Amendment A002.pdf
PDF 772 KB Posted
- Attached to
- TX NP MULTI PMS(1) Pavement Preservation Texas Federal contract opportunity
- Solicitation number
- 69056725R000006
About this file
This document is an Amendment (A002) to a Federal Highway Administration solicitation (No. 69056725R000006) for a Pavement Preservation project in Texas. The amendment, dated 11/07/2025, revises multiple sections of the original solicitation, specifically updating technical specifications for aggregate materials, surface treatment application procedures, and contract requirements. Key modifications include changes to chip seal, scrub seal, micro surfacing, and slurry seal aggregate specifications, with detailed revisions to gradation requirements, material testing standards, and application techniques for different aggregate types across various sieve sizes. The amendment provides updated language for Sections 108, 409, 421, and 703, incorporating both standard specifications and Texas Department of Transportation (TxDOT) material specifications for pavement preservation work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QA_11_10_2025.pdf | ||
| QA_11_07_2025.pdf | ||
| Amendment A001.pdf | ||
| QA_10_31_2025.pdf | ||
| QA_10_28_2025.pdf | ||
| txp-multi-pms1_BITH_C6_Final_Report.pdf | ||
| txp-multi-pms1_SAAN_C6_Final_Report.pdf | ||
| RFP 69056725R000006_TX NP MULTI PMS(1).pdf | ||
| txp-multi-pms1_AMIS_C6_Final_Report.pdf | ||
| txp-multi-pms1_FODA_C6_Final_Report.pdf | ||
| txp-multi-pms1_LYJO_C6_Final_Report.pdf | ||
| FLH Bridge oversized or overload vehicle permit request form August 2023.pdf | ||
| txp-multi-pms1_plans_Flattened.pdf | ||
| txp-multi-pms1_CHAM_C6_Final_Report.pdf | ||
| txp-multi-pms1_GUMO_C6_Final_Report.pdf | ||
| txp-multi-pms1_PAIS_C6_Final_Report.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 11/07/2025 N/A TX NP MULTI PMS(1),
Pavement Preservation Texas
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056725R000006
9B. DATED (SEE ITEM 11)
10/10/2025
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
TX NP MULTI PMS(1),Pavement Preservation Texas
See page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A002, dated 11-07-2025 TX NP MULTI PMS(1), Solicitation No. 69056725R000006 Pavement Preservation Texas
REVISIONS ARE AS FOLLOWS:
SOLICITATION PROVISIONS
SPECIAL CONTRACT REQUIREMENTS
Page E-25, Subsection 108.01(h)(3). Revises language.
Pages F-7 and F-7a, Subsection 409.10. Revises language and includes Table 409-2.
Page F-16, Subsection 421.09. Updates language.
Pages G-4 and G-4a, Subsection 703.09 and 703.10. Revises language and adds section with table.
ENCLOSURES
Pages:
E-25
F-7 and F-7a
F-16
G-4 and G-4a
E-25 DIVISION 100
(2) Perform all work on Visitor Center Parking Route 0900 between 5:00 p.m. to 7:00 a.m.
(3) Limit work hours to between 7:00 a.m. to 5:00 p.m. at all routes in the Ranch area of the park.
(g) PAAL. Maintain all routes and parking areas open for public use in PAAL during April 15 through May 31 (dates inclusive).
(h) PAIS
(1) Perform Section 407 and 409 work in the VIP Campground (Routes 0901BZ and 0400) Monday through Thursday, within the dates May 6 to May 16 (dates inclusive).
(2) Perform no work except to maintain traffic control devices, erosion control devices, the roadway driving surface, and to control dust during the month of March.
(3) Perform no work that generates ground vibrations above current park traffic conditions:
(a) Within a 0.5-mile radius of the Headquarters area turtle incubation facility (Routes 0902, 0903, 0906, and a portion of Route 0010);
(b) Milepost 0.35 to 0.49 (inclusive) at the last 0.15 miles of Route 0100 North
Beach Access Road; and
(c) Milepost 5.62 to 5.77 (inclusive) at the last 0.15 miles of Route 0010 Park Road (South Beach access road).
(i) SAAN. Perform Section 409 work on Route 0901 in two phases or between 5:00 p.m. to 7:00 a.m.
108.01A Labor. (Added Subsection).
Follow the requirements of FAR Clause 52.222-6 Construction Wage Rate Requirements.
Adjacent or virtually adjacent work sites, as used in FAR Clause 52.222-6, are defined to be work sites within ½ mile of the project. Application of Construction Wage Rate Requirements (Davis-
Bacon Act) for work sites beyond ½ mile of the project will be determined by the CO.
108.02 Subcontracting. Amend as follows:
Delete the text of the first paragraph and substitute the following:
Follow the requirements of FAR Clause 52.222-11 Subcontracts (Labor Standards).
Special Contract Requirements Revised by Amendment A002 Project: TX NP MULTI PMS(1), Pavement Preservation Texas
F-7 DIVISION 400
409.08 Calibration. Calibrate mixing equipment according to ISSA A143.
409.09 Production Start-Up Procedures. Conduct a pre-surfacing preparatory phase meeting according to Subsection 153.04(a).
On the first day of placement, construct one 300-foot (100-meter) long control strip, one lane wide.
Coordinate location of the control strip with the CO. Construct the control strip using material, lay-down, and rolling procedures intended for the entire project.
Cease production after construction of the control strip until the material and the control strip are evaluated and accepted by the CO. Repeat the control strip process until an acceptable control strip is produced.
Acceptable control strips may remain in place and will be accepted as a part of the completed surface treatment. Correct unacceptable control strips.
Use these start-up procedures when changing construction procedures, when resuming production after a termination of production due to unsatisfactory quality according to Subsection 106.04, or the beginning of a new construction season.
409.10 Application. Provide a micro surfacing mixture of the proper consistency at all times so as to provide the application rate required by the surface condition. Place with an application rate conforming to Table 409-1 when utilizing aggregate conforming to ISSA A143.
Table 409-1
Application Rate for Micro Surfacing
Aggregate Type(1) Application Rate (lb/yd2)
Type II 17 – 22
Type III 25 – 30
(1) See Table 703-8 for aggregate gradations.
Application rates are based upon the weight of dry aggregate in the mixture. Application rates are affected by the unit weight and gradation of the aggregate and the demand of the surface to which the micro surfacing is being applied.
Fog the surface with water in front of the spreader, when needed.
Provide the CO with a split certified shipping ticket for each separate emulsified asphalt shipment load prior to mixing and application.
Prior to starting application of micro surfacing, calibrate each mixing unit to be used on the project in accordance with ISSA A143 and in the presence of the CO or designated representative. Clean the spreader box prior to start of each work shift.
Blend the additives with the aggregate. Pre-wet the aggregate in the pugmill before mixing with the polymer-modified emulsified asphalt.
F-7a
Special Contract Requirements
Project: TX NP MULTI PMS(1), Pavement Preservation Texas
Place with an application rate conforming to Table 409-2 when conforming to current Texas
Department of Transportation (TxDOT) material specifications for Grade 2 Aggregate for micro surfacing aggregate.
Table 409-2
Application Rate for Micro Surfacing
Aggregate Type(1) Application Rate (lb/yd2)
Type II 20 - 25
Type III 25 – 30
(1) See current Texas Department of Transportation (TxDOT) material specifications for Grade 2 Aggregate for aggregate gradations.
Revised by Amendment A002
F-16 DIVISION 400
Repeat the control strip process until an acceptable control strip is produced. Cease production until the material and the control strip are evaluated and accepted. The CO will indicate which strip will serve as the approved project control strip.
Acceptable control strips may remain in place and will be accepted as a part of the completed project. Correct unacceptable control strips.
Use these start-up procedures when changing construction procedures, when resuming production after a termination of production due to unsatisfactory quality according to Subsection 106.04, or the beginning of a new construction season.
421.09 Polymer Modified Rejuvenating Asphaltic Emulsion Application. Calibrate asphalt distributors before the start of project and when directed by the CO. Calibrate the spray bar height, check nozzle angle, and verify longitudinal and transverse application rates according to ASTM
D2995.
Apply emulsion at a minimum temperature of 130 °F
Apply emulsion uniformly at the optimum application rate determined from the approved control strip. Immediately broom the emulsion to fill cracks and voids with the scrub broom. Use hand brooms in areas that cannot be adequately reached with Scrub Boom attached to and pulled by distributor truck, due to lot configuration. Maintain a neat and uniform line at the edge of the limits of the scrub seal application. Correct skipped areas or deficiencies.
At the end of each day’s production, provide the CO with documentation of calibrations and application rates.
Remove and dispose of material spills and associated debris at the end of each shift according to Subsection 203.05(a) and (d).
421.10 Aggregate Application. Verify the aggregate stockpile moisture daily and use moist surfaced aggregate.
Calibrate aggregate spreaders before the start of project and as directed by the CO. Calibrate the longitudinal and transverse spread rates.
Apply aggregate uniformly at the optimum application rate determined from the approved control strip. Apply the aggregate immediately after the emulsion is applied and broomed.
Operate the aggregate spreader so emulsion is covered with the aggregate before wheels pass over it. For part-width construction, leave an uncovered 6-inch (150-millimeter) wide emulsion strip to permit an overlap of emulsion.
Cover excess emulsion with blotter to protect traffic.
Correct excesses and deficiencies by adding or removing aggregate to achieve a uniform texture before the emulsion cures.
Operate rollers at a maximum speed of 5 miles (8 kilometers) per hour. Do not allow the aggregate to be displaced by pickup or sticking of material to the tire surface. Roll the surface to uniformly
G-4 DIVISION 700
Project: TX NP MULTI PMS(1), Pavement Preservation Texas
Section 703. — AGGREGATE
07/01/24–FP14
703.09 Chip Seal Aggregate. Delete the title of the Subsection and substitute the following:
703.09 Chip Seal and Scrub Seal Aggregate.
Delete the text of this Subsection and substitute the following:
Furnish hard durable particles or fragments of crushed gravel, crushed stone, crushed slag, or lightweight aggregates. Use only one type of aggregate on the surface treatment. Conform to the following or conform to current Texas Department of Transportation (TxDOT) material specifications for single course polymer asphaltic emulsion seal coat screenings for Grade
4 Aggregate for Chip Seal Type 1C. Use only one type of aggregate on the surface treatment at each park. Do not switch between TxDOT Material specifications and following within one park:
(a) Gradation
(b) Clay lumps and friable particles, AASHTO T 112
(c) Flat and elongated particles, ASTM D4791 (1:3 ratio, plus ⅜-inch (9.5-mm) sieve, calculated by mass, weighted average)
(d) Fractured faces, ASTM D5821
(e) Los Angeles abrasion, AASHTO T 96
(f) Soundness of aggregate using sodium sulfate, AASHTO T 104 (5 cycles)
Table 703-7
1.0 percent max.
10 percent max.
90 percent min.
35 percent max.
12 percent loss max.
Table 703-7
Target Value Ranges for Single and Double Course Chip Seal Aggregate
Gradation
Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation
A B C D Texas
1½ inch (37.5 mm)
1 inch (25 mm) 100(1)
¾ inch (19 mm) 90 – 100 (3) 100(1) 100(1)
½ inch (12.5 mm) 0 – 35 (5) 90 − 100 (3) 100(1) 95 – 100 (3)
⅜ inch (9.5 mm) 0 – 12 (3) 0 – 35 (5) 85 – 100 (3) 100(1) 60 – 80 (5)
No. 4 (4.75 mm) — 0 – 12 (3) 0 – 35 (5) 85 – 100 (3) 2 – 5 (3)
No. 8 (2.36 mm) — − 0 – 8 (3) 0 – 23 (4) 0.0 – 2 (0.5)
No. 200 (75 µm) 0.0 – 1.0 (0.5) 0.0 – 1.0 (0.5) 0.0 – 1.0 (0.5) 0.0 – 1.0 (0.5) –
(1) Statistical procedures do not apply.
( ) The value in the parentheses is the allowable deviations (±) from the target values.
G-4a
Project: TX NP MULTI PMS(1), Pavement Preservation Texas
703.10 Slurry Seal and Micro Surfacing Aggregate. Amend as follows:
(b) Micro surfacing aggregate. Delete the text of this Subsection and substitute the following:
Conform to ISSA A143 and the following or conform to current Texas Department of
Transportation (TxDOT) material specifications for Grade 2 Aggregate for micro surfacing aggregate. Use only one type of aggregate on the surface treatment at each park. Do not switch between TxDOT Material specifications and following within one park:
(1) Gradation Table 703-8
(2) Los Angeles abrasion, AASHTO T 96, Grading D 30 percent max.
(3) Sand equivalent AASHTO T 176, 65 min.
Alternate Method No. 2, Reference Method
(4) Soundness of aggregate using sodium sulfate, 15 percent loss max.
AASHTO T 104 (5 cycles)
Table 703-8
Micro Surfacing and Slurry Seal Aggregate
Gradation
Sieve
Size
Percent by Mass Passing Designated
Sieve (AASHTO T 27 & AASHTO T 11)
Grading Designation
I II III
⅜ inch (9.5 mm) − 100 100
No. 4 (4.75 mm) 100 90 − 100 70 − 90
No. 8 (2.36 mm) 90 – 100 65 − 90 45 − 70
No. 16 (1.18 mm) 65 – 90 45 − 70 28 − 50
No. 30 (600 µm) 40 – 65 30 − 50 19 − 34
No.50 (300 µm) 25 – 42 18 − 30 12 − 25
No. 100 (150 µm) 15 − 30 10 − 21 7 − 18
No. 200 (75 µm) 10.0 − 20.0 5.0 − 15.0 5.0 − 15.0