QandA_07-21-2026.pdf
PDF 288 KB Posted
- Solicitation number
- 69056726B000003
About this file
This document is a Questions and Answers (Q&A) log for a federal bridge construction project.
Project MT PRAIRIE 2016(3) is the Milwaukee Bridge Resurfacing and Replacement project administered by FHWA. The anticipated advertisement date is May/June 2026, with a Notice-to-Proceed (NTP) of October 8, 2026. The original Fixed Completion Date of April 13, 2027 has been extended to November 15, 2027 to accommodate permit processing timelines and in-water construction restrictions. No geotechnical information is available for the project; however, a surfacing memorandum for road approaches is included in the Physical Data. The project involves significant in-water work at Pier 4, including worktrestle installation, cofferdam construction, dewatering, excavation, and riprap scour mitigation placement. Construction activities are restricted between May 15 and July 15 annually due to environmental protections for the endangered pallid sturgeon, limiting work access to Pier 4 to commence no earlier than July 15. The Government has obtained USACE authorization for dewatering and temporary construction access within the original permit footprint; however, any deviations require amended permit applications at the contractor's expense. WFL is obtaining modifications to the Nationwide Permit to account for revised temporary impact quantities related to cofferdam concrete seal work.
Technical clarifications address structural design requirements for a custom steel grid deck with Licensed Professional Engineer certification, with 268 floor beams (corrected from initial quantity of 124) totaling 98,892 pounds, and 2,152 lineal feet of bridge rail (corrected from 2,170). All work must be performed according to solicitation documents and special contract requirements (SCR), including provisions in Section 107.10(e) regarding environmental protections and Section 555.03A regarding field assembly of bridge components. Minor concrete fill at floorbeams measures and pays under SCR Section 601. Dewatering of the cofferdam is required, and any additional excavation and concrete seal work is considered incidental to the Cofferdam pay item with no separate compensation provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidTab_MT PRAIRIE 2016(3).pdf | ||
| BidSum_MT PRAIRIE 2016(3).pdf | ||
| QandA_08-04-2026.pdf | ||
| Amendment A004.pdf | ||
| QandA_07-30-2026.pdf | ||
| Amendment A003.pdf | ||
| QandA_07-29-2026.pdf | ||
| QandA_07-28-2026_updated.pdf | ||
| QandA_07-28-2026.pdf | ||
| QandA_07-22-2026.pdf | ||
| QandA_07-20-2026.pdf | ||
| Amendment A002.pdf | ||
| QandA_07-17-2026.pdf | ||
| QandA_07-16-2026.pdf | ||
| QandA_07-13-2026.pdf | ||
| Amendment A001.pdf | ||
| QandA_07-07-2026.pdf | ||
| QandA_07-02-2026.pdf | ||
| Physical Data_mta-prairie2016-3.zip | ZIP file | |
| mta-prairie2016-3_plans_IFB.pdf | ||
| IFB_69056726B000003.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. MT PRAIRIE 2016(3)
Project: Milwaukee Bridge Resurfacing and Replacement
# General Technical Question Answer Date
1 x
Does the FHWA have an anticipated advertisement date along with an anticipated bid date for this project?
Anticipated advertisement date of
May/June 2026.
3/2/26
2 X
In regards to the above referenced project is there any Geotechnical information for this project? If so can you please publish it with the advertisement.
No geotechnical information is available for this project. A surfacing memorandum for the road approaches to the new bridge deck is included in the Physical Data.
7/1/26
3 X
In Section H of the SCR’s the letter from Army
Corps of Engineers states that the permit obtained by FHWA “ Does not authorized dewatering or temporary construction access”
This authorization can typically take up to 90 days. With the NTP shown in the contract of
10/08/26 if the authorization does take the full
90 days that would not leave us enough time to complete the project by the fixed completion date of 04/13/27. In the time of year we could expect to get this permit will be close to high water and we will likely not have time to complete the work until high water passes.
Would FHWA extend the contract to 09/30/27?
The Government has the authorization as long as the dewatering and access is completed according to the plans and impact footprint in the original permit submittal. If the dewatering or access deviates from what was in the permit, then there will need to be additional time for coordination with the USACE. The
Government will extend the Fixed
Completion Date to 9/30/2027 in
Amendment A001.
7/2/26
Check General or Technical
4 X
Is there any geotechnical data available? If so would FHWA please provide that data so we can properly plan for the temporary work access?
No geotechnical information is available for this project. A surfacing memorandum for the road approaches to the new bridge deck is included in the Physical Data.
7/2/26
5 X
On page E-10 of the SCR’s “e) Temporary works supporting public traffic.” Replaces
“(d)Temporary bridge structures for public use” from FP-14. On page E-46 of the SCR’s it states
“close road for the length of project during construction. What is meant by temporary works supporting public traffic?
Public traffic is not anticipated on any temporary work, see Section 156 for traffic restrictions. The Section 104 SCR is a standard edit/change included on all bridge projects.
7/2/26
6 X
On page E-46 of the SCR’s it states “Procedures for facilitating passage of emergency vehicles through the project limits.” If we are allowed to close the road for the during of the project does this mean we are required to provide a proper detour around the project for emergency vehicles?
An improved detour around the project is not required.
7/2/26
7 X
I think the language from page H-3 of solicitation contradicts the answer to question
#3. Are temporary works/access currently permitted?
The Government is calculating quantities to capture the impacts of the temporary access road, work platform and cofferdam.
We anticipate receiving the amended permit prior to issuing the Notice-to-
Proceed (NTP).
If the contractor develops a plan in which the permitted quantities will be exceeded, contractor is responsible for submitting a revised permit application.
7/7/26
8 X Is there any data available on typical water depth at Pier 4?
The Government does not have data regarding the typical water depth at Pier 4.
7/13/26
9 X
Plan sheet S.7 – Deck Framing Layout references a total of 124 floorbeams. If you apply the spacings noted across all 4 truss spans, I am coming up with a total of 268 ea. The only way you would get to 124 is if you are only installing floorbeams across the two end chords in each span (L0-L1, L1-L2, L7-L8, L8-L9). Plans indicate floorbeams across all chords, which is necessary for the designed grid deck plan. Please review and clarify.
This will be addressed in Amendment A002.
The corrected quantity is 268 floor beams, totaling 98,892 pounds.
7/13/26
10 X
Ref. Sheet 7 0f 13 Deck Framing Layout; The
Floor Beam Estimated Weights table states there are 124 floor beams. We find there to be
268 floor beams calculated as follows:
See the answer for question 9. 7/13/26
11 X
Plan sheet S.12 shows details for bridge rail.
Inside Elevation of Rail view shows tube rail ending 4” past the last post at the bridge end with rail extending beyond that to some un-detailed post off the end of the bridge. Appears to show like we are tying into bridge approach guardrail, but there is none. If rail ends at end of tube rail, I only come up with 2,152’ of rail
(plan qty is 2,170). Please provide additional details for rail at bridge ends, including any post details off the bridge end and required terminal or end shoe as there is no bridge approach guardrail or bid item shown in the plans or bid schedule to tie into.
This will be addressed in Amendment A002.
The corrected quantity is 2,152 lineal feet.
There is no approach rail; the rail will end at the delineators.
7/16/26
12 X
Is dewatering of the cofferdam anticipated and/or required for the Pier 4 bent scour countermeasure work?
Yes, dewatering will be required. 7/17/26
13 X
If inadequate sheet pile penetration or seepage requires additional excavation and placement of a concrete seal, is that work considered incidental to the Cofferdam pay item, or will additional compensation be provided?
Work is considered incidental to the
Cofferdam pay item 7/17/26
14 X
Would FHWA consider replacing the riprap section with concrete to eliminate the need for increasing the depth of the excavation to include a concrete seal in addition to the riprap section?
No, riprap scour mitigation is required. 7/17/26
15 X
If available, please provide any geotechnical or foundation information used to establish the cofferdam requirements and anticipated sheet pile embedment depth at Pier 4.
No geotechnical or foundation information is available.
7/17/26
16 X
As a follow up to question #12 and 13: If dewatering of the cofferdam is required for riprap placement, a concrete seal will be required in order to control seepage up from underneath the cofferdam. Reference is made to the USACE Nationwide Permit Verification on sheet H-3. This project is only permitted for
1,900 CY of material to be excavated/placed within the stream bed. With an estimated
1,600 CY of excavation and riprap placement for the permanent work, the additional excavation and placement of a concrete seal to control the water in this location would push the quantity well over the 1,900 CY permitted for this project. Will WFL be obtaining a modification to the Nationwide Permit for this work?
Yes, WFL is obtaining a modification to the
Nationwide Permit for this work, which will be based on revised temporary impact quantities. If the successful contractor proposes something different or proposes additional temporary impacts over what is in WFLs amended permit, Contractor will be responsible for submitting a revised amended permit application.
7/20/26
17 X
As a follow up to question #12 and 13:
Dewatering is a subjective requirement. Is the contractor required to perform the excavation and riprap work at Pier 4 in the dry?
WFL's assumption for the permitting of this work has been that the area will be dewatered and excavation performed in the dry before placement of riprap. This was driven partly by SCR 107.10.(e).14 and the requirement to sweep for the endangered pallid sturgeon and relocate them outside the cofferdam if present. The successful contractor can propose alternate ideas to accomplish the same objective, however for the 404 permit the successful contractor will have to submit an amended permit application if a different means and method is proposed.
7/20/26
18 X
Special Provisions Section 555.03A includes the following Language “Design and fabricate the bridge such that the components may be assembled in the field with basic tools and skills”. What part of the bridge design is the
General Contractor or Fabricator responsible for
Designing? Does the use of cranes to lift and place the floor beam system constitute basic tools and skills?
The intent in SCR 555.03A is for the steel bridge deck to be assembled in the field with basic tools and skills. The wording in this SCR section should read "Design and fabricate the bridge steel grid deck...." This will be corrected in a future amendment.
7/21/26
19 X
The plans call for structural design of the steel grid deck with a Licensed Professional Engineer.
Are there any acceptable standard steel deck alternatives that can be used to save on the design and fabrication costs of implementing a custom designed steel grid deck?
No. Please bid per the solicitation documents.
7/21/26
20 X
Plan sheet S.10 indicates minor concrete fill at the floorbeams to pour in the new steel grid deck panels. There is no bid item for this work.
Where does this measure and pay? What are the structural requirements of the concrete mix? Can a pea gravel type mix be used to aid in placement in these small/congested locations? Please clarify.
Bid per solicitation documents. See SCR
Section 601 for Minor Concrete specifications.
21 X
Section 107.10(e) of the general requirements
(page E-17) states no in water work will be performed between May 15 and July 15. Based on the work access plan shown on sheet G.3 and spring flows in the Yellowstone River, it is reasonable to anticipate that work access to
Pier 4 would commence, at earliest, on July 15
(perhaps later depending on river flows).
Considering the amount of worktrestle to be installed, along with cofferdam construction, dewatering, excavation and riprap placement, then removal of both cofferdam and worktrestle; we do not believe a contract completion date of September 30, 2027 is reasonable for the amount of in water work involved. We respectfully request that the owner consider extending the contract completion date to at least November 15, 2027 to allow all this work to be completed.
The Government will extend the Fixed
Completion Date (FCD) to 11/15/2027. This will be addressed in Amendment A003.