Attachment A_PWS_REV2.pdf
PDF 199 KB Posted
- Attached to
- Eisenhower and Snell Lock Pressure Grout Repairs
- Solicitation number
- 6923G525Q0660
About this file
This Performance Work Statement (PWS) details a contract for pressure grout repairs at Eisenhower and Snell Locks in Massena, New York, operated by the Great Lakes St. Lawrence Seaway Development Corporation (GLS). The project involves sealing approximately 1,817 linear feet of cracks in concrete structures across various cable galleries, risers, and cross-under areas to prevent water infiltration and potential equipment damage. The contractor will use SPETEC PUR F400 Hydrophobic Closed Cell Polyurethane Foam Injection Resin to seal active water leaks, with specific requirements for surface preparation, injection procedures, and quality control.
The contract includes multiple Contract Line Item Numbers (CLINs) for different repair areas, with a total performance period of 90 calendar days from the notice to proceed. The contractor must begin work within 10 calendar days of award and complete all repairs, including potential additional leak repairs up to 250 linear feet. Pricing will be submitted as a lump sum, with the government providing site access and existing system documentation. Safety protocols mandate compliance with OSHA regulations, GLS safety policies, and federal/state environmental regulations. Additional technical details and lock facility drawings are available for inspection upon request.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Spetec-F400-TDS.pdf | ||
| 6923G525Q0660 QA.pdf | ||
| Attachment B_Pricing Sheet_REV1.xlsx | XLSX spreadsheet | |
| 6923G525Q0660A00002.pdf | ||
| 6923G525Q0660A00001.pdf | ||
| Attachment A_PWS_REV1.pdf | ||
| Attachment B_Pricing Sheet.xlsx | XLSX spreadsheet | |
| Attachment A_PWS.pdf | ||
| Attachment C_Service Contract Act WD 2015-4169.pdf | ||
| RFQ 6923G525Q0660.pdf | ||
| Attachment D_Reference Drawings.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS) Eisenhower and Snell Lock Pressure Grout Repairs
1. Background InformaƟon:
The Great Lakes St. Lawrence Seaway Development CorporaƟon (GLS or CorporaƟon) is a wholly owned U.S. Government corporaƟon within the U.S. Department of TransportaƟon, which owns and operates that porƟon of the Saint Lawrence Seaway in U.S. territorial waters between Lake Ontario and Montreal, Canada. The CorporaƟon’s funcƟon is to facilitate the safe and efficient passage of commercial vessels through the Seaway. A major part of this funcƟon is the operaƟon and maintenance of Eisenhower and Snell Locks located in Massena, New York. These locks were constructed in the late 1950’s and opened to commercial navigaƟon in 1959. The lock walls are composed of a series of mass concrete monoliths, with internal galleries and recesses that contain lock machinery and uƟliƟes.
There are numerous cracks, seams, and construcƟon joints (all referred to as “cracks” in this document) in the walls and/or ceilings (surfaces) of these galleries and recesses that either currently leak water into the space or could leak in the near future. The cracks are of varying widths, but most are fine (approximately 3 mm. in width).
Although the cracked concrete is structurally stable, it is necessary to seal the cracks to prevent water infiltraƟon and resultant corrosion and damage to equipment and faciliƟes.
2. Mission/Purpose:
GLS is seeking a qualified third-party Contractor to seal designated cracks in the selected recesses to stop current water infiltration and any infiltration in adjacent areas as a result of the work.
3. Scope:
An esƟmated total of 1817 linear feet of crack is to be sealed as summarized by locaƟon below. Note that the esƟmated quanƟƟes by area are not consecuƟve linear feet and will entail mulƟple locaƟons within each area.
Eisenhower Lock
Recess Linear Footage (LF) of crack
Upstream South Cable Gallery 10
Upstream South Cable Riser 20
Downstream South Cable Gallery 5
Downstream South Cable Riser 20
North Cable Gallery 252
Upstream North Cable Riser 40
Downstream North Cable Riser 20
Upstream Crossunder Gallery 80
Downstream Crossunder Gallery 80
Eisenhower Total 527
Snell Lock
Recess Linear Footage (LF) of crack
Upstream South Cable Gallery 300
Upstream South Cable Riser 20
Downstream South Cable Gallery 60
Downstream South Cable Riser 80
North Cable Gallery 700
Upstream North Cable Riser 20
Downstream North Cable Riser 20
Upstream Crossunder Gallery 30
Downstream Crossunder Gallery 80
Snell Total 1290
The specific cracks to be repaired will be indicated to the Contractor by the ContracƟng
Officer’s RepresentaƟve (COR) in a walk-through inspecƟon at the beginning of the project. EsƟmated Linear Feet is given as a reference. Pricing should be submiƩed as a lump sum to seal all water infiltraƟon in the areas as listed in CLINs. CLIN 0009 has been added to the pricing sheet for a per linear foot unit price of crack repairs beyond the idenƟfied work areas at the beginning of the project. Any work performed under this CLIN will be under direcƟon of the COR and will not exceed 250 linear feet. Only verified work completed on a per unit basis against CLIN 0009 will be paid for. The
Contractor should be aware that there is high voltage and other uƟliƟes in these areas, and thus shall take appropriate safety precauƟons when working in the vicinity of them.
4. Requirements:
4.1 General
The Contractor shall furnish all labor, materials, equipment, and supervision necessary to seal acƟve water infiltraƟon through cracks, joints, or voids in concrete structures using a hydrophobic polyurethane injecƟon resin.
All work shall be performed in accordance with manufacturer’s installaƟon guidelines, industry best pracƟces, and applicable safety regulaƟons.
4.2 Materials
Approved Product: SPETEC PUR F400 Hydrophobic Closed Cell Polyurethane Foam InjecƟon Resin, or approved equal.
Performance Criteria requirements for an approved equal:
- Hydrophobic: Designed to react with water to form a closed-cell, flexible foam.
- Expansion: Minimum free-foam expansion of 20 Ɵmes original liquid volume.
- Water Cut-off Capability: Stops acƟve water leaks under hydrostaƟc pressure.
- Durability: Resistant to shrinkage, chemical degradaƟon, and long-term water exposure.
- Curing: Achieves full cure in accordance with manufacturer specificaƟons
(typically within minutes).
4.3 Surface and Crack PreparaƟon
Inspect and idenƟfy all cracks, joints, or voids with visible water infiltraƟon.
Clean crack surfaces to remove dirt, laitance, grease, loose parƟcles, or other contaminants that may impede bond or resin penetraƟon.
Drill injecƟon ports at proper spacing and angle to ensure complete crack penetraƟon.
Flush cracks with clean water as required to facilitate resin expansion and penetraƟon.
4.4 InjecƟon Procedure
Install injecƟon packers or ports at all designated locaƟons.
Mix and prepare SPETEC PUR F400 (or approved equal) per manufacturer’s instrucƟons.
Inject resin under controlled pressure unƟl resin flow is observed at adjacent ports or unƟl refusal.
Monitor pressure to prevent damage to surrounding concrete.
Remove packers aŌer injecƟon and patch holes with compaƟble non-shrink grout.
4.5 Quality Control
All materials shall be handled and installed by personnel experienced in polyurethane injecƟon systems.
Contractor shall verify complete crack fill and leak cessaƟon.
All repaired areas shall be inspected at least 24 hours aŌer injecƟon to confirm water infiltraƟon has been eliminated.
Any areas sƟll exhibiƟng leakage shall be re-injected at no addiƟonal cost to the Government unƟl fully sealed.
5. Deliverables
Tasks Deliverables Due
AƩend Pre-ConstrucƟon MeeƟng with GLS representaƟves.
Within 15 days of award
CLIN 0001 MobilizaƟon
CLIN 0002
Crack Repairs - Eisenhower Cable
Galleries
CLIN 0003
Crack Repairs - Eisenhower Cable
Risers
CLIN 0004
Crack Repairs - Eisenhower Cross
Unders
CLIN 0005 Crack Repairs - Snell Cable Galleries
CLIN 0006 Crack Repairs - Snell Cable Risers
CLIN 0007 Crack Repairs - Snell Cross Unders
CLIN 0008 DemobilizaƟon
CLIN 0009
Leaks Beyond Estimated Quantities
(as approved by the COR)
6. Period of Performance
The Contractor shall begin performance within 10 calendar days and complete within ninety (90) calendar days aŌer receiving the noƟce to proceed.
7. Government-Furnished Equipment, Property, and Services GLS will provide the following resources and services:
Access to the job site and secure work areas
ExisƟng system drawings and documentaƟon
8. Safety and Environmental Requirements
All work shall be conducted in accordance with applicable OSHA regulaƟons, GLS safety policies, and federal/state environmental regulaƟons.
9. AƩachments
326-C-20/26 Robinson Bay Lock Cable Galleries Details
326-C-20/27 Robinson Bay Lock Miscellaneous Galleries Details
326-C-20/28 Robinson Bay Lock Cable Risers Details
326-C-20/29 Robinson Bay Lock Misc. Rooms and Access Bldg. Details
327-C-20/24 Upper Sill and Crossover Galleries Details
327-C-20/30 Robinson Bay Lock Cable Galleries Details
327-C-20/31 Robinson Bay Lock Cable Risers Details
327-C-20/32 Robinson Bay Lock Misc. Rooms and Access Bldg. Details
*It should be noted that cable trays, uƟliƟes and some other features are not shown on these drawings. Other drawings can be made available for inspecƟon, upon request.*