This document is an Amendment (Amendment 0002) to Solicitation 6923G225B000002 for the USMMA Conference Room Renovation project. The amendment extends the solicitation due date to April 9, 2025, at 10:00 AM, with bid opening at 10:15 AM, located at Furuseth Hall, Room 212 Procurement at 300 Steamboat Road, Kings Point, NY. All bids must be submitted physically, with one hard copy delivered.

The amendment includes several questions and answers clarifying project details, such as carpet tile specifications (Navy-Blue on the raised platform), electrical work intentions (using existing wiring and circuitry), and confirming that the General Contractor (G.C.) can self-perform electrical work while adhering to current Wage Determination. Additional clarifications cover AV/Data outlet cable runs, equipment staging, and LED fixture specifications, which will be determined at the time of award via submittals. The solicitation is subject to additional oversight per recent Executive Order(s), with the government reserving the right to cancel the requirement at any time.

View the file

Other files

File Type Posted
Bid Abstract - 1409.pdf PDF
Wage Determination.pdf PDF
Amendment 0001.pdf PDF
Solicitation - RFQ.pdf PDF
SOW - USMMA OHara Conference Room.pdf PDF
Furniture Specs.pdf PDF
DOL Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

6923G225B000002 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

6923G2

KINGS POINT NY 11024-1699

300 STEAMBOAT ROAD

USMMA PROCUREMENT

MARITIME ADMINISTRATION

04/04/20250002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/12/2025

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this Amendment is to post RFI response and extend the due date according.

1. This solicitation is hereby extended to April 9, 2025, at 1000-hours, bid opening at

1015-hours. LOCATION: Furuseth Hall, Room 212 Procurement. 300 Steamboat Road, Kings Point, NY 11024.

2. All bids must be submitted physical to be accepted i.e. hand-delivered or postal services before the 10AM, one hard copy must be delivered.

3. The additional Q&A is hereby posted below:

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Maxmillian Diah

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6923G225B000002/0002

Change Item 00002 to read as follows(amount shown is the obligated amount):

00002 NOTE: This solicitation is subject to additional oversight per recent Executive Order(s). We may elect to cancel this requirement at any time due to the best interest of the government.

QUESTONS & ANSWERS

22. Can owner please clarify whether anchor design for carpeting is to be incorporated on carper at the new raised platform or the carpet area of the main conference room floor?

ANSWER. Carpet tiles (Navy-Blue) on the raised platform, no design and no preference on size.

23. (a) Please advise if contractor can tap off branch circuitry within the conference room to feed new electrical devices or if new wiring shall be run to feed new electrical devices

(b) Please advise if existing electrical wiring is to be re-used as part of Alternate Price #2 -

Light fixtures and Lighting control?

ANS. The intent was to use existing.

24. What are the specs for the LED (high hat) fixtures?

ANS. To be determined at time of award via submittals.

25. Please advise/confirm - Is the intent for the under-carpet pre-wired power raceway system to be installed on top of the concrete slab or does owner request the concrete slab be saw cut from

TV wall to new conference table and channel the new raceway within the slab?

ANS. The intent was to run it above the slab.

26. Is GC allowed to self-perform the electrical scope of work?

ANS. Yes, the G.C. may self-perform any aspect of the work and must adhere to current Wage

Determination.

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6923G225B000002/0002

27. As part of Electrical Scope 10.2 Installation of new AV/Data outlets, Is the contractor to price new data cable runs from conference room to existing data rack at basement level?

ANS. The intent is to use existing cables from the rack.

28. Can existing storage room closet within conference room be used for equipment and material staging?

ANS. To be determined with Awardee.