Attachment A_PWS_REV1.pdf
PDF 163 KB Posted
- Attached to
- Eisenhower and Snell Lock Pressure Grout Repairs
- Solicitation number
- 6923G525Q0660
About this file
This Performance Work Statement (PWS) details a federal contract for pressure grout repairs at the Eisenhower and Snell Locks in Massena, New York, operated by the Great Lakes St. Lawrence Seaway Development Corporation. The project involves sealing approximately 1,817 linear feet of cracks in various cable galleries, risers, and crossunder galleries to prevent water infiltration and potential equipment damage. The contractor will use SPETEC PUR F400 Hydrophobic Closed Cell Polyurethane Foam Injection Resin to seal the cracks, with specific requirements including hydrophobic properties, minimum 20-times expansion, water cut-off capabilities, and durability.
The contract includes multiple Contract Line Item Numbers (CLINs) for different repair areas, with a total performance period of 90 calendar days from the notice to proceed. The contractor must begin work within 10 calendar days, attend a kickoff meeting within 15 days of award, and complete all repairs according to detailed specifications. Key requirements include using experienced personnel, following manufacturer guidelines, conducting quality control inspections, and ensuring complete crack filling and leak cessation. The government will provide job site access, secure work areas, and existing system documentation. Safety protocols must adhere to OSHA regulations and federal/state environmental standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Spetec-F400-TDS.pdf | ||
| Attachment A_PWS_REV2.pdf | ||
| 6923G525Q0660 QA.pdf | ||
| Attachment B_Pricing Sheet_REV1.xlsx | XLSX spreadsheet | |
| 6923G525Q0660A00002.pdf | ||
| 6923G525Q0660A00001.pdf | ||
| Attachment B_Pricing Sheet.xlsx | XLSX spreadsheet | |
| Attachment A_PWS.pdf | ||
| Attachment C_Service Contract Act WD 2015-4169.pdf | ||
| RFQ 6923G525Q0660.pdf | ||
| Attachment D_Reference Drawings.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS) Eisenhower and Snell Lock Pressure Grout Repairs
1. Background Information:
The Great Lakes St. Lawrence Seaway Development Corporation (GLS or Corporation) is a wholly owned U.S. Government corporation within the U.S. Department of Transportation, which owns and operates that portion of the Saint Lawrence Seaway in U.S. territorial waters between Lake Ontario and Montreal, Canada. The Corporation’s function is to facilitate the safe and efficient passage of commercial vessels through the Seaway. A major part of this function is the operation and maintenance of Eisenhower and Snell Locks located in Massena, New York. These locks were constructed in the late 1950’s and opened to commercial navigation in 1959. The lock walls are composed of a series of mass concrete monoliths, with internal galleries and recesses that contain lock machinery and utilities.
There are numerous cracks, seams, and construction joints (all referred to as “cracks” in this document) in the walls and/or ceilings (surfaces) of these galleries and recesses that either currently leak water into the space or could leak in the near future. The cracks are of varying widths, but most are fine (approximately 3 mm. in width).
Although the cracked concrete is structurally stable, it is necessary to seal the cracks to prevent water infiltration and resultant corrosion and damage to equipment and facilities.
2. Mission/Purpose:
GLS has a requirement for a qualified Contractor to seal designated cracks in the selected recesses to stop current water infiltration and any infiltration in adjacent areas as a result of the work.
3. Scope:
An estimated total of 1817 linear feet of crack is to be sealed as summarized by location below. Note that the estimated quantities by area are not consecutive linear feet and will entail multiple locations within each area.
Eisenhower Lock
Recess Linear Footage (LF) of crack
Upstream South Cable Gallery 10
Upstream South Cable Riser 20
Downstream South Cable Gallery 5
Downstream South Cable Riser 20
North Cable Gallery 252
Upstream North Cable Riser 40
Downstream North Cable Riser 20
Upstream Crossunder Gallery 80
Downstream Crossunder Gallery 80
Eisenhower Total 527
Snell Lock Recess Linear Footage (LF) of crack
Upstream South Cable Gallery 300
Upstream South Cable Riser 20
Downstream South Cable Gallery 60
Downstream South Cable Riser 80
North Cable Gallery 700
Upstream North Cable Riser 20
Downstream North Cable Riser 20
Upstream Crossunder Gallery 30
Downstream Crossunder Gallery 80
Snell Total 1290
The specific cracks to be repaired will be indicated to the Contractor by the Contracting
Officer’s Representative (COR) in a walk-through inspection at the beginning of the project. Estimated Linear Feet is given as a reference. Pricing should be submitted as a lump sum to seal all water infiltration in the areas as listed in CLINs. The Contractor should be aware that there is high voltage and other utilities in these areas, and thus shall take appropriate safety precautions when working in the vicinity of them.
4. Requirements:
4.1 General
The Contractor shall furnish all labor, materials, equipment, and supervision necessary to seal active water infiltration through cracks, joints, or voids in concrete structures using a hydrophobic polyurethane injection resin.
All work shall be performed in accordance with manufacturer’s installation guidelines, industry best practices, and applicable safety regulations.
4.2 Materials
Approved Product: SPETEC PUR F400 Hydrophobic Closed Cell Polyurethane
Foam Injection Resin or approved equal.
Performance Criteria requirements for an approved equal:
- Hydrophobic: Designed to react with water to form a closed-cell, flexible foam.
- Expansion: Minimum free-foam expansion of 20 times original liquid volume.
- Water Cut-off Capability: Stops active water leaks under hydrostatic pressure.
- Durability: Resistant to shrinkage, chemical degradation, and long-term water exposure.
- Curing: Achieves full cure in accordance with manufacturer specifications
(typically within minutes).
4.3 Surface and Crack Preparation
Inspect and identify all cracks, joints, or voids with visible water infiltration.
Clean crack surfaces to remove dirt, laitance, grease, loose particles, or other contaminants that may impede bond or resin penetration.
Drill injection ports at proper spacing and angle to ensure complete crack penetration.
Flush cracks with clean water as required to facilitate resin expansion and penetration.
4.4 Injection Procedure
Install injection packers or ports at all designated locations.
Mix and prepare SPETEC PUR F400 (or approved equal) per manufacturer’s instructions.
Inject resin under controlled pressure until resin flow is observed at adjacent ports or until refusal.
Monitor pressure to prevent damage to surrounding concrete.
Remove packers after injection and patch holes with compatible non-shrink grout.
4.5 Quality Control
All materials shall be handled and installed by personnel experienced in polyurethane injection systems.
Contractor shall verify complete crack fill and leak cessation.
All repaired areas shall be inspected at least 24 hours after injection to confirm water infiltration has been eliminated.
Any areas still exhibiting leakage shall be re-injected at no additional cost to the Government until fully sealed.
5. Deliverables
Tasks Deliverables Due
Attend Kickoff Meeting with GLS representatives.
Within 15 days of award
CLIN 0001 Mobilization
CLIN 0002
Crack Repairs - Eisenhower Cable
Galleries
CLIN 0003
Crack Repairs - Eisenhower Cable
Risers
CLIN 0004
Crack Repairs - Eisenhower Cross
Unders
CLIN 0005 Crack Repairs - Snell Cable Galleries
CLIN 0006 Crack Repairs - Snell Cable Risers
CLIN 0007 Crack Repairs - Snell Cross Unders
CLIN 0008 Demobilization
6. Period of Performance
The Contractor shall begin performance within 10 calendar days and complete within ninety (90) calendar days after receiving the notice to proceed.
7. Government-Furnished Equipment, Property, and Services GLS will provide the following resources and services:
Access to the job site and secure work areas
Existing system drawings and documentation
8. Safety and Environmental Requirements
All work shall be conducted in accordance with applicable OSHA regulations, GLS safety policies, and federal/state environmental regulations.
9. Attachments
326-C-20/26 Robinson Bay Lock Cable Galleries Details
326-C-20/27 Robinson Bay Lock Miscellaneous Galleries Details
326-C-20/28 Robinson Bay Lock Cable Risers Details
326-C-20/29 Robinson Bay Lock Misc. Rooms and Access Bldg. Details
327-C-20/24 Upper Sill and Crossover Galleries Details
327-C-20/30 Robinson Bay Lock Cable Galleries Details
327-C-20/31 Robinson Bay Lock Cable Risers Details
327-C-20/32 Robinson Bay Lock Misc. Rooms and Access Bldg. Details
*It should be noted that cable trays, utilities and some other features are not shown on these drawings. Additional drawings can be made available for inspection, upon request.*