This is a Questions and Answers (Q&A) document for Project No. WA NP MORA 11(1), Fryingpan Creek Bridge, a federal construction project.
The Fryingpan Creek Bridge project is scheduled to be advertised for bid in Spring 2026 (April/May), with an original target of December 2025. The project involves constructing a new bridge over Fryingpan Creek, with work governed by permit requirements from USACE, EPA, USFS, USFWS, NMFS, and NPS. Key technical specifications include: Stevens Canyon Road will be cleared for contractor access one to two weeks before public opening (typically around May 22), with raw rock harvesting from avalanche chutes required before Memorial Day weekend; the 100-year water surface elevation and scour data are available on Sheet G.2 and in the Hydraulics Report; temporary bridge foundation piles are limited to 16 piles between OHWM limits designed for 100-year water surface plus 5 feet freeboard; full road closures are limited to 8 closures of 6 hours each for blasting and girder setting, with no night work or back-to-back closures permitted. The contractor must utilize stones conserved from existing bridge structures first, with additional stones sourced from avalanche chutes as needed. Construction sequencing must comply with permitted allowances under SCR 107.10. Timber mats for temporary crane operations (up to 2,000 SF) are authorized under the NWP 14 half-acre allowance, provided they minimize compaction and do not require ground disturbance. Amendment A002 will address turn-in date extensions and provide additional details on anchor rod shear plate welds for elastomeric bearing assemblies. All Q&As were issued between February 20, 2026 and May 29, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidTab_WA NP MORA 11(1) Fryingpan Creek Bridge_Update.pdf | ||
| BidTab_WA NP MORA 11(1) Fryingpan Creek Bridge.pdf | ||
| BidSum_WA NP MORA 11.pdf | ||
| Amendment A005.pdf | ||
| QA_06-25-2026.pdf | ||
| QA_06-24-2026.pdf | ||
| QA_06-22-2026.pdf | ||
| Amendment A004.pdf | ||
| QA_06-18-2026.pdf | ||
| QA_06-16-2026.pdf | ||
| QA_06-12-2026.pdf | ||
| QA2_06-11-2026.pdf | ||
| QA_06-11-2026.pdf | ||
| Amendment A003.pdf | ||
| Physical Data WA NP MORA 11(1) A003.zip | ZIP file | |
| QA_06-08-2026.pdf | ||
| QA_06-03-2026.pdf | ||
| Amendment A002.pdf | ||
| Amendment A001.pdf | ||
| QA_05-26-2026.pdf | ||
| mora11-1_plans.pdf | ||
| IFB 69056726B000001.pdf | ||
| Physical Data WA NP MORA 11(1).zip | ZIP file |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. WA NP MORA 11(1), Project Fryingpan Creek Bridge
# General Technical Question Answer Date
1 X
Could you tell me when the Frying Pan Bridge
Project is scheduled to be advertised for bid?
The original plan was December 2025.
We are now anticipating a Spring 2026
(April/May) advertisement.
2/20/26
2 X
SCR 105.02(a) requires harvesting raw rock from the Stevens Canyon Road avalanche chutes
"before Memorial Day weekend" each year, but also states access will only be granted "once the
Park has cleared the road in May." In recent years, what has been the typical road opening date for Stevens Canyon Road, and how should bidders plan for years when the road opens close to Memorial Day weekend?
The public road opening for Stevens Canyon
Road is set for May 22 this year; typically the Park clears the road for admin traffic one to two weeks ahead of public road opening; during this time the contractor would be able to access the road for avalanche chute harvesting.
The raw rock is a supplemental resource and the existing bridge rock shall be used first. The existing bridge rock will require the contractor to cut, split, and shape the rock. We will be drafting an Amendment to clarify that the Contractor is to "utilize stones conserved from existing structures.
Source additional stones from the avalanche chutes as needed"
5/20/26
3 X
SCR 575.03 limits temporary bridge foundation piles to no more than 16 piles between OHWM limits, and requires design for 100-year water surface plus 5 feet of freeboard. Has the government performed a hydraulic analysis establishing the 100-year WSE at the bridge site, and if so, can that elevation and the associated scour data be made available to bidders to support temporary work bridge design?
OHW for 100-year WSE is shown on Sheet
G.2. Scour data is available in the Hydraulics
Report in the physical data
5/20/26
4 X
SCR 156.04 allows full road closures up to 8 times for 6 hours each for blasting and girder setting. Does the government anticipate any preferred closure windows (e.g., overnight, weekday daytime) to minimize impact, and can closures be approved consecutively (e.g., two 6-hour closures back-to-back for an overnight 12-hour window)?
No night work allowed, and no back-to-back
(e.g. no 7am to 7pm). 6 hours per calendar day during daytime is allowed for full road closures.
5/20/26
Check General or Technical
5 X
The USACE permit drawings (NWS-2025-0362 sheets H-71 through H-76) lay out a specific three-season construction sequence: Season 1 abutments and majority of riprap, Season 2 girder erection and deck, Season 3 existing bridge demolition and final riprap. How much flexibility does the contractor have to propose an alternate construction sequence, or to revise the means and methods shown in the permit drawings (for example, work bridge configuration, stream diversion footprint, or temporary girder erection foundation layout), as long as the proposed approach stays within the permitted impact footprint and timing windows? Specifically, if the contractor identifies a more efficient sequence, does the government require a permit modification through the original permitting authorities
(USACE, EPA, USFS, USFWS, NMFS, NPS), or can changes be approved at the CO level under SCR
104.03 submittal authority?
Construction sequence must fall within the permitted allowances and comply with all conditions as stated in SCR 107.10
5/20/26
6 X
Permit Drawing H-75 (NWS-2025-0362, sheet
18/19) shows a "Timber Pads Alternative" with a
Directly Affected impact of 168 SQFT during existing bridge demolition. NWP 14 explicitly authorizes "temporary mats" as part of the permitted activity, subject to the overall 1/2-acre NWP 14 cap. For the existing bridge demolition described in SCR 203.04, the contractor anticipates requiring approximately
2,000 SF of temporary timber crane mats to support a crawler crane and rigging operations inside the isolated, dewatered zone (mats placed on existing streambed, removed in their entirety at completion, with full streambed restoration). Will the government confirm that this scope of temporary timber mat use is within the existing NWP 14 authorization given the temporary nature of the mats and the cumulative project impacts remain below the
1/2-acre cap? If a permit modification is required, will the government coordinate the modification with USACE Seattle District, or is it the contractor's responsibility?
Timber mats fall may under the Corps allowance of one half acre for mats, provided that the mats minimize compaction and do not require ground disturbance when placing them. The contractor will be required to provide a detail of the timber matts and also show the footprint of these timber mats on design drawings in the Stormwater
Pollution Prevention Plan."
5/20/26
7 X
With the complexity of this project, quantity of subcontractors/suppliers involved, and two different bid schedules, would there be consideration to add a week or two to the turn-in date?
This will be addressed by Amendment
A002.
5/29/26
8 X
Please provide weld size and locations for the anchor rod shear plates (sheet S.19) on the elastomeric bearing assemblies.
This will be addressed by Amendment
A002.
5/29/26