MT PRAIRIE 2016(3), Milwaukee Bridge Resurfacing and Rehabilitation
Solicitation number
69056726B000003
Issued by

About this file

This is a Questions and Answers (Q&A) document for Project No. MT PRAIRIE 2016(3), the Milwaukee Bridge Resurfacing and Replacement project. The document contains 25 technical questions posed by bidders regarding contract requirements, design specifications, permitting issues, and constructability concerns, along with FHWA responses dated between March 2, 2026 and July 22, 2026.

Key contract modifications announced through Q&A responses include: extension of the Fixed Completion Date from the original 04/13/27 to 09/30/27 (Amendment A001, dated 7/2/26), further extension to 11/15/2027 (Amendment A003, dated 7/21/26), correction of floor beam quantity from 124 to 268 units totaling 98,892 pounds (Amendment A002, dated 7/13/26), and correction of bridge rail quantity from 2,170 to 2,152 linear feet (Amendment A002, dated 7/16/26). The FHWA clarified that no geotechnical or foundation information is available for cofferdam design at Pier 4, though the work area must be adequately isolated and capable of being dewatered while preventing turbid water discharge. The Government is obtaining a modification to the Nationwide Permit to address temporary excavation and placement quantities related to dewatering and riprap scour mitigation work. Additional clarifications addressed temporary traffic control requirements referencing U.S. Army Corps of Engineers standards, elimination of approach guardrail requirements, confirmation that riprap scour mitigation is mandatory, and specification that the steel grid deck design and fabrication shall be assembled in the field with basic tools and skills. The Notice-to-Proceed is scheduled for 10/08/26, with anticipated contract advertisement in May/June 2026.

View the file

Other files

File Type Posted
BidTab_MT PRAIRIE 2016(3).pdf PDF
BidSum_MT PRAIRIE 2016(3).pdf PDF
QandA_08-04-2026.pdf PDF
Amendment A004.pdf PDF
QandA_07-30-2026.pdf PDF
Amendment A003.pdf PDF
QandA_07-29-2026.pdf PDF
QandA_07-28-2026_updated.pdf PDF
QandA_07-28-2026.pdf PDF
QandA_07-21-2026.pdf PDF
QandA_07-20-2026.pdf PDF
Amendment A002.pdf PDF
QandA_07-17-2026.pdf PDF
QandA_07-16-2026.pdf PDF
QandA_07-13-2026.pdf PDF
Amendment A001.pdf PDF
QandA_07-07-2026.pdf PDF
QandA_07-02-2026.pdf PDF
Physical Data_mta-prairie2016-3.zip ZIP file
mta-prairie2016-3_plans_IFB.pdf PDF
IFB_69056726B000003.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. MT PRAIRIE 2016(3)

Project: Milwaukee Bridge Resurfacing and Replacement

# General Technical Question Answer Date

1 x

Does the FHWA have an anticipated advertisement date along with an anticipated bid date for this project?

Anticipated advertisement date of

May/June 2026.

3/2/26

2 X

In regards to the above referenced project is there any Geotechnical information for this project? If so can you please publish it with the advertisement.

No geotechnical information is available for this project. A surfacing memorandum for the road approaches to the new bridge deck is included in the Physical Data.

7/1/26

3 X

In Section H of the SCR’s the letter from Army

Corps of Engineers states that the permit obtained by FHWA “ Does not authorized dewatering or temporary construction access”

This authorization can typically take up to 90 days. With the NTP shown in the contract of

10/08/26 if the authorization does take the full

90 days that would not leave us enough time to complete the project by the fixed completion date of 04/13/27. In the time of year we could expect to get this permit will be close to high water and we will likely not have time to complete the work until high water passes.

Would FHWA extend the contract to 09/30/27?

The Government has the authorization as long as the dewatering and access is completed according to the plans and impact footprint in the original permit submittal. If the dewatering or access deviates from what was in the permit, then there will need to be additional time for coordination with the USACE. The

Government will extend the Fixed

Completion Date to 9/30/2027 in

Amendment A001.

7/2/26

Check General or Technical

4 X

Is there any geotechnical data available? If so would FHWA please provide that data so we can properly plan for the temporary work access?

No geotechnical information is available for this project. A surfacing memorandum for the road approaches to the new bridge deck is included in the Physical Data.

7/2/26

5 X

On page E-10 of the SCR’s “e) Temporary works supporting public traffic.” Replaces

“(d)Temporary bridge structures for public use” from FP-14. On page E-46 of the SCR’s it states

“close road for the length of project during construction. What is meant by temporary works supporting public traffic?

Public traffic is not anticipated on any temporary work, see Section 156 for traffic restrictions. The Section 104 SCR is a standard edit/change included on all bridge projects.

7/2/26

6 X

On page E-46 of the SCR’s it states “Procedures for facilitating passage of emergency vehicles through the project limits.” If we are allowed to close the road for the during of the project does this mean we are required to provide a proper detour around the project for emergency vehicles?

An improved detour around the project is not required.

7/2/26

7 X

I think the language from page H-3 of solicitation contradicts the answer to question

#3. Are temporary works/access currently permitted?

The Government is calculating quantities to capture the impacts of the temporary access road, work platform and cofferdam.

We anticipate receiving the amended permit prior to issuing the Notice-to-

Proceed (NTP).

If the contractor develops a plan in which the permitted quantities will be exceeded, contractor is responsible for submitting a revised permit application.

7/7/26

8 X Is there any data available on typical water depth at Pier 4?

The Government does not have data regarding the typical water depth at Pier 4.

7/13/26

9 X

Plan sheet S.7 – Deck Framing Layout references a total of 124 floorbeams. If you apply the spacings noted across all 4 truss spans, I am coming up with a total of 268 ea. The only way you would get to 124 is if you are only installing floorbeams across the two end chords in each span (L0-L1, L1-L2, L7-L8, L8-L9). Plans indicate floorbeams across all chords, which is necessary for the designed grid deck plan. Please review and clarify.

This will be addressed in Amendment A002.

The corrected quantity is 268 floor beams, totaling 98,892 pounds.

7/13/26

10 X

Ref. Sheet 7 0f 13 Deck Framing Layout; The

Floor Beam Estimated Weights table states there are 124 floor beams. We find there to be

268 floor beams calculated as follows:

See the answer for question 9. 7/13/26

11 X

Plan sheet S.12 shows details for bridge rail.

Inside Elevation of Rail view shows tube rail ending 4” past the last post at the bridge end with rail extending beyond that to some un-detailed post off the end of the bridge. Appears to show like we are tying into bridge approach guardrail, but there is none. If rail ends at end of tube rail, I only come up with 2,152’ of rail

(plan qty is 2,170). Please provide additional details for rail at bridge ends, including any post details off the bridge end and required terminal or end shoe as there is no bridge approach guardrail or bid item shown in the plans or bid schedule to tie into.

This will be addressed in Amendment A002.

The corrected quantity is 2,152 lineal feet.

There is no approach rail; the rail will end at the delineators.

7/16/26

12 X

Is dewatering of the cofferdam anticipated and/or required for the Pier 4 bent scour countermeasure work?

Yes, dewatering will be required. 7/17/26

13 X

If inadequate sheet pile penetration or seepage requires additional excavation and placement of a concrete seal, is that work considered incidental to the Cofferdam pay item, or will additional compensation be provided?

Work is considered incidental to the

Cofferdam pay item 7/17/26

14 X

Would FHWA consider replacing the riprap section with concrete to eliminate the need for increasing the depth of the excavation to include a concrete seal in addition to the riprap section?

No, riprap scour mitigation is required. 7/17/26

15 X

If available, please provide any geotechnical or foundation information used to establish the cofferdam requirements and anticipated sheet pile embedment depth at Pier 4.

No geotechnical or foundation information is available.

7/17/26

16 X

As a follow up to question #12 and 13: If dewatering of the cofferdam is required for riprap placement, a concrete seal will be required in order to control seepage up from underneath the cofferdam. Reference is made to the USACE Nationwide Permit Verification on sheet H-3. This project is only permitted for

1,900 CY of material to be excavated/placed within the stream bed. With an estimated

1,600 CY of excavation and riprap placement for the permanent work, the additional excavation and placement of a concrete seal to control the water in this location would push the quantity well over the 1,900 CY permitted for this project. Will WFL be obtaining a modification to the Nationwide Permit for this work?

Yes, WFL is obtaining a modification to the

Nationwide Permit for this work, which will be based on revised temporary impact quantities. If the successful contractor proposes something different or proposes additional temporary impacts over what is in WFLs amended permit, Contractor will be responsible for submitting a revised amended permit application.

7/20/26

17 X

As a follow up to question #12 and 13:

Dewatering is a subjective requirement. Is the contractor required to perform the excavation and riprap work at Pier 4 in the dry?

WFL's assumption for the permitting of this work has been that the area will be dewatered and excavation performed in the dry before placement of riprap. This was driven partly by SCR 107.10.(e).14 and the requirement to sweep for the endangered pallid sturgeon and relocate them outside the cofferdam if present. The successful contractor can propose alternate ideas to accomplish the same objective, however for the 404 permit the successful contractor will have to submit an amended permit application if a different means and method is proposed.

7/20/26

18 X

Special Provisions Section 555.03A includes the following Language “Design and fabricate the bridge such that the components may be assembled in the field with basic tools and skills”. What part of the bridge design is the

General Contractor or Fabricator responsible for

Designing? Does the use of cranes to lift and place the floor beam system constitute basic tools and skills?

The intent in SCR 555.03A is for the steel bridge deck to be assembled in the field with basic tools and skills. The wording in this SCR section should read "Design and fabricate the bridge steel grid deck...." This will be corrected in a future amendment.

7/21/26

19 X

The plans call for structural design of the steel grid deck with a Licensed Professional Engineer.

Are there any acceptable standard steel deck alternatives that can be used to save on the design and fabrication costs of implementing a custom designed steel grid deck?

No. Please bid per the solicitation documents.

7/21/26

20 X

Plan sheet S.10 indicates minor concrete fill at the floorbeams to pour in the new steel grid deck panels. There is no bid item for this work.

Where does this measure and pay? What are the structural requirements of the concrete mix? Can a pea gravel type mix be used to aid in placement in these small/congested locations? Please clarify.

Bid per solicitation documents. See SCR

Section 601 for Minor Concrete specifications.

21 X

Section 107.10(e) of the general requirements

(page E-17) states no in water work will be performed between May 15 and July 15. Based on the work access plan shown on sheet G.3 and spring flows in the Yellowstone River, it is reasonable to anticipate that work access to

Pier 4 would commence, at earliest, on July 15

(perhaps later depending on river flows).

Considering the amount of worktrestle to be installed, along with cofferdam construction, dewatering, excavation and riprap placement, then removal of both cofferdam and worktrestle; we do not believe a contract completion date of September 30, 2027 is reasonable for the amount of in water work involved. We respectfully request that the owner consider extending the contract completion date to at least November 15, 2027 to allow all this work to be completed.

The Government will extend the Fixed

Completion Date (FCD) to 11/15/2027. This will be addressed in Amendment A003.

22 X

With the lack of geotechnical information the design for the cofferdam located at bent 4 can range from a simple sheet pile cofferdam to a highly complex sheet pile cofferdam that would include a robust multi-leveled interior wale frame and strut design that would have to be installed systematically while the cofferdam is being dewatered. This puts the contractor at a high level of risk as the cost of construction of these designs would be orders of magnitude different and that is not taking into account the potential for needing a sealing slab to shut the water off in the cofferdam. Can the FHWA give the contractors an expected bedrock elevation to utilize for bidding purposes? This does not seem unreasonable as geotechnical reports giving this data are standard practice for construction projects of this scope and size, allowing the contractor to make these risk assessments to the best of their ability. As it stands right now there is insufficient geotechnical information for even the most competent of contractors to bid this work at anything less than the worst case scenario.

Bid per the solicitation documents. FHWA does not have an expected bedrock elevation available. The work area does not necessarily need to be completely dry.

However, the work area must be adequately isolated, capable of being dewatered and drained, while preventing the discharge of turbid water into the surrounding waterway.

7/22/26

23 X

Bid schedule and traffic control quantity table in plans reference Temporary Traffic Control (River

Traffic) LS. Section 635.04 (page F-23) makes general reference to Furnish, install, and maintain aids to navigation and other traffic control devices used for river traffic. However, it provides no specific details on what is to be provided. Please clarify required work under

Temporary Traffic Control (River Traffic) bid item. Number of signs, details, locations, any required buoys on site, etc.

Bid per the solicitation documents. SCR

635.04 references - "Use river traffic control devices identified in the U.S. Army Corps of

Engineers Sign Standards Manual (EP 310-1-

6a) current edition, or by the U.S. Bureau of

Reclamation Sign Guidelines for Planning, Design, Fabrication, Procurement, and

Maintenance of Signs for Outdoor Public

Use (current edition)."

24 X

I reviewed the sign standards manual prior to writing the RFI. It provides no clarification or details for temporary river navigation signs that would be relevant to this project.

U.S. Army Corps of Engineers Sign

Standards Manual (EP 310-1-6a) specifies the placement of navigational signs under the section titled "Water View Safety

Signs". U.S. Bureau of Reclamation Sign

Guidelines for Planning, Design, Fabrication, Procurement, and Maintenance of Signs for

Outdoor Public Use has general guidelines for navigation sign colors and sizes.

The resource agencies - specifically

Montana Fish, Wildlife and Parks - wants the river channel between Pier 4 and the abutment to be open to river traffic. The

Contractor is responsible for designing, fabricating and installing the notification signs. FHWA envisions directional signs hung from the bridge (on both sides - ie upstream and downstream face) with directional arrows pointing to the channel between Pier 4 and the abutment, plus an advanced sign both upstream and downstream of the bridge face at the locations identified in EP 310-1-6a.

7/22/26

25 X

We are hearing from qualified suppliers that the lead times for the W-beams could be extensive and is unknown. Would FHWA consider accepting C-channel bolted back to back as an acceptable alternative to W-beams?

No. Please bid per the solicitation documents.