QA_03-14-2025.pdf

PDF 57 KB Posted

Attached to
ID BOR SRAO 0017(1), Sportsman’s Park Transportation Improvements
Solicitation number
69056724B000017
Issued by

About this file

This document is a Questions and Answers (Q&A) file for the Sportsman's Park Transportation Improvements federal contract opportunity, specifically addressing technical questions related to the solicitation. The document contains one technical question regarding Special Contract Provision 635, which concerns the requirement for a traffic control supervisor on-site during work performance. The government's response clarifies that no separate bid item will be added for the traffic control supervisor, and contractors should consider this cost incidental to the project, referring to FP14 Subsection 109.05 for additional guidance. The Q&A document is dated 3/14/2025 and is associated with Solicitation Number 69056724B000017 from the Department of Transportation Federal Highway Administration.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID BOR SRAO 0017(1)

Sportsman’s Park Transportation Improvements

# General Technical Question Answer Date

1 X

Special contract provision 635 calls out a traffic control supervisor to follow section 156.09 of the FP-14. In the FP-14 it calls for a traffic control supervisor to be on site on daily while work is performed and to be qualified as per FP-

14 section 156.03. Is a bid item going to be added as in previous contracts to pay for that person or is it to be considered incidental to the project?

The Government does not intend to add a

Traffic Control Supervisor pay item. See FP-

14 Subsection 109.05, and please bid accordingly.

3/14/2025