Plan, Sheet M11, for the seed rates. See Section 625 in the Special contract Stabilize 3.1 acres as a result of this project. The area will be prepared for turf establishment with topsoil and mulch.
VEGETATIVE STABILIZATION
Sheet 1 of 4
U.S. DEPARTMENT OF TRANSPORTATION
NARRATIVE
EROSION AND SEDIMENT CONTROL
BLUE RIDGE PARKWAY
11/26/21 Siou removal"
AMD #4 - Inserted "bridge demolition and fh fl fi le s e rv e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d \P ro j_
D e v \C
A D
D \O p e n R o a d
-1
-2
\A m e n d m e n t \M
-M
B
L R
I2 D n a r-
P e rm it A
M D
.d g n
:4 e c e m b e r
D fh fl fi le s e rv e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d \P ro j_
D e v \C
A D
D \O p e n R o a d
-1
-2
\A m e n d m e n t \M
-M
B
L R
I2 D n a r-
P e rm it A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 M01
802885
NAIL
Covered
32.51'PC
NAIL
R C
P x .1
TBAR
TBAR
I N
V
.3
MP
TBAR
NAIL
TBAR
NAIL
40789
NAIL
IN
V
.3
40788
NAIL
x .7
'R
C P
TBAR
TBAR
NAIL
TBAR
TBAR
I N
V
.3
IN
V
.0
N
435' of temporary plastic fence
108+30.0 - 112+41.7 RT, install install inlet protection
109+28 RT,
install 332' of silt fence
108+30 - 111+60 LT,
line waterway)
Install slope drain (plastic check dams (fiber roll), 50' spacing
109+83 - 110+83 RT, install 3
BLUE RIDGE PARKWAY
SOUTH LAUREL FORK ROAD
108+30.0
17.0' LT
108+30.0
17.0' RT
109+40.0
17.0' LT
109+81.0
42.0' LT
110+40.0
45.0' RT
109+73.0
36.2' RT
108+73.0
32.0' RT
NPS boundary
108+73.0
17.0' RT
SCALE IN FEET
0 25 50
Sheet 1 of 4
AMD #4 - Revised temporary plastic fence length
U.S. DEPARTMENT OF TRANSPORTATION
PLAN
EROSION AND SEDIMENT CONTROL
C
.0
P
:1 e c e m b e r
M
S h e e t] f h f l1 f il e s e r v e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d \P r o j_
D e v \C
A D
D \O p e n R o a d
\A m e n d m e n t
\M
M
B
L R
I D e s p la n P e r m it A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 M07
OHWM 2835.12'
OHWM 2835.61'
TBAR
NAIL
NAIL
NAIL2
NAIL
NAIL
NAIL
IN
V
.2 1'
IN
V
.8 7'
CMP
"x
.1 4'
OHWM 2856.86'
OHWM 2853.92'
NAIL
NAIL
NAIL
NAIL
TBAR
TBAR
TBAR
NAIL
TBAR
N
143' of temporary plastic fence
111+60.0 - 113+00.7 LT, install
75' of silt fence
111+91.0, install
75' of silt fence
112+19.0, install
93' of silt fence
112+54.0, install install 122' of silt fence
113+00.7 - 114+10.5 LT,
install 229' of silt fence
51+11.7 - 51+15.8 LT to RT, 80' of silt fence
111+65, install
Creek bank
Edge of buffer zone
Do not disturb trail.
Existing Mountains-to-Sea Trail.
fence
126' of temporary plastic
10+00 - 11+20.5 LT, install of silt fence
11+65.6 - 12+96.1 RT, install 245'
Staging Area 2
Staging Area 1 of riprap, class 2
Place 4 tons road, 14-ft wide
Temporary construction access
115+70.0, install 75' of silt fence
Temporary Bridge
160' of temporary slope drain
110+83.0 - 112+43 RT, install
170' of temporary slope drain
54+53.6 - 56+28.4 RT, install
BLUE RIDGE PARKWAY
information.
See Details E157-09 and E157-10 for more temporary diversion berm bypass pumping.
pipe culvert replacement work area. Install
Install filter bag for the dewatering from the
Notes:
1. 51+45.8 to 52+89.1 RT, install 120 ft of silt fence.
2. Apply permanent turf establishment to the pier finished slope areas within 7 calendar days, or as directed by the CO.
See Note 2.
Existing piers. (typ.)
dams (fiber roll), 50' spacing.
12+38.0 - 13+35.0 LT, install 3 check
25'
Place 4 tons of riprap, class 2
25'
25' install 131' of silt fence
10+00.0 - 11+30.8 RT,
Wetlands
Wetlands
Tem porary Bridge
L A
U R
E L F
O R
K C
R E E
K
111+60.0
45.0' LT
113+00.7
54.6' LT
112+17.1
32' LT
113+00.7
32.6' LT
10+00.0
16.6' RT
10+00.0
18.0' LT
dam (fiber roll) install 1 check
53+88.0 LT,
Place 4 tons of riprap, class 2
11+30.8
16.6' LT
11+20.5
18.0' LT
134' of temporary slope drain
54+64.1 - 55+94.0 LT, install
50+13.4
6.5' LT
50+22.3
7.2' RT
51+11.7
51.5' LT
51+06.9
48.6' RT
13+48.4
184.6' RT
51+72.5
49.4' RT
12+12.3
55.4' RT
12+49.0, 18.0' LT
12+31.5
13.0' RT
See Note 1
163.3'
13+94.2
23.0' RT
30'
46'
40.8'
16.7'
20.3'
41'
41'
13+20.0, 18.0' LT
13+72.3
23.0' RT
12+96.1, 31' RT
13+17.1, 13.0' RT
11+96.3
86.4' RT
30'
14+34.5
7.0' RT
13+72.3
46.2' RT
12+04.6
77.2' RT
of silt fence
13+09.3 - 14+49.8 RT, install 258'
25'
CREEK
UNNAMED
14+49.8
168.8' RT
12+19.1
47.2' RT
Edge of buffer zone
25'
SCALE IN FEET
0 25 50
Sheet 2 of 4
AMD #4 - Replaced entire Sheet M08
U.S. DEPARTMENT OF TRANSPORTATION
AMENDMENT #4 1
C
11+02.17 PC
11+ 19.
PT
11+88.11 PC
10+57.46 PT
11+ 27.
PC
11+47.28 PT
.0
PO
B
.6
51+89.96 PT
.0
PO
:1 e c e m b e r
M
S h e f h f l1 f il e s e r v e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d \P r o j_
D e v \C
A D
D \O p e n R o a d
\A m e n d m e n t
\M
M
B
L R
I D e s p la n P e r m it A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 M08
IN
V
3.
NAIL
TBAR
R C
P x .2
I N
V
.2
TBAR
Paved Water Way
TBAR
51050
NAIL
TBAR
TBAR
TBAR
51069
NAIL
TBAR
51070
NAIL
51071
NAIL
50982
NAIL
I N
V
.4
N install 419' of silt fence
115+79.6 - 119+86.0 RT,
install 86' of silt fence
116+14.0, install 93' of silt fence
116+57.0, install inlet protection
118+30.0 LT,
dams (fiber roll), 50' spacing
117+30.0 - 117+80.0 LT, install 2 check
Existing Mountains-to-Sea Trail
BLUE RIDGE PARKWAY
438' of temporary plastic fence
115+56.9 - 119+86.0 LT, install
117+66.2
45' RT
118+20.0
17.0' RT
119+86.0
17.0' RT
118+72.3
10.0' LT
119+39.4
9.9' LT
119+86.0
18.5' LT
58+45.8
27.43' LT
58+01.6
32.0' LT
15'
15'
15'
5' dams (fiber roll), 50' spacing
55+97.0 - 57+55.0 LT, install check
56+99.5
26.5' LT
55+88.4
20.1' LT
57+65.6
32.0' LT
58+49.7
15.5' LT
Edge of buffer zone
25'
25'
UN
N
AM
ED
CREEK
SCALE IN FEET
0 25 50
Sheet 3 of 4
AMD #4 - Added edge of buffer zone
AMD #4 - Added buffer zone widths
AMD #4 - Added Unnamed Creek label
U.S. DEPARTMENT OF TRANSPORTATION
AMENDMENT #4
31 2
C
C
C
.1
P
:1 e c e m b e r
M
S h e f h f l1 f il e s e r v e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d \P r o j_
D e v \C
A D
D \O p e n R o a d
\A m e n d m e n t
\M
M
B
L R
I D e s p la n P e r m it A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 M09
NAIL
TBAR
NPS 25
60873
NPS 24-A
60928
NAIL
NPS 24
60929
NPS 23
60930
TBAR
TBAR
TBAR
Parce l ID 1
44370 24 00
Owner: W
ILHELM, DALE F &
KATHY B
Acrea ge 0.7
5 Lot n/a D
B/Pag e 338
/1132 Plat/P age 4 /374A
Acreage 1 Lot n/a DB/Page 338/1134 Plat/Page 4/374A
OHWM 2856.86'
OHWM 2853.92'
N
Do not disturb trail.
Existing Mountains-to-Sea Trail.
not disturb existing trail and steps.
Existing Mountains-to-Sea Trail. Do access road
Temporary construction easement
Existing highway
Existing NPS boundary
Sou th L aur el F ork Ro ad
(SR 1
Wetlands
15+12.6, 13.0' RT
road, 14-ft wide
Temporary construction access dams (fiber roll), 50' spacing.
13+50.0 - 16+00.0 LT, install 6 check
Staging Area 2
13+28.2, 36' RT
install 531' of silt fence
14+62.3 - 18+04.4 RT,
13+42.6, 36' RT
13+48.2, 36' RT
13+60.3, 18' RT
13+59.8, 36' RT
17+15.1, 9.0' LT
17+59.9, 13.0' RT
17+63.0, 7.9' RT
17+78.1, 13.0' RT
18+04.4, 19.5' RT
17+75.0, 8.5' RT
17+11.5, 18.0' LT
17+82.7, 15.1' LT
17+87.1, 18.5' LT
17+95.5, 19.3' LT
467' of temporary plastic fence
13+48.2 - 17+95.5 LT, install
123' of temporary plastic fence
12+49.0 - 13+42.6 LT, install dams (fiber roll), 32' spacing.
17+00.0 - 17+95.0 LT, install 3 check
17+80.0, 7.0' RT
183.2' RT
14+83.9
25' (typ.)
U N
N A
M
ED
CREEK
Edge of buffer zone
SCALE IN FEET
0 25 50
Sheet 4 of 4
AMD #4 - Replaced entire Sheet M10
U.S. DEPARTMENT OF TRANSPORTATION
S °2
'0 "W
S '1
W
S '1
W S '5
W
15+06.42
PT
15+85.40
PC
16+15.34
PT
16+66.48
PC
17+13.33 PT
+96
18+11.79POE
:4 e c e m b e r
M
S h e f h f l1 f il e s e r v e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d \P r o j_
D e v \C
A D
D \O p e n R o a d
\A m e n d m e n t
\M
M
B
L R
I D e s p la n P e r m it A
M D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 M10
TBAR
NAIL
NAIL
NAIL2
0 2
NAIL
1"
PVC (
Unk no wn U tl)
1.5 " P
VC (
Unk no wn U tl)
NAIL
NAIL
NAIL
NAIL
IN
V
.2 1'
IN
V
.8 7'
CMP
"x
4'
C
M P
IN
V
.4
IN
V
.3
P
V C
IN
V
.3
IN
V
2855TOP
NAIL
NAIL
NAIL
NAIL
RCA
18" CMP BuriedINV 2884.1'
NAIL
C
M P
IN
V
.5
IN
V
.7
TBAR
0 2900
TBAR
TBAR
50980
NPS-9-40
BRASS
PRC
60287
NPS 25
60873
NPS 24-A
60928
NAIL
NPS 24
60929
NPS 23
60930
TBAR
TBAR
TBAR
PRC
60817
R C
P x .2
NAIL
TBAR
TBAR
TBAR
TBAR
TBAR
I N
V
.2
NAIL
50981
2-D29
NPS-9-40-USDI
BRASS
TBAR
Pav ed
Wate r W ay
C o v e re d
.5 'P
C
TBAR
NAIL
TBAR
TBAR
TBAR
NAIL
TBAR
NAIL
R C
P x .1
TBAR
TBAR
I N
V
.3
TBAR
NAIL
TBAR
NAIL
TBAR
NAIL
40789
NAIL
40788
NAIL
TBAR
TBAR
NAIL
TBAR
TBAR I
N
V
.4
I N
V
.3
Acr eag e 0 .75 Lot n/a
DB/P
age
8/1 Pla t/Pa ge 4/3
74A
Owner : W
ILHELM,
DALE F
& K
ATHY B
Par cel
ID 1
4 0
Acr eag e 1 Lot n/a
DB/P
age
8/1 Pla t/Pa ge 4/3
74A
Owner : W
ILHELM,
DALE F
& K
ATHY B
Par cel
ID 1
4 0
N
Turf shoulder seed mix
Virginia Creeper seed mix
Riparian Meadow seed mix
Upland Meadow seed mix
Seed Mixes:
Area= 19,569 sqft
Area= 1,265 sqft
Area= 2,247 sqft
Area= 2,720 sqft
Area= 2,752 sqft
Area= 24,824 sqft
Area= 33,862 sqft
Area= 2,421 sqft
Area= 1,856 sqft
Area= 1,514 sqft
Area= 2,395 sqft
Area= 1,397 sqft
Area= 26,159 sqft
Area= 5,387 sqft
Wetlands
Wetlands
Wetlands
Wetlands
Wetlands
Area=8,609 sqft
L A
U R
E L F
O R
K C
R E E
K
Area= 671 sqft
UN
N
AM
ED
CREEK
SCALE IN FEET
0 50 100
So uth La ure l F ork Rd
Blu e R idg e P ark way
AMD #4 - Added buffer zone patterns
AMD #4 - Added Unnamed Creek label
AMD #4 - Revised area
U.S. DEPARTMENT OF TRANSPORTATION
PERMANENT REVEGETATION
AMENDMENT #4 31 2
C
C
C
C
C
.0
P
.1
P
6 1 7 1 8 1
:2 e c e m b e r
M f h f l1 f il e s e r v e .f lh d
.f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \b lr i\ d
\P r o j_ D e v
\C A
D D
\O p e n
R o a d
\A m e n d m e n t
\M
B
L R
I
D
L a n d s c a p in g
A r e a s
A M
D
.d g n
STATE PROJECT
NUMBER
SHEET
NC NP-BLRI 2D17 M11
| NP-BLRI2D17_Amendment-Plan_Sheets.pdf |
| A02 |
| C01 |
| C02 |
| C03 |
| C04 |
| C10 |
| D03 |
| M01 |
| M07 |
| M08 |
| M09 |
| M10 |
| M11 |
File details come from the government source that posted it. Updated .