Results of Bid Opening - MO ERFO NPS OZAR 2017-1(1) and MO ERFO NPS OZAR 2017-1(3) .pdf

PDF 119 KB Posted

Attached to
Ozark National Scenic Riverways
Solicitation number
693C73-21-B-000002
Issued by

About this file

This document summarizes the results of a bid opening for the Ozark National Scenic Riverways Project. The project involves replacement of two pedestrian bridges and reconstruction of various sites throughout Ozark National Scenic Riverways in Missouri. The work includes asphalt paving, drainage improvements, trail repair, parking lot reconstruction, and other miscellaneous tasks. The project will be split into multiple schedules with the total cost expected to range between $1 million to $5 million. Six contractors submitted bids by the November 17, 2020 deadline ranging from $2.8 million to $5.4 million. The engineer's estimate was $3.7 million. If awarded, the work must be completed within 425 calendar days.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration Eastern Federal Lands Highway Division

Bid Opening for

Ozark National Scenic Riverways

PROJECT: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3)

SOLICITATION NO. 693C73-21-B-000002

November 17, 2020 at 2:00 p.m.

Ashburn, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-21-B-000002 Project: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3)

November 17, 2020, 2:00 p.m. local time

BIDDERS BID TOTALS DAYS TOTAL PRICE

Central Southern Construction Corp

SCHEDULE A SCHEDULE B

$3,699,900.00 $654,675.00

SCHEDULE C SCHEDULE D

$134,950.00 $109,550.00

SCHEDULE E SCHEDULE F

$167,550.00 $192,325.00

SCHEDULE G SCHEDULE H

$187,375.00 $270,950.00

SCHEDULE A + SCHEDULE B +

SCHEDULE C + SCHEDULE D +

SCHEDULE E + SCHEDULE F +

SCHEDULE G + SCHEDULE H =

$5,417,275.00

Eclipse Co. LLC SCHEDULE A SCHEDULE B $3,321,798.51 $701,399.50

SCHEDULE C SCHEDULE D

$115,024.00 $105,174.50

SCHEDULE E SCHEDULE F

$126,564.50 $177,785.00

SCHEDULE G SCHEDULE H

$172,068.00 $232,694.00

SCHEDULE A + SCHEDULE B +

SCHEDULE C + SCHEDULE D +

SCHEDULE E + SCHEDULE F +

SCHEDULE G + SCHEDULE H =

$4,952,508.01

If the Government awards the contract as Schedules A + B + C + D + E + F + G + H, the performance period to complete all contract work will be 425 calendar days.

BID OPENING for SOLICITATION NO. 693C73-21-B-000002 Project: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3)

November 17, 2020, 2:00 p.m. local time

BIDDERS BID TOTALS DAYS TOTAL PRICE

GC Works Inc. SCHEDULE A SCHEDULE B $1,307,802.50 $386,128.00

SCHEDULE C SCHEDULE D

$162,187.00 $126,329.00

SCHEDULE E SCHEDULE F

$181,110.00 $216,702.50

SCHEDULE G SCHEDULE H

$206,415.00 $284,880.00

SCHEDULE A + SCHEDULE B +

SCHEDULE C + SCHEDULE D +

SCHEDULE E + SCHEDULE F +

SCHEDULE G + SCHEDULE H =

$2,871,554.00

Kozeny – Wagner, Inc. SCHEDULE A SCHEDULE B $2,553,178.00 $330,569.50

SCHEDULE C SCHEDULE D

$78,361.00 $52,857.00

SCHEDULE E SCHEDULE F

$119,830.00 $192,793.00

SCHEDULE G SCHEDULE H

$160,862,00 $161,465.00

SCHEDULE A + SCHEDULE B +

SCHEDULE C + SCHEDULE D +

SCHEDULE E + SCHEDULE F +

SCHEDULE G + SCHEDULE H =

$3,649,915.50

If the Government awards the contract as Schedules A + B + C + D + E + F + G + H, the performance period to complete all contract work will

BID OPENING for SOLICITATION NO. 693C73-21-B-000002 Project: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3)

November 17, 2020, 2:00 p.m. local time

BIDDERS BID TOTALS DAYS TOTAL PRICE

Lehman Construction LLC SCHEDULE A SCHEDULE B $2,238,495.00 $554,437.00

SCHEDULE C SCHEDULE D

$55,640.00 $45,425.00

SCHEDULE E SCHEDULE F

$122,815.00 $204,550.00

SCHEDULE G SCHEDULE H

$259,280.00 $184,550.00

SCHEDULE A + SCHEDULE B +

SCHEDULE C + SCHEDULE D +

SCHEDULE E + SCHEDULE F +

SCHEDULE G + SCHEDULE H =

$3,665,192.00

Pavkov Contracting Co. Inc. SCHEDULE A SCHEDULE B $2,401,040.00 $473,107.00

SCHEDULE C SCHEDULE D

$30,450.00 $66,540.00

SCHEDULE E SCHEDULE F

$113,590.00 $156,300.00

SCHEDULE G SCHEDULE H

$171,790.00 $260,475.00

SCHEDULE A + SCHEDULE B +

SCHEDULE C + SCHEDULE D +

SCHEDULE E + SCHEDULE F +

SCHEDULE G + SCHEDULE H =

$3,673,292.00

If the Government awards the contract as Schedules A + B + C + D + E + F + G + H, the performance period to complete all contract work will

BID OPENING for SOLICITATION NO. 693C73-21-B-000002 Project: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3)

November 17, 2020, 2:00 p.m. local time

BIDDERS BID TOTALS DAYS TOTAL PRICE

Robertson Contractors, Inc. SCHEDULE A SCHEDULE B $3,157,975.000 $462,270.00

SCHEDULE C SCHEDULE D

$103,250.00 $107,310.00

SCHEDULE E SCHEDULE F

$131,500.00 $238,575.00

SCHEDULE G SCHEDULE H

$210,950.00 $312,425.00

SCHEDULE A + SCHEDULE B +

SCHEDULE C + SCHEDULE D +

SCHEDULE E + SCHEDULE F +

SCHEDULE G + SCHEDULE H =

$4,724,255.00

Engineers Estimate SCHEDULE A SCHEDULE B $2,510,000.00 $390,000.00

SCHEDULE C SCHEDULE D

$34,000,00 $46,000.00

SCHEDULE E SCHEDULE F

$108,000.00 $108,000.00

SCHEDULE G SCHEDULE H

$128,000.00 $347,000.00

SCHEDULE A + SCHEDULE B +

SCHEDULE C + SCHEDULE D +

SCHEDULE E + SCHEDULE F +

SCHEDULE G + SCHEDULE H =

$3,671,000.00

If the Government awards the contract as Schedules A + B + C + D + E + F + G + H, the performance period to complete all contract work will

Slide Number 1
�FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-21-B-000002� Project: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3) �November 17, 2020, 2:00 p.m. local time �
�FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-21-B-000002� Project: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3) �November 17, 2020, 2:00 p.m. local time �
�FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-21-B-000002� Project: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3) �November 17, 2020, 2:00 p.m. local time �
�FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-21-B-000002� Project: MO ERFO NPS OZAR 2017-1(1) & MO ERFO NPS OZAR 2017-1(3) �November 17, 2020, 2:00 p.m. local time �

File details come from the government source that posted it. Updated .