This amendment modifies a solicitation for landslide repair services on PR-10 in Utuado, Puerto Rico. The project involves embankment reconstruction, reinforced soil slope construction, drainage installation, landslide stabilization, retaining walls, soil nailing, box culverts, pavement restoration, guardrails, bridges, and other work. The amendment advises that Executive Order 14026 establishing a $15 minimum wage for federal contractors applies. It also provides responses to bidder questions and reschedules both technical and price proposals to be due on January 6, 2022.

View the file

Other files

File Type Posted
Amendment 0007 - PR ER PRMNT RPR(10).pdf PDF
Amendment 0006 - PR ER PRMNT RPR (10).pdf PDF
Amendment 0004 - PR ER PRMNT RPR (10).pdf PDF
Amendment 0003 - PR ER PRMNT RPR (10).pdf PDF
Amendment 0002 - PR ER PRMNT RPR (10).pdf PDF
Amendment 0001 - PR ST ER PRMT RPR(10).pdf PDF
Plans 826579 - PR ER PRMNT RPR(10).pdf PDF
Utility Endorsement_PREPA.pdf PDF
Report - Asbestos_AC-827579 Km 44.7 thru Km 45.2 Utuado.pdf PDF
Plans 827579 - PR ER PRMNT RPR(10)_Part 2.pdf PDF
Report - Lead_AC-827579 Km 44.7 thru Km 45.2 Utuado.pdf PDF
Plans 828579 - PR ER PRMNT RPR(10)_Part 1.pdf PDF
Categorical Exclusion Form (NEPA)_827579.pdf PDF
Report - Geotechnical_HWY_5 and 6_AC-826579.pdf PDF
PRHTA Standard Drawings.pdf PDF
PRHTA Material Testing Schedule.pdf PDF
Report - Lead and Asbestos_AC-826579.pdf PDF
Report - Geotechnical_HWY_14_AC-828579.pdf PDF
Report - Geotechnical_HWY_9_AC-827579.pdf PDF
Categorical Exclusion Form (NEPA)_828579.pdf PDF
Categorical Exclusion Form (NEPA)_828579_Appendices.pdf PDF
RFP Solicitation - PR ER PRMNT RPR(10).pdf PDF
ADV_Offerors Qualifications Form.doc DOC document
USFWS Conservation Measures.pdf PDF
Report - Geotechnical_HWY_8_AC-827579.pdf PDF
Report - Asbestos_AC-827579 Km 46.7 thru Km 47.5 Utuado.pdf PDF
Plans 828579 - PR ER PRMNT RPR(10)_Part 2.pdf PDF
Plans 827579 - PR ER PRMNT RPR(10)_Part 1.pdf PDF
PRHTA Special Provisions applicable to the project.pdf PDF
Report - Asbestos_AC-828579.pdf PDF
Report - Lead_AC-827579 46.7 thru Km 47.5 Utuado.pdf PDF
Categorical Exclusion Form (NEPA)_827579_Appendices.pdf PDF
VETS-4212 Form.pdf PDF
Utility Endorsement_PRASA.pdf PDF
Plans 828579 - PR ER PRMNT RPR(10)_Part 3.pdf PDF
Categorical Exclusion Form (NEPA)_826579.pdf PDF
Report - Lead and Asbestos_AC-828579.pdf PDF
DTOP Manual de Senales de Transito (MST).pdf PDF
PRHTA Standard Specifications.pdf PDF
ADV_Subcontracting Plan - PR ER PRMNT RPR(10).doc DOC document
Report - Asbestos_AC-826579.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

693C7322R000005 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ASHBURN VA 20147

ATTN: CONSTRUCTION

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

ASHBURN VA 20147

ATTN: ACQUISITIONS

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

See Block 1412/10/20210005

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

10/07/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project PR ER RPMNT RPR(10)

The purpose of this Amendment is to:

1) Advise Offerors that Executive Order 14026 raising the minimum wage for workers performing on or in connection with covered federal contracts to $15.00 per hour will apply to this contract. For more information refer to https://www.dol.gov/agencies/whd/government-contracts/eo14026.

2) Provide a summary of responses to questions/clarifications asked by potential bidders.

No additional questions will be considered for this solicitation after the issuance of this amendment.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

693C7322R000005/0005

3) Reschedule RFP Proposal Package (both Technical and Price Proposals) due date to

January 6, 2022 at 2:00 p.m. EST.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Amendment No. 0005

Info Page 1 of 1

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Project PR ER PRMNT RPR(10)

Puerto Rico Highway and Transportation Authority Landslide Repairs on PR-10 in the Municipality of Utuado

Solicitation # 693C73-22-R-000005

The purpose of this Amendment is to:

1) Advise Offerors that Executive Order 14026 raising the minimum wage for workers performing on or in connection with covered federal contracts to $15.00 per hour will apply to this contract. For more information refer to https://www.dol.gov/agencies/whd/government-contracts/eo14026.

2) Provide a summary of responses to questions/clarifications asked by potential bidders. No additional questions will be considered for this solicitation after the issuance of this amendment.

3) Reschedule RFP Proposal Package (both Technical and Price Proposals) due date to January 6, 2022 at 2:00 p.m. EST.

https://www.dol.gov/agencies/whd/government-contracts/eo14026

Questions/Clarifications

Questions/Clarifications

1. Can it be assumed that item in Schedule A (91900-0000) Dewatering Wells, is only the well excavation?

Response: No, this item includes well excavation, installation of well pumps, pumping groundwater, and/or other necessary work to achieve the required drawdown. Please refer to the SCR 919 and PRHTA Special Provision 919 Dewatering (included on Amendment # 1) for the complete scope of this item.

2. Can it be assumed that item in Schedule A (91900-1000) Ground Water Treatment System, refers to placing the pump, operating it, and treating the water? If this is correct, what treatment would be given to the water and the unit of the batch should be LS or Day?

Response: This item includes but is not limited to testing and monitoring groundwater for presence of contaminants, providing a dewatering system capable of diverting contaminated groundwater to mobile groundwater treatment system, removing contaminants as specified, and other incidental work. Please refer to the SCR 919 and PRHTA Special Provision 919 Dewatering (included on Amendment #

1) for the complete scope of Dewatering on this project.

3. The bid documents ask to build the drilled shafts embedded in the rock formation, however the bids documents do not include core logs or rock information. Does the government have, or will it provide this information?

Response: The information available has been provided in the solicitation documents. Refer to PRHTA’s Special Provision 901-3.05(a) and (b). The contractor shall consider providing methods and equipment capable of constructing shaft in the depth equal to the deepest shaft included in the plans plus 20 feet or plus 3 times the shaft’s diameter whichever is greater.

4. Request that EFL considers the postponement of the submission date for this project taking into consideration that subcontractors and suppliers for this project have yet to submit their proposals this added to the consideration that many of them are on Christmas recess.

Response: The proposal due date is being postponed to January 6 in this amendment.